Contract No. CM 04/2024 – Outlying Islands Sewerage Stage 2 – South
Lantau Sewerage Works – Environmental Team Services (2025 - 2027) |
||
|
Quarterly Environmental Monitoring, and
Audit Report for: November to January 2026 Revision 2 |
||
|
|
Certified
By: ______________ Lau Hoi Wai,
Josephine Environmental
Team Leader Report
Date: 24
March 2026 |
|
|
|
|
|
Content:
1.2 Environmental
Monitoring & Audit Programme
1.3 Quarterly
Environmental Monitoring & Audit Report
2. Basic project
Information and Environmental Status
2.3 Works
undertaken during the Reporting quarter
3. Environmental
Monitoring and Audit (“EM&A”) Requirement
3.1 Summary of Monitoring Parameters
3.2 Environmental quality performance
limits (Action and Limit levels); and Results Summary
3.3 Implementation Status of
Environmental Mitigation Measures
3.4 Complaints, Non-Compliance, and
Notification of Summons and Prosecution
4.1 Environmental
Monitoring and Audits
4.2 Implementation
of Environmental Mitigation Measures
Tables:
Table 2.1: Contact Details of Key Personnel
Table 3.1: Summary of Impact EM&A Requirements
Table 3.2: Action and Limit Levels for Noise Monitoring
Table 3.3: Action and Limit Levels for Water Quality
Table 3.4: Summary of Ecological Impact Monitoring
Table 3.5: Summary of
Quantities of Waste Material in the Reporting Quarter
Figures:
Figure
3.1 Locations of Noise Monitoring
Station
Figure
3.2 Locations of Water Quality
Monitoring Station
Appendices:
Appendix
3.1 Noise Monitoring Graphical
Presentations
Appendix
3.2 Waste Material
in the Reporting Quarter
Appendix 4.1 Final Investigation Report
This Quarterly
Environmental Monitoring and Audit (“EM&A”) Report summarises project monitoring, and auditing data, with full
interpretation illustrating the acceptability or otherwise of any environmental
impacts, and identification or assessment of the implementation status of
agreed mitigation measures, including monitoring results, and findings of the
EM&A Programme, along with findings recorded during the site Inspections,
and audits, reports of Complaints, Notifications of Summons, and Successful
Prosecutions, and other necessary observations obtained within this reporting
quarter from 1 November 2025 to 31 January 2026.
Key Construction
Works in the Reporting quarter
San Shek Wan Sewage
Treatment Works (“SSWSTW”)
·
Superstructure Reinforced Concrete (“RC”)
works
·
Waterproofing Work
·
Backfilling work
·
Excavation and Site formation
·
Electrical and Mechanical (“E&M”)
Installation
·
Slope Work
near SSWSTW
Pui O Sewage Pumping
Station (“POSPS”)
·
Excavation, sewer laying, construction of
manhole
·
Excavation and Excavation and Lateral Support (”ELS”) work
·
E&M Installation
Lo Uk Tsuen, Pui O
·
Excavation, sewer laying, construction of
manhole
South Lantau Road
·
Excavation, sewer laying, construction of
manhole
Chi Ma Wan Road
·
Excavation, sewer laying, construction of
manhole
·
Trenchless drilling works
Environmental
Monitoring, and Audit Progress
The EM&A Programme
is implemented in accordance with the EM&A Manual under the EIA Report. A
summary of the monitoring activities during this reporting quarter as below:
|
Monitoring Activity |
Monitoring Date |
||
|
November 2025 |
December 2025 |
January 2026 |
|
|
Noise |
7,
13-15, 18-20 and 25 |
1,
11-12, 18, 23-24 and 30 |
5,
16, 22-23 and 28 |
|
Nursery visit for
transplanted trees |
24 |
15 |
12
and 19 |
|
Site Inspection |
3,
10, 17 and 24 |
1,
8, 15, 23 and 30 |
8,
12, 19 and 26 |
Breaches of Action,
and Limit Levels
Noise Monitoring has been conducted at 8 of
the designated monitoring locations (N12a, N12b, N13, N14, N15b,
N16a, N16b, and N17) where construction works
has been conducted nearby during the reporting month.
Noise limit level exceedance of 75 dB(A) was
recorded at N12a on 24 December 2025. Site observation recorded a breaker
operating at a roadside works site on South Lantau Road during monitoring.
Also, local traffic noise, that comprises of heavy vehicles including trucks and
buses, was observed to be high. As such, the exceedance would be due to
combination of construction works and traffic flow. Hence, it is considered
that the exceedance maybe project-related
Repeat monitoring was conducted on 30
December 2025 due to no construction works during the public holidays on 25–26
December. Corrected noise level of 72dB(A) at N12a was recorded. Site
investigation conducted on 30 December 2025 observed that no beaker was in operation
at the work site. Corresponding remedial actions, including reminding the
Contractor to maintain vigilance over construction noise and implemented proper
construction noise mitigation measures according to EM&A Manual and
Construction Noise Mitigation Plan. And formalizing the mandatory erection of
noise barriers for future concrete breaking activities to prevent the
recurrence of similar incidents. The final investigation report was submitted to
EPD on 30 January 2026, and the final investigation report is given in Appendix
4.1.
Subsequent
to the completion of
marine work on 24 May 2025, water quality monitoring was considered completed
by 30 May 2025. No water quality monitoring is conducted in this reporting
quarter. Should marine works resume, water quality monitoring will be conducted
in accordance with the requirement stipulated in the EM&A Manual
accordingly.
A summary of environmental
exceedances for this reporting quarter is as follows:
|
Environmental
Monitoring |
Parameters |
Action Level |
Limit Level |
|
Noise |
Leq
(30 min) |
0 |
1 |
Ecological Impact
Monitoring
Transplanting of the
trees of Aquilaris sinensis was
completed on 26 April 2022. Maintenance works for trees in holding nursery have
commenced.
4 trees found (1 no.
of Aquilaria sinensis, and 3 nos. of Gmelina chinensis) within
the site of SSWSTW which are considered to be the plant
species with conservative importance for temporarily transplanted to the
nursery at Kam Tin and eventually be transplanted to POSPS.
The weekly site
audit was carried out by ET include checking whether good site practices are
being properly implemented by the Contractor.
The extent of the
work site boundaries was checked by the ET during the weekly site audit.
Complaints,
Notification of Summons and Prosecution
No notification of summons
and successful prosecution regarding construction works were recorded in the
reporting quarter.
Reporting Changes
There are no reporting changes in the
reporting quarter.
1.1.1
The Environmental Protection Department (“EPD”)
completed the Outlying Islands Sewerage Master Plan (“SMP”) Study in 1994 and
drew up a SMP for Lantau Island and other outlying islands. The proposed
sewerage works of the SMP were divided into 2 stages. The Stage 2 Works of the SMP were subsequently
reviewed by EPD under the Outlying Islands Sewerage Master Plan Stage 2 Review
(SMP Review Study) in 2001.
1.1.2
The proposed sewerage works for South Lantau
were further reviewed in 2008 under the Review of Sewerage Scheme for South
Lantau (Review Study). According to the Review Study, the proposed sewerage
works for South Lantau would serve the unsewered areas of Shui Hau, Tong Fuk,
Cheung Sha, San Shek Wan, Pui O and Ham Tin.
1.1.3
The Outlying Islands Sewerage Stage 2 – South Lantau
Sewerage Works, herein referred to as “the Project”, referred to the sewerage
works for South Lantau that would serve the unsewered areas of Shui Hau, Tong
Fuk, Cheung Sha, San Shek Wan, Pui O and Ham Tin.
1.1.4
The Project mainly comprises of the following
items:
a)
Construction of a secondary sewage treatment
works (“STW”) at San Shek Wan in South Lantau;
b)
Construction of sewage pumping station (“SPS”)
at Pui O, San Shek Wan, Cheung Sha, Cheung Fu Street, Shui Hau and Tong Fuk;
c)
Construction of about 1.4km of twin submarine
outfalls with a diameter of 350mm for the disposal of treated effluent from the
STW at San Shek Wan;
d)
Construction of about 10.1km of gravity sewers
with diameters ranging from 150mm to 375mm along South Lantau Road and Chi Ma
Wan Road and at Pui O; and
e)
Construction of about 3.1km of twin rising mains
with a diameter of 200mm to 250mm along South Lantau Road and Chi Ma Wan Road.
1.2.1
An Environmental Impact Assessment (“EIA”) was
subsequently prepared to review the potential environmental impact that would
be due to the Project during its construction works and operational works. The
EIA Report was submitted and approved on 24 April 2017, and Environmental
Permit (“EP”) No. EP-538/2017 was subsequently granted on 13 July 2017.
1.2.2
The EM&A Programme is therefore implemented
in accordance with the EM&A Manual under the EIA Report.
1.2.3
Umwelt Consulting Limited (“UCL”) has been appointed
to work as the Environmental Team (“ET”) under EP No. EP-538/2017 to implement
the EM&A programme as stipulated in the EM&A Manual of the approved EIA
Report for the Outlying Islands Sewerage Stage 2 – South Lantau Sewerage Works
(Register No.: AEIAR-210/2017).
1.3.1
This Quarterly EM&A Report summarises project monitoring
and auditing data, with full interpretation illustrating the acceptability or otherwise
of any environmental impacts and identification or assessment of the
implementation status of agreed mitigation measures, including monitoring
results and findings of the EM&A Programme, along with findings recorded
during the site Inspections and audits, reports of Complaints, Notifications of
Summons and Successful Prosecutions, and other necessary observations obtained
within this reporting quarter form November 2025 to January 2026.
2.1.1
Drainage Services
Department (“DSD”) is the project proponent and the permit holder of the
Project. For the construction phase of the Project, Contractor(s), ET and
Independent Environmental Checker (“IEC”) are appointed to manage and control
environmental issues. Key personnel and contact particulars are summarized in Table 2.1.
2.1.2
Upon conclusion of
Contract No: SD 15/2022 Outlying Island Sewerage Stage 2 – South Lantau Sewage Works
– Environmental Team Services (2023 – 2024), the subsequent contract, Contract
No. CM 04/2024 Outlying Islands Sewerage Stage 2 – South Lantau Sewerage Works
– Environmental Team Services (2025-2027), has been awarded to Umwelt
Consulting Limited (“UCL”)
starting 1 February 2025. As such the environmental team leader (“ETL”)
appointed for the Project has been updated to Mr. Ting Po Chung, Ivan since 1
February 2025. His contact details has been updated in Table 2.1.
2.1.3
There are no other
reporting changes in the reporting quarter.
Table 2.1: Contact
Details of Key Personnel
|
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
|
Drainage Services Department |
The Engineer for the Contract |
Engineer |
Mr. KK Chan |
2594 7297 |
3104 6426 |
|
Binnies Hong Kong Limited |
Engineer’s Representative |
Resident Engineer |
Mr. Kevin Chan |
3529 3003 |
- |
|
Kwan Lee – Chun Wo
Joint Venture |
Contractor |
Sub Agent |
Mr. Daniel Chu |
6737 6701 |
2744 6937 |
|
Environmental Supervisor |
Ms. Joey Pang |
6978 2876 |
|||
|
Environmental Supervisor |
Mr. Philip Wong |
6908 8920 |
|||
|
SMEC Hong Kong |
IEC |
IEC |
Ms. Kitty Lee |
3995 8140 |
3422 3631 |
|
Umwelt Consulting Limited |
ET |
ET Leader |
Mr. Ivan Ting |
3756 9590 |
3582 3310 |
2.2.1
The proposed sewerage
works will collect the sewage generated from the unsewered areas of Shui Hau,
Tong Fuk, Cheung Sha, San Shek Wan, Pui O and Ham Tin in South Lantau (i.e. within
the Project Catchment Area) and convey it to a proposed sewage treatment works
at San Shek Wan for treatment and disposal into outer bay of Pui O / Chi Ma Wan
via a submarine outfall.
2.2.2
The Project was divided into 3 contracts. The current contract, Contract No.
DC/2020/02 - Construction of San Shek Wan Sewage Treatment Works, Associated
Submarine Outfall and Pui O Sewerage Works (“the Contract”) would have the following implementations. The works site of the Contract
is also given in Figure 2.1.
2.2.3
The major components
of the Contract under Environmental Permit (“EP”) (EP No. EP-538/2017)
comprises:
a) Construction of a secondary sewage treatment works
(“STW”) at San Shek Wan in South Lantau;
b) Construction of a sewage pumping station (“SPS”) at
Pui O, San Shek Wan, Cheung Sha and Cheung Fu Street;
c) Construction of about 1.4km of submarine outfall
with a diameter of 350mm for the disposal of treated effluent from the STW at
San Shek Wan;
d) Construction of about 10.1km of gravity sewers with
diameters ranging from 150mm to 375mm along South Lantau Road and Chi Ma Wan road and at Pui O; and
e) Construction of about 3.1km twin rising mains with
a diameter of 200mm to 250mm along South Lantau Road and Chi Ma Wan Road.
2.3.1
In the reporting quarter, the principal work
activities conducted are as follow:
a)
Excavation, Sewer Laying, and Construction of Manhole
a)
Excavation, Sewer Laying, and Construction of Manhole
a)
Excavation, Sewer Laying, and Construction of Manhole
b)
Trenchless drilling works
3.1.1
The EM&A programme requires environmental monitoring, noise
monitoring, water quality monitoring, and ecology as specified in the approved
EM&A Manual.
3.1.2
A summary of Impact EM&A requirements is presented in Table 3.1. The
locations of noise monitoring stations, and water quality monitoring stations are shown in Figure 3.1 and
Figure 3.2 respectively.
Table 3.1: Summary of Impact EM&A Requirements
|
Environmental
Monitoring Aspects |
Parameters and
Unit |
Monitoring Station |
Frequencies |
Remarks |
|
Noise |
Leq (30mins), L10 (30mins)
and L90 (30mins) |
N12a, N12b,
N13, N14, N15b, N16a, N16b, and N17 |
At least once per
week |
Daytime on normal
weekdays (0700-1900 hrs). |
|
Water Quality |
Dissolved Oxygen,
mg/L Temperature, °C Salinity, 0/00 Turbidity, NTU Suspended Solids,
mg/L pH |
CE, CF, SR4,
SR5, SR6, SR9, SR10, SR12, and SR15 |
Three times per week
during mid-ebb, and mid-flood tides |
Samples are
collected at 3 depths (1 m below water, mid-depth, and 1 m above seabed)
shall be collected. Where the water
depth is less than 6 m, in which case the mid-depth station may be omitted. Should the water
depth be less than 3 m, only the mid-depth station will be monitored |
3.2.1
A-weighted equivalent continuous sound pressure level (“Leq”) over a period of 30 minutes Leq (30min) shall
be used as the monitoring parameter for construction noise monitoring.
Supplementary information for data auditing, statistical results such as L10,
and L90 should also be recorded for reference.
3.2.2
For impact monitoring of construction works, noise monitoring should be
undertaken on weekly basis. Six consecutive Leq
(5min) between 07:00-19:00 hours on normal weekdays is taken in this
EM&A Programme.
3.2.3
The Action and Limit Levels for noise monitoring are given as in Table 3.2. No examination was conducted during the reporting quarter.
Table 3.2: Action and Limit Levels for Noise Monitoring
|
Monitoring
Station ID |
Monitoring
Location |
Action Level |
Limit Level |
|
N12a |
Lo Uk Tsuen |
When one documented complaint is received from
any one of the noise sensitive receivers |
75 dB(A) |
|
N12b |
Lo Uk Tsuen |
75 dB(A) |
|
|
N13 |
Pui O San Wai
Tsuen |
75 dB(A) |
|
|
N14 |
South Lantau
Community Centre |
75 dB(A) |
|
|
N15b |
Pui O Lo Wai Tsuen |
75 dB(A) |
|
|
N16a |
Residences at Ham
Tin |
75 dB(A) |
|
|
N16b |
Residences at Ham
Tin |
75 dB(A) |
|
|
N17 |
Bui O Public
School |
70 dB(A) / 65
dB(A) 1 |
Note:
1. The Limit Level for N17 is 70 dB(A) for
being an educational institution. The Limit Level is reduced to 65 dB(A) during
school examination period.
3.2.4
Noise limit level
exceedance of 75 dB(A) was recorded at N12a on 24 December 2025. Site observation
recorded a breaker operating at a roadside works site on South Lantau Road
during monitoring. Also, local traffic noise, that comprises of heavy vehicles
including trucks and buses, was observed to be high. As such, the exceedance
would be due to combination of construction works and traffic flow. Hence, it
is considered that the exceedance maybe project-related
3.2.5
Repeat monitoring
was conducted on 30 December 2025 due to no construction works during the public
holidays on 25–26 December. Corrected noise level of 72dB(A) at N12a was
recorded. Site investigation conducted on 30 December 2025 observed that no
beaker was in operation at the work site. Corresponding remedial actions,
including reminding the Contractor to maintain vigilance over construction
noise and implemented proper construction noise mitigation measures according
to EM&A Manual and Construction Noise Mitigation Plan. And formalizing the mandatory
erection of noise barriers for future concrete breaking activities to prevent
the recurrence of similar incidents. The final investigation report was
submitted to EPD on 30 January 2026, and the final investigation report is
given in Appendix 4.1.
3.2.6
The detailed results and graphical plot for noise monitoring is given in
Appendix 3.1.
Water Quality
Monitoring
Completion of Water Quality
Monitoring
3.2.7
Subsequent to the
completion of marine work on 24 May 2025, water quality monitoring
was considered
completed by 30 May 2025. No water quality monitoring was conducted during the
reporting quarter. Should marine works resume, water quality
monitoring will be conducted in accordance with
the requirement stipulated in the EM&A Manual accordingly.
Ecological Impact
Monitoring
3.2.8
Monitoring in the form of regular site inspections should be carried out
to ensure ecological measures in the form of tree transplantation, and
establishment are being implemented, and effective for plant species of conservation
importance (e.g. Aquilaria sinensis).
3.2.9
Transplanting works for plant species, Aquilaris
sinensis, was completed on 26 April 2022. Maintenance works for trees in
holding nursery have commenced.
3.2.10 Monitoring of maintenance
works for the transplanted plant species was conducted at the holding nursery
while in the reporting period.
3.2.11 As per latest version of
PTP, four tree found (1 no. of Aquilaria sinensis,
and 3 nos. of Gmelina chinensis) within the site of SSWSTW which are considered to be the plant species with conservative
importance for temporarily transplanted to the nursery at Kam Tin and
eventually be transplanted to POSPS.
3.2.12
Within this reporting
period, holding nursery visit for transplanted trees on 24
November, 15 December 2025, 12 and 19 January 2026
3.2.13
No non-compliance was
found during the site inspection while reminders on environmental measures were
recommended. Results and findings of these inspections in this reporting period
are listed below in Table 3.4.
Table 3.4: Summary of Ecological Impact Monitoring
|
Inspection
Date |
Reminder
and Recommendations |
Close-out
Date / Status |
|
24
November 2025 |
Nil |
-- |
|
15
December 2025 |
Nil. |
-- |
|
12
January 2026 |
Nil. |
-- |
|
19
January 2026 |
Nil. |
-- |
3.2.14
The quantities of waste for disposal in
present quarter are summarized in Table 3.5.
Table 3.5: Summary of
Quantities of Waste Material in the Reporting Quarter
|
Waste Type |
Quantity for Reporting Quarter |
Cumulative Quantity-to-Day |
|
Hard Rock and Large Broken Concrete (Inert), in ‘000m3 |
0 |
0 |
|
Reused in this Contract (Inert),in ‘000m3 |
0 |
0 |
|
Reused in other Projects
(Inert), in ‘000m3 |
0 |
0 |
|
Disposal as Public Fill
(Inert), in ‘000m3 |
0.77 |
31.39789 |
|
Metals (in ‘000kg) |
1.16 |
115.14617 |
|
Paper / Cardboard Packing, in
‘000kg |
0.149 |
1.51928 |
|
Plastics in ‘000kg |
0.0096 |
0.12176 |
|
Chemical Waste in ‘000kg |
0 |
0 |
|
General Refuse in ‘000kg |
270.16 |
1353.99 |
Note:
The table is summary
of quantities of waste material of November 2025 to January 2026 period.
3.3.1
The mitigation measures recommended in the
EIA Report has been implemented where applicable. The implemented mitigation
measures for the reporting quarter are listed below:
a)
Prevention of site runoff during heavy rainstorms;
b)
Implementation of noise pollution control in accordance with Construction Noise Mitigation Plan;
c)
Dust control during dust generating works;
d)
Adopt surface drainage and sediment control facilities for sewage installation in village and public roads;
e)
Adopt temporary drainage and sediment control facilities on Site;
f)
Vehicle wheel-washing and body washing facilities should be provided at the site entrance;
g)
Regular water spraying on excavation works for dust control; and
h)
Proper waste handling, recycling and storage.
3.3.2
The implemented mitigation measures are
considered effective.
3.4.1
No environmental complaint was recorded in the
reporting quarter.
3.4.2
The detail of exceedance has been discussed in Section 3.2.4-3.2.5.
3.4.3
No notification of summons and successful
prosecution regarding construction works were recorded in the reporting
quarter.
4.1.1
Environmental monitoring
and audits including Noise, Water Quality, Ecology, and Site audits have been
conducted in the reporting quarter in accordance with the requirement
stipulated in the EM&A Manua.
Noise Monitoring
4.1.2
Noise Monitoring has
been conducted at 8 of the designated monitoring locations where construction works
has been conducted nearby during the reporting period.
4.1.3
Noise limit level
exceedance of 75 dB(A) was recorded at N12a on 24 December 2025. Site observation
recorded a breaker operating at a roadside works site on South Lantau Road
during monitoring. Also, local traffic noise, that comprises of heavy vehicles
including trucks and buses, was observed to be high. As such, the exceedance
would be due to combination of construction works and traffic flow. Hence, it
is considered that the exceedance maybe project-related
4.1.4
Repeat monitoring was
conducted on 30 December 2025 due to no construction works during the public holidays
on 25–26 December. Corrected noise level of 72dB(A) at N12a was recorded. Site
investigation conducted on 30 December 2025 observed that no beaker was in
operation at the work site. Corresponding remedial actions, including reminding
the Contractor to maintain vigilance over construction noise and implemented
proper construction noise mitigation measures according to EM&A Manual and
Construction Noise Mitigation Plan. And formalizing the mandatory erection of
noise barriers for future concrete breaking activities to prevent the
recurrence of similar incidents. The final investigation report was submitted
to EPD on 30 January 2026, and the final investigation report is given in Appendix
4.1
Water Quality Monitoring
4.1.5
Subsequent to the completion of marine
work on 24 May 2025, water quality monitoring was considered completed by 30 May
2025. No water quality monitoring is conducted in this reporting period.
Ecological Impact Monitoring
4.1.6
Transplanting of the trees of Aquilaris
sinensis was completed on 26 April 2022. Maintenance works for trees in
holding nursery have commenced.
4.1.7
As per latest version of PTP, 4 tree found (1
no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within
the site of SSWSTW which are considered to be the plant species with
conservative importance for temporarily transplanted to the nursery at Kam Tin
and eventually be transplanted to Pui O Pumping Station.
4.1.8
The weekly site audit was carried out by ET include checking whether
good site practices are being properly implemented by the Contractor.
4.1.9
The extent of the work site boundaries was checked by the ET during the
weekly site audit.
4.1.10 No
non-compliance was found during the site inspection while reminders on
environmental measures were recommended.
4.2.1
No environmental complaint, notification of summons
and successful prosecution regarding construction works were recorded in the
reporting quarter.
4.3.1
The mitigation measures recommended in the EIA Report has been
implemented where applicable. The implemented mitigation measures are
considered effective.