�

 

 

environmental permit no. ep-538/2017

Outlying Islands Sewerage Stage 2 � South Lantau Sewerage Works

 

 

Contract No. SD 6/2020

Construction of San Shek Wan Sewage Treatment Works, Associated Submarine Outfall and Pui O Sewerage Works �

Environmental Team Services (2021-2022)

 

 

baseline monitoring report

Revision 9.2

�������������������������


 

 

PREPARED FOR:

PREPARED BY:

 

Drainage Services Department

 

 

Lam Environmental Services Limited

 

19/F Remex Centre

42 Wong Chuk Hang Road

Hong Kong

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

CERTIFIED by:



 

�����������������������������������������������

Derek Lo

Environmental Team Leader

 

 

 

DATE:

 

11 August 2022

 

 

 

 


Table of Contents

Executive Summary. 4

1����� Introduction. 8

1.1�� Background. 8

1.2�� Purpose of Baseline Monitoring Report 9

 

2����� NOISE MONITORING.. 10

2.1�� Monitoring Requirements. 10

2.2�� Monitoring Equipment 10

2.3�� Monitoring Locations. 10

2.4�� Monitoring Parameters, Frequency and Duration. 11

2.5�� Monitoring Methodology. 11

2.6�� Results and Observations. 12

2.7�� Action and Limit Levels. 12

 

3����� WATER QUALITY MONITORING.. 14

3.1�� Monitoring Requirements. 14

3.2�� Monitoring Equipment 14

3.3�� Monitoring Locations. 15

3.4�� Monitoring Parameters, Frequency and Duration. 15

3.5�� Monitoring Methodology. 16

3.6�� QA/QC Requirements. 16

3.7�� Results and Observations. 17

3.8�� Action and Limit Levels. 22

 

4����� LANDSCAPE AND VISUAL MONITORING.. 25

4.1�� Objectives. 25

4.2�� Review of the Approved EIA Report 25

4.3�� Review of the Tree Preservation and Removal Proposal 26

4.4�� Baseline Monitoring. 27

 

5����� Revision for inclusion into EM&A Manual 32

 

6����� Comments, Recommendations and Conclusions. 34

 

 

LIST OF FIGURES

Figure 1.0������� Construction Programme

Figure 1.1������� Location of Project Site

Figure 1.2������� Location of Contract Site

Figure 1.3������� Master Layout Plan

 


LIST OF APPENDIXES

Appendix A����� Baseline Monitoring Schedule for Noise and Water Quality Monitoring

Appendix B����� Calibration Certificates of Monitoring Equipment

Appendix C����� Location of Noise Monitoring Stations

Appendix D����� Baseline Noise Monitoring Data

Appendix E����� Location of Water Quality Monitoring Stations

Appendix F����� Baseline Water Quality Monitoring Data and Wind data from Hong Kong Observatory

Appendix G����� Key Plan of Contract Area

Appendix H����� Key Plan of Landscape Resources and Landscape Character Areas

Appendix I������ Landscape Resources and Landscape Character Areas showing on the Revised Layout of Pui O Sewage Pumping Station

Appendix J������ Location of Noise Monitoring Stations and Construction Areas

Appendix K����� Sensitivity Analysis of Control Station Criteria

�����������������������


Executive Summary

i.              This Baseline Monitoring Report is to report baseline findings for the Project of Outlying Islands Sewerage Stage 2 � South Lantau Sewerage Works (Register No. AEIAR-210/2017) (hereinafter �Project�).

ii.             Baseline monitoring for existing landscape and visual condition was conducted on 9 February 2021 to reconfirm the status of Landscape Resources and Landscape Character Areas within works area.

iii.            In accordance with the EM&A Manual, baseline noise monitoring was conducted at sixteen (16) monitoring stations for consecutive 14 days; while, baseline water monitoring was be carried out at nine (9) monitoring stations, three days per week, for at least 4 weeks prior to the commencement of construction works.

iv.           This report presents the findings and information of baseline noise monitoring during the period from 2 March 2021 to 22 April 2021, and those of baseline water quality monitoring during the period from 3 March 2021 to 29 March 2021. No construction activities under the Project were undertaken during the baseline monitoring period.

 

Landscape and Visual Condition

v.            Compared to the findings in the approved EIA report, the status of the LRs and LCAs covered in the works area of Contract No. DC/2020/02 for the Project generally in line with the EIA report. Baseline of other LR and LCA will be supplemented under separate submission(s) to capture the baseline condition of the corresponding part(s) under other contracts when corresponding work areas, detailed project works and landscape design become available for review as per EM&A manual Section 9.

 

Noise Monitoring

vi.           The baseline noise levels established at sixteen (16) monitoring stations are summarized as shown in Table I. Action & Limit levels of baseline noise levels are summarized as shown in Table II.

 

Water Quality Monitoring

vii.          Average results and Action & Limit levels of baseline water quality level at nine (9) stations are summarized as shown in Table III, Table IV, Table V and Table VI.

 

 

 

 

 

 

 

 

 

 

 

 

Table I Summary of Baseline Noise Levels

Monitoring Station ID

Monitoring Station

0700-1900 hrs on normal weekdays

Leq (30min), dB(A)

Average

Range

N01a *

Shui Hau Village

75.5

74.7 � 79.4

N01c *

Shui Hau Village

62.0

58.4 � 71.1

N03a *

Tong Fuk Village

74.9

73.2 � 78.0

N05a *

Residences at Cheung Fu Street

73.9

72.5 � 78.7

N07 *

Government Holiday Bungalows

58.3

54.6 � 71.9

N08 *

Cheung Sha Ha Tsuen

70.0

66.5 � 72.6

N10

Cheung Sha Sheung Tsuen

68.8

65.6 � 88.6

N11b *

San Shek Wan � Ming Garden

72.3

70.6 � 76.3

N12a *

Lo Uk Tsuen

73.3

71.3 � 75.0

N12b *

Lo Uk Tsuen

76.8

75.2 � 86.1

N13 *

Pui O San Wai Tsuen

73.6

70.5 � 77.5

N14

South Lantau Community Centre

62.2

57.3 � 74.3

N15b

Pui O Lo Wai Tsuen

70.7

62.4 � 78.7

N16a *

Residences at Ham Tin

68.1

63.9 � 75.2

N16b *

Residences at Ham Tin

68.5

64.1 � 80.5

N17

Bui O Public School

62.3

58.7 � 66.4

Remark:

Each of daily 30-minute sampling period includes six consecutive Leq (5min) readings.

* Due to free-field measurement, a correction factor of +3 dB(A) is adopted.

 

Table II Summary of Action & Limit Levels of Baseline Noise Levels

Monitoring Station ID

Time Period

Parameter

Action Level

Limit Level

dB(A)

All

0700-1900 hrs on normal weekdays

Leq, 30min

When one documented complaint is received from any one of the noise sensitive receivers

Or

75dB(A) recorded at the monitoring station

70dB(A) for school

And

65dB(A) during examination period

 

 

 

Table III Summary of Baseline Water Quality Monitoring Results

Monitoring Station

DO (mg/L)

DO (mg/L)

Surface and Middle Layer

Bottom Layer

Average

Range

Average

Range

CE

6.5

5.3 - 7.2

6.5

5.6 - 8.2

CF

6.6

5.9 - 7.4

6.4

5.9 - 7.2

SR4

6.4

5.6 - 7.1

6.3

5.8 - 7.5

SR5

6.4

5.8 - 7.2

6.3

5.8 - 7.1

SR6

6.3

5.5 - 7.2

6.4

6.4 - 6.4

SR9

6.5

5.6 - 7.2

6.4

5.5 - 6.9

SR10

6.5

5.8 - 7.3

6.3

6.2 - 6.4

SR12

6.6

5.9 - 7.5

-

-

SR15

6.4

5.7 - 7.9

-

-

Remark: � � � implies monitoring was conducted at middle layer only with respect to corresponding water depth.

 

Table IV Summary of Baseline Water Quality Monitoring Results during Mid-flood Tide

Monitoring Station

Turbidity (NTU)

SS (mg/L)

BOD5 (mg/L)

Average

Range

Average

Range

Average

Range

CE

6.1

1.8 - 14.6

3.9

1.3 - 13.7

1.3

0.6 - 2.9

CF

7.9

2.6 - 22.9

6.4

1.4 - 46.4

1.5

0.7 - 3.6

SR4

8.8

3.1 - 15.0

6.9

2.8 - 21.1

1.5

0.8 - 2.5

SR5

7.0

1.9 - 14.0

5.1

1.3 - 13.4

1.3

0.3 - 2.1

SR6

9.6

3.4 - 29.1

12.1

2.1 � 20.8

1.2

0.7 - 1.7

SR9

7.7

2.0 - 26.1

6.1

1.4 - 29.5

1.3

0.9 - 1.9

SR10

10.8

2.7 - 35.2

9.7

1.7 - 41.7

1.3

0.8 - 2.2

SR12

7.1

2.6 - 17.0

5.3

1.9 - 17.8

1.4

0.7 - 2.6

SR15

9.5

3.6 - 17.7

9.3

2.3 - 44.3

1.5

0.4 - 2.4

 

Table V Summary of Baseline Water Quality Monitoring Results during Mid-flood Tide

Monitoring Station & Depth

Total Inorganic Nitrogen (mg/L)

Unionized Ammonia (mg/L)

E. coli (CFU per 100ml)

Average

Range

Average

Range

Average

Range

CE

0.14

0.01 - 0.25

0.003

0.001 - 0.006

3.4

1.0 - 56.0

CF

0.15

0.01 - 0.25

0.003

0.001 - 0.007

10.6

1.0 - 61.0

SR4

0.13

0.01 - 0.22

0.003

0.001 - 0.006

6.3

1.0 - 135.0

SR5

0.15

0.01 - 0.25

0.003

0.001 - 0.008

3.2

1.0 - 66.5

SR6

0.15

0.01 - 0.24

0.003

0.001 - 0.006

7.7

1.0 - 106.0

SR9

0.14

0.01 - 0.24

0.003

0.001 - 0.007

3.8

1.0 - 61.5

SR10

0.14

0.01 - 0.25

0.002

0.001 - 0.006

3.6

1.0 - 32.5

SR12

0.13

0.01 - 0.23

0.002

0.001 - 0.006

3.0

1.0 - 17.5

SR15

0.14

0.01 - 0.25

0.003

0.001 - 0.006

8.6

1.0 - 48.0

 


Table VI Summary of Action & Limit Level of Baseline Water Quality

Parameters

Action Level

Limit Level

Construction Phase Marine Water Monitoring

DO in mg/L B

Surface and Middle: 5.8 mg/L

Bottom: 5.9 mg/L

Surface and Middle: 4 mg/L

Bottom: 2 mg/L

Turbidity in NTU

(Depth-averaged A) C

14.4 NTU and

20% exceedance of value at any impact station compared with corresponding data from control station D

23.5 NTU and

30% exceedance of value at any impact station compared with corresponding data from control station �D

SS in mg/L

(Depth-averaged  A) C

13.1 mg/L and

20% exceedance of value at any impact station compared with corresponding data from control station D

30.4 mg/L and

30% exceedance of value at any impact station compared with corresponding data from control station �D

Operation Phase Marine Water Monitoring

Dissolved oxygen in mg/L B

Surface and Middle: 5.8 mg/L

Bottom: 5.9 mg/L

Surface and Middle: 4 mg/L

Bottom: 2 mg/L

Turbidity in NTU (Depth-averaged  A) C

14.4 NTU and

20% exceedance of value at any impact station compared with corresponding data from control station D

23.5 NTU and

30% exceedance of value at any impact station compared with corresponding data from control station �D

SS in mg/L (Depth-averaged A) C

13.1 mg/L and

20% exceedance of value at any impact station compared with corresponding data from control station D

30.4 mg/L and

30% exceedance of value at any impact station compared with corresponding data from control station �D

5-day Biochemical Oxygen Demand in mg/L (Depth-averaged  A) C

2.2 mg/L and

20% exceedance of value at any impact station compared with corresponding data from control station D

5 mg/L E

Total Inorganic Nitrogen in mg/L (Depth-averaged  A) C 

0.23 mg/L

0.25 mg/L F

Unionized Ammonia in mg/L (Depth-averaged A) C

0.006 mg/L

0.021 mg/L G

E. coli

in cfu per 100 ml

(Depth-averaged A) C

31.0 cfu per 100 ml L and

20% exceedance of value at any impact station compared with corresponding data from control station D

(i) 61.1 cfu per 100 ml, or 610 cfu/100mL as geometric mean for secondary contact, recreation subzones H

(ii) 61.1 cfu per 100 ml, or 180 cfu/100mL as geometric mean for bathing beach subzones H

Notes (with proposed amendments in AL/LL in underlined text):

A. �Depth-averaged� is calculated by taking the arithmetic means of reading of all three depths.

B.  For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

C.  For SS, turbidity, 5-day Biochemical Oxygen Demand, Total Inorganic Nitrogen, Unionized Ammonia and E. coli, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

D. Action Level and Limit Level with 95%-ile / 99%-ile derived from baseline data �and� 20% / 30% exceedance of control station proposed in Section 5.1.1 justified with the sensitivity analysis of control station criteria detailed in Section 3.8.2.

E. 99%-ile of baseline BOD5 data is 2.7 mg/L, which is considered too close to the proposed action level of 2.2 mg/L. False alarm would be easily triggered if 2.7 mg/L is adopted as limit level. Thus, 5 mg/L of criterion is adopted as limit level.

F. 99%-ile of baseline TIN data is 0.25 mg/L. Owing to and-clause conditions, 0.25 mg/L is adopted as limit level.

G. 99%-ile of baseline UIA data is 0.006 mg/L, which is same as the proposed action level. In order to avoid ambiguity of triggering action and limit level, 0.021 mg/L is adopted as limit level for effective implementation of event and action plan.

H. Referring to Table 4.1 of the EIA report, for secondary contact recreation subzones, the level of Escherichia coli should not exceed 610 per 100 milligrams per litre, calculated as the geometric mean of all samples collected in one calendar year. While, for bathing beach subzones, the level of Escherichia coli should not exceed 180 per 100 milligrams per litre, calculated as the geometric mean of all samples collected from March to October inclusive in one calendar year. Samples should be taken at least 3 times in a calendar month at intervals of between 3 and 14 days.


1              Introduction

 

1.1          Background

1.1.1.     The purpose of this Project is to construct and operate a sewerage system for proper collection, treatment and disposal of the sewage arising from South Lantau, which includes the areas in Shui Hau, Tong Fuk, Cheung Sha, San Shek Wan, Pui O and Ham Tin. Construction programme and Layout of project site is presented in Figure 1.0 and Figure 1.1 respectively.

1.1.2.     The proposed Project would be implemented as follows:

(i)             Village sewerage works: It comprises the provision of village sewerage to unsewered villages of Shui Hau, Tong Fuk, Cheung Sha, San Shek Wan, Pui O and Ham Tin in South Lantau. The works will involve construction of sewers inside villages� alleys, which are then connected into the trunk sewerage system below.

(ii)            Trunk sewerage works: It comprises the construction of trunk sewers, a total of six (6) number of sewage pumping stations and the associated twin rising mains along South Lantau Road for collection and conveyance of sewage from the village sewerage system to the proposed San Shek Wan Sewage Treatment Works (STW).

(iii)           San Shek Wan STW and associated submarine outfall.

1.1.3.     The entire Project are divided into three contracts. Contract No. DC/2020/20 (the Contract) would have the following implementations as demonstrated in Figure 1.2 & Figure 1.3.

(i)             Construction of a secondary sewage treatment works at San Shek Wan in South Lantau;

(ii)            Construction of a sewage pumping station (SPS) at Pui O;

(iii)           Construction of about 1.4 km of submarine outfall with a diameter of 350 mm for disposal of treated effluent from the STW at San Shek Wan;

(iv)          Construction of about 4.1 km of gravity sewers with diameters ranging from 150 mm to 375 mm along South Lantau Road and Chi Ma Wan Road and at Pui O Lo Uk; and

(v)           Construction of about 1.2 km of twin rising mains with a diameter of 200 mm along South Lantau Road and Chi Ma Wan Road.

1.1.4.     Baseline noise and water quality monitoring covers all contract areas in this report; while, baseline condition of landscape resources and landscape character areas only cover the area of Contract No. DC/2020/02. Baseline condition of other LR and LCA under other contracts will be supplemented under separate submission(s).

1.1.5.     In accordance with Condition 3.3 stated in the Environmental Permit (EP-538/2017), four hard copies and one electronic copy of the Baseline Monitoring Report shall be submitted to the Director at least 2 weeks before the commencement of construction of the project.

1.1.6.     In accordance with Section 12.1 of the Project Environmental Monitoring and Audit (EM&A) Manual, the Baseline Environmental Monitoring Report should be prepared and submitted within 10 days of completion of the baseline monitoring.

 

1.2          Purpose of Baseline Monitoring Report

1.2.1.     Baseline monitoring is to review baseline conditions of noise level and water quality along the Project boundary, and to establish baseline levels for noise and water quality in accordance with the EM&A Manual. These levels would be used as the basis for assessing environmental impact and compliance during construction and operation stage of the Project. Baseline conditions of landscape resources and landscape character areas are also reviewed under this report to reconfirm the findings in the approved EIA report (Register No. AEIAR-210/2017).

1.2.2.     This baseline monitoring report presents baseline monitoring requirements, methodologies, monitoring results and determination of action and limit levels for each monitoring parameter at sixteen (16) noise monitoring stations and nine (9) water quality monitoring stations.


2              NOISE MONITORING

 

2.1          Monitoring Requirements

2.1.1       In accordance with the EM&A Manual, baseline noise levels at sixteen (16) monitoring stations shall be measured for a continuous period of at least 14 consecutive days at a minimum logging interval of 30 minutes during daytime between 0700 and 1900 hours.

2.1.2       The baseline noise monitoring at sixteen (16) monitoring stations were conducted in three batches separately during the monitoring period from 2 March 2021 to 22 April 2021 and the relevant findings are summarized in this report. The baseline monitoring schedule is shown in Appendix A.

 

2.2          Monitoring Equipment

2.2.1       Noise monitoring was performed using sound level meter at the designated monitoring location. Sound level meters shall comply with the International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications. Acoustic calibrator shall be deployed to check the sound level meters at a known sound pressure level.� Brand and model of the equipment is given in Table 2.1.

Table 2.1����������� Noise Monitoring Equipment

Equipment

Brand and Model

Series Number

Integrated Sound Level Meter

Larson Davis LxT

4797

6307

6344

6345

6346

6357

Acoustic Calibrator

Larson Davis Cal 200

13437

 

2.2.2       Calibration certificates of the noise monitoring equipment are attached in Appendix B.

 

2.3          Monitoring Locations

2.3.1       In order to prevent from potential disturbances to others and facilitate noise monitoring works, fine adjusted monitoring location was therefore proposed. The fine adjusted noise monitoring stations for baseline noise monitoring are presented in Table 2.2 and shown in Appendix C.

Table 2.2����������� Baseline Noise Monitoring Stations

 

Monitoring Station ID (1)

Monitoring Location

Measurement Type

Level

(in terms of

no. of floor)

N01a

Shui Hau Village

Free-Field

G/F

N01c

Shui Hau Village

Free-Field

G/F

N03a

Tong Fuk Village

Free-Field

G/F

N05a

Residences at Cheung Fu Street

Free-Field

G/F

N07

Government Holiday Bungalows

Free-Field

G/F

N08

Cheung Sha Ha Tsuen

Free-Field

G/F

N10

Cheung Sha Sheung Tsuen

Fa蓷de

G/F

N11b

San Shek Wan � Ming Garden

Free-Field

G/F

N12a

Lo Uk Tsuen

Free-Field

G/F

N12b

Lo Uk Tsuen

Free-Field

G/F

N13

Pui O San Wai Tsuen

Free-Field

G/F

N14

South Lantau Community Centre

Fa蓷de

G/F

N15b

Pui O Lo Wai Tsuen

Fa蓷de

G/F

N16a

Residences at Ham Tin

Free-Field

G/F

N16b

Residences at Ham Tin

Free-Field

G/F

N17

Bui O Public School

Fa蓷de

R/F

Remarks (1): Fine adjustment of noise monitoring stations at all locations was proposed as per EP Condition 3.1.

2.4          Monitoring Parameters, Frequency and Duration

 

2.4.1       Monitoring parameters, frequency and duration of noise monitoring are summarized in Table 2.3.

Table 2.3����������� Baseline Noise Monitoring Parameters, Frequency and Duration

Monitoring

Period

Duration

Measurement Parameter

Measurement Period

Frequency

Baseline Monitoring

Continuous period of at least 14 consecutive days

A-weighted levels Leq, L10 and L90

Including 30 minutes (six consecutive Leq(5min) readings)

Between 0700 and 1900 hours

Daily

 

2.5          Monitoring Methodology

 

2.5.1       Monitoring Procedure

(a)           Fa蓷de and free-field measurements were made at corresponding monitoring locations. For free-field measurement, a correction factor of +3 dB (A) would be applied.

(b)           The battery condition was checked to ensure the correct functioning of the meter.

(c)           Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:

(i)       Frequency weighting: A time weighting: Fast

(ii)      Time measurement: Daily measurement of A-weighted levels Leq, L10 and L90 shall be conducted for a continuous period of at least 14 consecutive days at a minimum logging interval of 30 minutes. Daily measurement periods should be between 0700 and 1900 hours (six consecutive Leq(5min) readings).

(d)           Prior and after to the noise measurement, the meter was checked using the acoustic calibrator for 94dB (A) at 1000 Hz. If the difference in the calibration level before and after measurement was more than �1.0dB(A), the measurement would be considered invalid and repeat of noise measurement would be required after re-calibration or repair of the equipment.

2.5.2       Maintenance and Calibration

(a)           The microphone head of the sound level meter was cleaned with soft cloth at regular intervals.

(b)           The sound level meter and calibrator were calibrated at yearly intervals.

 

2.6          Results and Observations

 

2.6.1       Baseline noise monitoring was carried out from 2 March 2021 to 22 April 2021 in three batches for recording two-week monitoring data and the weather were mostly fine and cloudy. During the baseline monitoring period, no construction activities were observed. The major noise source was traffic noise and community noise near the monitoring station.

2.6.2       The baseline noise monitoring results are summarized in Table 2.4 respectively. Detailed noise monitoring results are presented in Appendix D.

Table 2.4 ���������� Summary of Baseline Noise Monitoring Results

Monitoring Station

0700-1900 hrs on normal weekdays

Leq (30min), dB(A)

Average

Range

N01a *

75.5

74.7 � 79.4

N01c *

62.0

58.4 � 71.1

N03a *

74.9

73.2 � 78.0

N05a *

73.9

72.5 � 78.7

N07 *

58.3

54.6 � 71.9

N08 *

70.0

66.5 � 72.6

N10

68.8

65.6 � 88.6

N11b *

72.3

70.6 � 76.3

N12a *

73.3

71.3 � 75.0

N12b *

76.8

75.2 � 86.1

N13 *

73.6

70.5 � 77.5

N14

62.2

57.3 � 74.3

N15b

70.7

62.4 � 78.7

N16a *

68.1

63.9 � 75.2

N16b *

68.5

64.1 � 80.5

N17

62.3

58.7 � 66.4

Remark:

Each of daily 30-minute sampling period includes six consecutive Leq (5min) readings.

* Due to free-field measurement, a correction factor of +3 dB(A) is adopted.

 

2.7          Action and Limit Levels

 

2.7.1       Action and Limit Levels of noise monitoring have been set in accordance with the criteria specified in the EM&A Manual as shown in Table 2.5 below.

 

 

 

Table 2.5 ���������� Action and Limit Levels for Construction Noise

 

Monitoring Station

Action Level

Limit Level

All

When one documented complaint is received from any one of the noise sensitive receivers

Or

75dB(A) recorded at the monitoring station

70 dB(A) for school

And

65dB(A) during examination period


3              WATER QUALITY MONITORING

 

3.1          Monitoring Requirements

 

3.1.1       In accordance with the Project EM&A Manual, the measurements shall be taken at all designated monitoring stations including control stations, for three times a week at mid-ebb and mid-flood tides for 4 consecutive weeks during prior to the commencement of the construction works. The interval between 2 sets of monitoring should not be less than 36 hours. Replicate in-situ measures should be carried out in each sampling event. The levels of dissolved oxygen (DO), turbidity, salinity and pH shall be measured in situ, while suspended solids (SS), 5-day biochemical oxygen demand (BOD5), total inorganic nitrogen (TIN), unionized ammonia (UIA) and E.coli shall be determined by laboratory analysis at all the designated monitoring stations. Water samples shall be extracted at 1m below surface, 1m above seabed and at the mid-depth level at where the water depth is at least 6m. If the water depth is less than 3m, water samples shall only be collected at the mid-depth level. For stations with depth less than 6m, the mid-depth sample can be omitted.

3.1.2       The baseline water quality monitoring was conducted during the baseline monitoring period from 3 March 2021 to 29 March 2021 and the relevant findings are summarized in this report. The baseline monitoring schedule is shown in Appendix A.

 

3.2          Monitoring Equipment

 

3.2.1       The baseline water quality monitoring was performed using Multifunctional Meter and Turbid Meter at each designated monitoring station. They are capable of measuring:

(a)           a dissolved oxygen level in the range of 0-20mg/L and 0-200% saturation (Detection Limit: 0.1mg/L)

(b)           a temperature of 0-45 degree Celsius (Detection Limit: 0.1 degree Celsius)

(c)           turbidity level between 0-1000NTU (Detection Limit: 0.1NTU)

(d)           salinity in the range of 0-40ppt (Detection Limit: 0.1ppt)

(e)           pH value in range of 0.0 � 14.0 (Detection Limit: 0.1units)

 

Other monitoring equipment namely water depth meter, water current meter, dGPS positioning device, water sampler listed below were also deployed,

(a)           Water depth meter (Range: 0.6 -100m, Resolution: 0.1m)

(b)           Water current meter (Range: 0-360o, Detection Limit: 1mm/s)

(c)           dGPS positioning device (Resolution: Horizontal: 0.25m; Vertical: 0.50 m )

(d)           Water sampler (Horizontal discrete type, Capacity: 2.2L)

 

3.2.2       Brand and model of the equipment are given in Table 3.1.

 

���������� Table 3.1������������������������������������������������� Water Quality Monitoring Equipment

 

Equipment

Brand and model

�������������� Series Number

Multifunctional Meter

Sonde YSI Professional Plus

17F100236

Turbid meter

Xin Rui WGZ-3B

1807079

 

3.2.3       Calibration certificates of the water quality monitoring equipment are attached in Appendix B.

 

3.3          Monitoring Locations

 

3.3.1       Water quality monitoring stations for baseline water quality monitoring are presented in Table 3.2 and shown in Appendix E.

 

� Table 3.2����� Details of Baseline Water Quality Monitoring Stations

Station

Description

Easting

Northing

CE

Upstream control station at ebb tide

810900

807690

CF

Upstream control station at flood tide

815720

807980

SR4 (1)

Ecological Sensitive Receiver (Coral Communities) at Pui O Wan

814938

810975

SR5

Ecological Sensitive Receiver (Coral Communities) at Pui O Wan

814326

810540

SR6

Gazetted Bathing Beach at Lower Cheung Sha

810553

810475

SR9 (1)

Ecological Important Stream at Tong Fuk

811325

809787

SR10

Secondary Contact Recreational Zones at South Lantau

810561

809494

SR12 (1)

Proposed Special Site of Scientific Interest (SSSI) at Shui Hau Wan

810359

808989

SR15

Gazetted Bathing Beach at Pui O and Ecologically Important Stream at Pui O

816037

810722

Remarks (1): Fine adjustment of water quality monitoring stations at SR4, SR9 and SR12 was proposed as per EP Condition 3.1, and baseline monitoring was conducted at corresponding fine adjusted locations.

 

3.4          Monitoring Parameters, Frequency and Duration

3.4.1       Monitoring parameters, frequency and duration of water quality monitoring are summarized in Table 3.3.

 

3.4.2       The levels of DO, temperature, turbidity and salinity shall be measured in situ while SS, BOD5, TIN, UIA and E.coli shall be determined by laboratory analysis at all the designated monitoring stations.

 

3.4.3       In association with the water quality parameters, other relevant data shall also be recorded, such as monitoring location / position, time, pH, DO saturation, weather conditions, and any special phenomena underway near the monitoring station.

 

Table 3.3 Water Quality Monitoring Parameters and Frequency

Monitoring Period

Duration

Sampling Parameter

Frequency

Remarks

Baseline

Monitoring

at least 4 weeks prior to the commencement of construction works

DO, temperature, turbidity, salinity, SS, BOD5, TIN, UIA and E.coli

three days per

week

Duplicate samples for in-situ measurements and laboratory analysis

3.5          Monitoring Methodology

3.5.1       Monitoring Procedure

 

(a)           The condition near the monitoring stations shall be observed and recorded on the data log sheet.

(b)           Check of sensors and electrodes with certified standard solutions before each use.

(c)           Wet bulb calibration for a DO meter should be carried out before measurement.

(d)           Water depth should be recorded by detector before sampling.

(e)           Sample would be taken using water sampler at surface, middle and bottom level.

(f)            Transfer the sampled water carefully into cleaned water bottles provided by the laboratory at the spot after the collection of the water sample for the subsequent laboratory testing of SS, BOD5, TIN, UIA and E.coli.

(g)           Transfer the sampled water from the bucket sampler to the rinsed water container for in-situ measurement (In case of the in-situ measurement cannot be carried at spot due to safety and adverse weather condition, sampled water will be transfer to cleaned water bottles provided by laboratory. Then, In-situ measurement will be conducted at a safe location which sampled water inside cleaned water bottle will be transfer to the rinsed water container for in-situ measurement) In-situ measurement shall be measured in duplicate.

(h)           Parameters including Water Temperature (℃ ), pH (units), Salinity (ppt), DO (mg/L), DO saturation (%) will be measured by the Multifunctional Meter and Turbidity (NTU) will be measured by turbid meter.

(i)             Record the result on the data log sheet and record any special finding during / after in-situ measurement.

(j)             The water sample bottles will store in a cool box, which shall be delivered to HOKLAS laboratory for further testing to determine the level of SS, BOD5, TIN, UIA and E.coli.

3.6          QA/QC Requirements

3.6.1       Maintenance and Calibration

(a)           The responses of sensors and electrodes of the water quality monitoring equipment were cleaned and checked at regular intervals.

(b)           DO meter (Multifunctional Meter) and turbid meter was certified by a laboratory accredited under HOKLAS or any other international accreditation scheme, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring as per Section 3.2.7 in Appendix-D2: General Technical Requirements of Environmental Monitoring of Guidelines for Development Projects in Hong Kong and typical EM&A requirements of current projects with water quality monitoring (e.g. Expansion of Hong Kong International Airport into a Three-Runway System, Tung Chung New Town Extension), which recommended 3 monthly intervals calibration.

3.6.2       Decontamination Procedures

Water sampling equipment used during the course of the monitoring programme was decontaminated by manual washing and rinsed clean seawater/distilled water after each sampling event. All disposable equipment was discarded after sampling.

 

3.6.3       Laboratory measurement

Analysis of SS, BOD5, TIN, UIA and E.coli. will be conducted by a HOKLAS accredited laboratory, which is ALS Technichem (HK) Pty. Ltd.

 

3.6.4       Quality Control Measures implemented by ALS Technichem (HK) Pty. Ltd

(a)           Reporting limit of SS, BOD5, TIN, UIA and E.coli. are 1.0 mg/L, 0.1 mg/L, 0.01 mg/L, 0.001mg/L and 1.0 CFU per 100ml, respectively.

(b)           Water samples were collected and stored in appropriate sampling bottles. All procedures in testing of the water samples were in accordance with our standard procedures as set in QA/QC procedures of the HOKLAS laboratory.

(c)           QC samples comprise those which monitor and control the laboratory performance namely Laboratory Control Sample (LCS), Duplicate Control Sample (DCS), Method Blanks and those which are used for data assessment and the evaluation of matrix effects by using Surrogates, Matrix Spike (MS), Matrix Spike Duplicate (MSD) and Sample Duplicates.

(d)           Quality control samples such as Laboratory Blanks and Quality Control Sample, and/or Certified Reference Materials (CRM) are run at a frequency of 1 in 20 per 'lot' of samples. Sample Duplicates and Matrix Spikes are run at a frequency of 1 in 20 or 1 per batch, whichever is more frequent.

3.7          Results and Observations

3.7.1       The baseline water quality monitoring was carried out from 3 March 2021 to 29 March 2021 and the weather was mostly fine and sometimes cloudy. Representative photos of the site condition during baseline monitoring are shown in Table 3.7. During the baseline monitoring period, no construction activities were observed.

3.7.2       The baseline water quality monitoring results are summarized in Table 3.4, Table 3.5 and Table 3.6. Detailed water quality monitoring results and record of wind data from Hong Kong Observatory are presented in Appendix F.

 

Table 3.4 Summary of Baseline DO Monitoring Results

Monitoring Station

DO (mg/L)

DO (mg/L)

Surface and Middle Layer

Bottom Layer

Average

Range

Average

Range

CE

6.5

5.3 - 7.2

6.5

5.6 - 8.2

CF

6.6

5.9 - 7.4

6.4

5.9 - 7.2

SR4

6.4

5.6 - 7.1

6.3

5.8 - 7.5

SR5

6.4

5.8 - 7.2

6.3

5.8 - 7.1

SR6

6.3

5.5 - 7.2

6.4

6.4 - 6.4

SR9

6.5

5.6 - 7.2

6.4

5.5 - 6.9

SR10

6.5

5.8 - 7.3

6.3

6.2 - 6.4

SR12

6.6

5.9 - 7.5

-

-

SR15

6.4

5.7 - 7.9

-

-

Remark: � � � implies monitoring was conducted at middle layer only with respect to corresponding water depth.

 


Table 3.5 Summary of Baseline Turbidity, SS & BOD5 Monitoring Results

Monitoring Station

Turbidity (NTU)

SS (mg/L)

BOD5 (mg/L)

Average

Range

Average

Range

Average

Range

CE

6.1

1.8 - 14.6

3.9

1.3 - 13.7

1.3

0.6 - 2.9

CF

7.9

2.6 - 22.9

6.4

1.4 - 46.4

1.5

0.7 - 3.6

SR4

8.8

3.1 - 15.0

6.9

2.8 - 21.1

1.5

0.8 - 2.5

SR5

7.0

1.9 - 14.0

5.1

1.3 - 13.4

1.3

0.3 - 2.1

SR6

9.6

3.4 - 29.1

12.1

2.1 - 20.8

1.2

0.7 - 1.7

SR9

7.7

2.0 - 26.1

6.1

1.4 - 29.5

1.3

0.9 - 1.9

SR10

10.8

2.7 - 35.2

9.7

1.7 - 41.7

1.3

0.8 - 2.2

SR12

7.1

2.6 - 17.0

5.3

1.9 - 17.8

1.4

0.7 - 2.6

SR15

9.5

3.6 - 17.7

9.3

2.3 - 44.3

1.5

0.4 - 2.4

 

Table 3.6 Summary of Baseline TIN, UIA & E. Coli Monitoring Results

Monitoring Station & Depth

Total Inorganic Nitrogen (mg/L)

Unionized Ammonia (mg/L)

E. coli (CFU per 100ml)

Average

Range

Average

Range

Average

Range

CE

0.14

0.01 - 0.25

0.003

0.001 - 0.006

3.4

1.0 - 56.0

CF

0.15

0.01 - 0.25

0.003

0.001 - 0.007

10.6

1.0 - 61.0

SR4

0.13

0.01 - 0.22

0.003

0.001 - 0.006

6.3

1.0 - 135.0

SR5

0.15

0.01 - 0.25

0.003

0.001 - 0.008

3.2

1.0 - 66.5

SR6

0.15

0.01 - 0.24

0.003

0.001 - 0.006

7.7

1.0 - 106.0

SR9

0.14

0.01 - 0.24

0.003

0.001 - 0.007

3.8

1.0 - 61.5

SR10

0.14

0.01 - 0.25

0.002

0.001 - 0.006

3.6

1.0 - 32.5

SR12

0.13

0.01 - 0.23

0.002

0.001 - 0.006

3.0

1.0 - 17.5

SR15

0.14

0.01 - 0.25

0.003

0.001 - 0.006

8.6

1.0 - 48.0

 

Table 3.7 - Photographic view of the water quality monitoring stations

Station

Site condition during baseline monitoring

CE

09/03/2021

 

CF

03/03/2021

 

SR4

05/03/2021

 

SR5

05/03/2021

 

SR6

05/03/2021

 

SR9

05/03/2021

 

SR10

05/03/2021

 

SR12

09/03/2021

 

SR15

03/03/2021

 

 

3.7.3       Reviewing the monitoring results, one highest value in suspended solid (SR6 at 134.9mg/L) and two highest values in E.coli. (135cfu/100ml at SR4, 106cfu/100ml at SR6) were reviewed.

3.7.4       Checked the baseline monitoring results, suspended solid at 134.9mg/L of SR6 subject to abnormal turbulence resulting in higher bottom SS captured during the baseline monitoring is considered as outliner and discarded in Action and Limit Level calculation.

3.7.5       For the two extraordinary high values in E.coli., 135cfu/100ml at SR4 could be due to SR4 is located at the downstream of 2 streams surrounding the existing San Shek Wan Village where only old septic system is available without sewerage system such that occasional domestic effluent discharge from upstream could be captured on some baseline monitoring days, whereas 106cfu/100ml at SR6 could be due to the absence of sewerage system for existing Lower Cheung Sha public village as well as the presence of nearby septic system of the existing Lower Cheung Sha Public Toilet on coastal landside of SR6.� Under this situation, occasions of high values in E.coli. from upstream source that captured during the baseline monitoring shall not be discarded.


3.8          Action and Limit Levels

3.8.1       Action and Limit Levels of water quality monitoring have been set with reference to the criteria in the EM&A Manual as shown in Table 3.8 below.

Table 3.8��������������������� Action and Limit Levels for Water Quality

Parameters

Action Level

Limit Level

Construction Phase Marine Water Monitoring

DO in mg/L

Surface and Middle

5%-ile of baseline data for surface and middle layer

Bottom

5%-ile of baseline data for bottom layers

Surface and Middle

4 mg/L

 

Bottom

2 mg/L

Turbidity in NTU

(Depth-averaged a) c

95%-ile of baseline data, or

20% exceedance of value at any impact station compared with corresponding data from control station

99%-ile of baseline data, or

30% exceedance of value at any impact station compared with corresponding data from control station

SS in mg/L

(Depth-averaged  a) c

95%-ile of baseline data, or

20% exceedance of value at any impact station compared with corresponding data from control station

99%-ile of baseline data, or

30% exceedance of value at any impact station compared with corresponding data from control station

Operation Phase Marine Water Monitoring

Dissolved oxygen in mg/L b

Surface and Middle

5%-ile of baseline data for surface and middle layer

Bottom

5%-ile of baseline data for bottom layers

Surface and Middle

4 mg/L

 

 Bottom

2 mg/L

Turbidity in NTU (Depth-averaged  a) c

 

95%-ile of baseline data, or

20% exceedance of value at any impact station compared with corresponding data from control station

99%-ile of baseline data, or

30% exceedance of value at any impact station compared with corresponding data from control station

SS in mg/L (Depth-averaged  a) c

 

95%-ile of baseline data, or

20% exceedance of value at any impact station compared with corresponding data from control station

99%-ile of baseline data, or

30% exceedance of value at any impact station compared with corresponding data from control station

5-day Biochemical Oxygen Demand in mg/L (Depth-averaged  a) c

95%-ile of baseline data, or

20% exceedance of value at any impact station compared with corresponding data from control station

99%-ile of baseline data, or

5 mg/L

Total Inorganic Nitrogen in mg/L (Depth-averaged  a) c 

95%-ile of baseline data

99%-ile of baseline data, and

0.1 mg/L

Unionized Ammonia in mg/L (Depth-averaged  a) c

95%-ile of baseline data

 

99%-ile of baseline data, or

0.021 mg/L

E. coli

in cfu per 100 ml

(Depth-averaged  a) c

 

95%-ile of baseline data, or

20% exceedance of value at any impact station compared with corresponding data from control station

 

(i) 99 %-ile of baseline or 610 cfu/100mL as geometric mean for secondary contact, recreation subzones

(ii) 99 %-ile of baseline or 180 cfu/100mL as geometric mean for bathing beach subzones.

Notes:

a. �Depth-averaged� is calculated by taking the arithmetic means of reading of all three depths.

b.  For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

c.  For SS, turbidity, 5-day Biochemical Oxygen Demand, Total Inorganic Nitrogen, Unionized Ammonia and E. coli, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

 

3.8.2       With the use of baseline water quality monitoring data, the action and limit level for impact stations (i.e. SR4, SR5, SR6, SR9, SR10, SR12 and SR15) are derived.as presented in Table 3.9. �Action Level and Limit Level with 95-ile / 99-ile were derived from baseline water quality data �and� 20% / 30% exceedance of control station would be proposed in Section 5.1.1 based on the sensitivity analysis of control station criteria presented in Appendix K which revealed the following,

a)     In the sensitivity analysis, the 20% / 30% exceedance of control station criteria required for the water quality parameters turbidity, SS, BOD5 and E. coli. were derived and compared with percentiles of these parameters for testing its sensitivity with the baseline monitoring data.

b)     On applying �OR� criteria, sensitivity analysis revealed that the 20% / 30% exceedance would result in daily exceedances on turbidity and SS at various impact stations with substantial percentage of non-project related exceedance anticipated (up to 64.3% for turbidity and up to 73.8% for SS) even under the baseline water quality condition as compared with the 95%-ile / 99%-ile derived with within 5% of exceedance reported.

c)     Similar situation was also noted in the reported exceedance on BOD5 and E. coli. at various impact stations with substantial numbers of non-project related exceedance anticipated (up to 26.2% for BOD5 and up to 28.6% for E. coli.) even under the baseline water quality condition reported within the monthly monitoring period as compared with the 95-ile / 99-ile derived with is within 5% of exceedance reported.

d)     On applying �OR� criteria, the 20% / 30% exceedance of control station criteria would make in the derived Action/Limit Levels (ALs/LLs) over-sensitive and ineffective in monitoring the water quality impact for both construction and operation phases due to percentage of non-project related exceedance anticipated.� Adopting �AND� approach with 95%-ile / 99%-ile in the ALs/LLs could counter-balance the over-sensitivity effect as reflected from similar percentage at around 5% of exceedance anticipated.

e)     In order to eliminate such over-sensitivity and the substantial numbers non-project related exceedances reported impairing the effectiveness of the EM&A programme, it is proposed to amend "OR" to "AND" for the AL/LL of turbidity and SS, AL of BOD5 and AL of E.coli respectively as referred to Note D of Table 3.9.

3.8.3       LLs of BOD5, TIN and UIA - the justifications for the proposed amendments to the LLs are provided in Notes E, F and G of Table 3.9.

 


Table 3.9 Derived Action and Limit levels

Parameters

Action Level

Limit Level

Construction Phase Marine Water Monitoring

DO in mg/L B

Surface and Middle: 5.8 mg/L

Bottom: 5.9 mg/L

Surface and Middle: 4 mg/L

Bottom: 2 mg/L

Turbidity in NTU

(Depth-averaged A) C

14.4 NTU and

20% exceedance of value at any impact station compared with corresponding data from control station D

23.5 NTU and

30% exceedance of value at any impact station compared with corresponding data from control station �D

SS in mg/L

(Depth-averaged  A) C

13.1 mg/L and

20% exceedance of value at any impact station compared with corresponding data from control station D

30.4 mg/L and

30% exceedance of value at any impact station compared with corresponding data from control station �D

Operation Phase Marine Water Monitoring

Dissolved oxygen in mg/L B

Surface and Middle: 5.8 mg/L

Bottom: 5.9 mg/L

Surface and Middle: 4 mg/L

Bottom: 2 mg/L

Turbidity in NTU (Depth-averaged  A) C

14.4 NTU and

20% exceedance of value at any impact station compared with corresponding data from control station D

23.5 NTU and

30% exceedance of value at any impact station compared with corresponding data from control station �D

SS in mg/L (Depth-averaged A) C

13.1 mg/L and

20% exceedance of value at any impact station compared with corresponding data from control station D

30.4 mg/L and

30% exceedance of value at any impact station compared with corresponding data from control station �D

5-day Biochemical Oxygen Demand in mg/L (Depth-averaged  A) C

2.2 mg/L and

20% exceedance of value at any impact station compared with corresponding data from control station D

5 mg/L E

Total Inorganic Nitrogen in mg/L (Depth-averaged  A) C 

0.23 mg/L

0.25 mg/L F

Unionized Ammonia in mg/L (Depth-averaged A) C

0.006 mg/L

0.021 mg/L G

E. coli

in cfu per 100 ml

(Depth-averaged A) C

31.0 cfu per 100 ml L and

20% exceedance of value at any impact station compared with corresponding data from control station D

(i) 61.1 cfu per 100 ml, or 610 cfu/100mL as geometric mean for secondary contact, recreation subzones H

(ii) 61.1 cfu per 100 ml, or 180 cfu/100mL as geometric mean for bathing beach subzones H

Notes (with proposed amendments in AL/LL in underlined text):

A. �Depth-averaged� is calculated by taking the arithmetic means of reading of all three depths.

B.  For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

C.  For SS, turbidity, 5-day Biochemical Oxygen Demand, Total Inorganic Nitrogen, Unionized Ammonia and E. coli, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

D. Action Level and Limit Level with 95%-ile / 99%-ile derived from baseline data �and� 20% / 30% exceedance of control station proposed in Section 5.1.1 justified with the sensitivity analysis of control station criteria detailed in Section 3.8.2.

E. 99%-ile of baseline BOD5 data is 2.7 mg/L, which is considered too close to the proposed action level of 2.2 mg/L. False alarm would be easily triggered if 2.7 mg/L is adopted as limit level. Thus, 5 mg/L of criterion is adopted as limit level.

F. 99%-ile of baseline TIN data is 0.25 mg/L. Owing to and-clause conditions, 0.25 mg/L is adopted as limit level.

G. 99%-ile of baseline UIA data is 0.006 mg/L, which is same as the proposed action level. In order to avoid ambiguity of triggering action and limit level, 0.021 mg/L is adopted as limit level for effective implementation of event and action plan.

H. Referring to Table 4.1 of the EIA report, for secondary contact recreation subzones, the level of Escherichia coli should not exceed 610 per 100 milligrams per litre, calculated as the geometric mean of all samples collected in one calendar year. While, for bathing beach subzones, the level of Escherichia coli should not exceed 180 per 100 milligrams per litre, calculated as the geometric mean of all samples collected from March to October inclusive in one calendar year. Samples should be taken at least 3 times in a calendar month at intervals of between 3 and 14 days.


4              LANDSCAPE AND VISUAL MONITORING

 

4.1          Objectives

 

4.1.1       In accordance with Section 9 of EM&A Manual under the approved EIA report (Register No. AEIAR-210/2017) requirement, a baseline monitoring report shall be prepared to check, record and re-confirm the status of the Landscape Resources (LR) and Landscape Character Areas (LCA) within the works area. The report shall review the proposed mitigation measures and assess their feasibility with reference to the operational requirements of the detailed project works. Any potential conflicts between proposed mitigation measures and the proposed works shall be resolved at an early stage (prior to construction) and any necessary changes to the mitigation measures shall be incorporated into the detailed design.

4.2          Review of the Approved EIA Report

 

4.2.1       The approved EIA Report (Register No. EIA-210/2017) � Outlying Islands Sewerage Stage 2 � South Lantau Sewerage Works has been reviewed to extract relevant information about the baseline conditions of the LRs and LCAs within and immediately adjacent to, the construction and works areas during the EIA stage.

4.2.2       At the EIA stage, three LRs were identified within the Project site which was identified as Woodland (LR1), Plantation (LR3) and Urban/ Village Area (LR5). Two LCAs were identified as South Lantau Coastal Uplands and Hillsides (LCA1) and South Lantau Coastal Settled Valleys (LCA2) Description of the baseline conditions of the above three LRs and two LCAs in approved EIA report are as follows:

-               LR1 � Woodland: This LR consists of large areas of trees growing mainly on the upland and hillside areas, but also some areas closer to the shore at lower elevations.  These woodlands vary in maturity and have a canopy height ranging between 5-12 m on average.  Species vary in different areas but are dominated by a mixture of native pioneer species including Schefflera heptaphylla, Sapium sebiferum, Claoxylon indicum, Zanthoxylum avicennae, backshore species including Hibiscus tiliaeceus and Pandanus tectorius. This LR also includes some relatively old woodland behind Shui Hau, Tong Fuk, Ham Tin and Pui O villages, in which woodlands behind Shui Hau and Tong Fuk are recognised as Fung Shui woodland by AFCD (Figures 5.4a-m), giving it high local significance.  Species in these areas include Aquilaria sinensis, Schefflera heptaphylla, Ficus variegata, Cinnamomum camphora and Aporusa dioica.   Whilst this LR is common in Hong Kong, it is of high conservation value due to its naturalness and undisturbed nature, and some areas are protected as they fall inside the Lantau South Country Park and Green Belt.  This LR is thus of high local importance and high quality.  Overall this LR is relatively intolerant to change and its sensitivity is high.

-               LR3 � Plantation: This LR contains planted trees and is largely located along roadsides, within and around developed areas and above catch water although there is also a large area east of San Shek Wan and Pui O Wan from the coast up to the catch water of the Lantau Trail. Most trees in this LR are exotic species, including Acacia confusa, Casuarina equisetifolia and Pinus elliotii. This LR is common in Hong Kong, and those areas that are protected as Lantau South Country Park, Green Belt and Coastal Protection Areas are considered to be of conservation value. This is an LR planted by man and despite its tall canopy the plantation is considered relatively immature and of medium quality, and its overall sensitivity is medium.

-               LR5 � Urban/ Village Area: This LR includes the villages of Shui Hau, Tong Fok, Cheung Sha, San Shek Wan, Pui O and Ham Tin as well as the penal institution at Tong Fuk and large areas of modified landscape such as that near the junction of the new Tung Chung Road with South Lantau Road. It also includes South Lantau Road itself and the new and old Tung Chung Roads as well as the cemented landing site at Tong Fuk and the road leading down to this. This LR is mainly modified but has some vegetation including village trees and private amenity planting which, along with the traditional village houses and ancestral halls also found within this LR, are vulnerable to the change. This LR is common in Hong Kong and of low conservation value. Overall this LR has limited greening, is low to medium quality and has a reasonable tolerance to change. Its overall sensitivity is considered medium.

-               LCA1 � South Lantau Coastal Uplands and Hillsides: This LCA comprises uplands and hillsides adjacent to the coast between the Lo Kei Wan and Chi Ma Wan peninsulas, predominantly lying below 300 mPD and going down to sea level in some areas. There are almost no built forms in this LCA, which is highly vegetated by relatively mature scrubland, woodland and some patches of plantation. Whilst this LCA is common in Hong Kong, it is of high conservation value due to its naturalness and undisturbed nature, and some areas are protected as they fall inside the Lantau South Country Park and Green Belt. This LCA is of high quality with limited ability to accommodate change and its sensitivity is considered to be high.

-               LCA2 � South Lantau Coastal Settled Valley: This LCA is composed of valleys where they meet the sea mainly around river or stream estuaries. It is populated by scattered low-rise villages and buildings with easy access to the sea and generally has low-lying topography. This LCA has significant human settlement i.e. is developed, but also has significant vegetation including some woodland and plantation of varying maturity, as well as small areas of agricultural lands and marsh. This LCA is common in Hong Kong, and those areas that are protected as Lantau South Country Park, Green Belt and Coastal Protection Areas are considered to be of conservation value. This LCA is considered to be of medium quality due to the amount of development it contains which makes it adaptable to change and its sensitivity is considered to be medium.

4.2.3       As illustrated in Fig. 1.2, LR3, LR5 and LCA2 are potentially affected by Pui O Sewage Pumping Station (POSPS); LR1, LR5 and LCA2 are potentially affected by San Shek Wan Sewage Treatment Works (SSWSTW) and LR5 is potentially affected by pipe works under this Contract. The estimated total affected areas are in line with Table 10.3 of EIA report.

4.3          Review of the Tree Preservation and Removal Proposal

 

4.3.1       Tree Preservation and Removal Proposal (TPRP) for the project of Outlying Islands Sewerage Stage 2 � South Lantau Sewerage Works and Other Works � Design and Construction dated March 2020 was approved. The approval TPRP has been reviewed to extract relevant information about the baseline conditions of relevant landscape resources of the area covering Pui O Sewage Pumping Station (POSPS), San Shek Wan Sewage Treatment Works (SSWSTW) and Pui O Lo Uk Tsuen.

-               Section 8.1.1 - A total of 362 tree specimens including 10 exotic species (91 trees), 32 local species (247 trees) and 24 dead trees were identified and surveyed at the proposed site of SSWSTW, POSPS and Pui O Lo Uk Tsuen. Because of provisioning of space for building SSWSTW and POSPS and the limited space for compensatory trees, a total of 276 (36 trees at POSPS, 238 trees at SSWSTW and 2 trees at Lo Uk Tsuen) trees within the project area have been recommended for felling under Package 1. 80 trees are retained (60 trees at POSPS and 20 trees at Pui O Lo Uk Tsuen) and 6 trees will be transplanted (4 trees at SSWSTW and 2 trees at POSPS).

-               Section 8.1.2 - The compensatory planting of a ratio similar to 1:1 in terms of number, i.e. total 276 trees will be implemented on-site to compensate for the loss of trees in Package 1 commencing in end-2020 for completion in end-2026.

4.3.2       The updated tree survey was carried out from 6 July 2021 to 30 August 2021 and 14 January 2022. The total no. of trees was 574 are recorded within the Project site and 397 trees are affected based on the refined design of the San Shek Wan Sewage Treatment Works and roadworks taking into account the actual topographic situation and future operational needs. The nos. of affected trees in LR3 and LR5 at POSPS is 115 and 281 trees in LR1 and LR5 at SSWSTW and 1 tree in LR5 at pipe works are affected. The additional affected trees will be covered in revised TPRP and details of mitigation will be elaborated in Landscape Mitigation Plan to be submitted as per condition 2.14 of EP-538/2017.

4.4          Baseline Monitoring

 

4.4.1       Baseline monitoring for the existing landscape condition was conducted on 9 February 2021. During the baseline monitoring, LR and LCA covered within works areas in Contract No. DC/2020/02 (the Contract) have been conducted. Location of the Project Site is shown in Appendix G.

4.4.2       LR1 � Woodland: Trees species in San Shek Wan Sewage Treatment Works (SSWSTW) include mixture of native pioneer species including Schefflera heptaphylla, Sapium sebiferum, Claoxylon indicum, Zanthoxylum avicennae. The dominant species are Acacia confusa. Aporusa dioica and Alangium chinense. In addition, 3 nos. of Gmelina chinensis and 2 nos. of Aquilaria sinensis are identified within the proposed boundary of SSWSTW which is rare and precious plant. The condition of LR1 is consistent with the baseline conditions described in Section 10.6.4 and 10.6.6 of the approved EIA report. Photographic view of the existing conditions of LR1 as shown in Table 4.1.

4.4.3       LR3 � Plantation: Planted trees were observed along roadsides, within and around developed areas in the area of San Shek Wan and Pui O Wan. Exotic species were found, including Acacia confusa, Casuarina equisetifolia and Pinus elliotii. In Pui O Sewage Pumping Station (POSPS) the dominant species are Celtis sinensis and Acacia confusa while in SSWSTW the dominant species are Acacia confusa and Pinus massoniana. The condition of LR3 is consistent with the baseline conditions described in Section 10.6.4 and 10.6.6 of the approved EIA report. Photographic view of the existing conditions of LR3 as shown in Table 4.1.

4.4.4       LR5 � Urban/ Village Area: Low-density villages of San Shek Wan and Pui O were observed near South Lantau Road. Vegetation, including village trees and private amenity planting, was found along with traditional village houses and ancestral halls. The condition of LR5 is generally similar with the baseline conditions described in Section 10.6.4 of the approved EIA report. Photographic view of the existing conditions of LR5 as shown in Table 4.1.

4.4.5       LCA1 � South Lantau Coastal Uplands and Hillsides: Uplands and hillsides were observed with highly vegetated by relatively mature scrubland, woodland and patches of plantation. Naturalness and undisturbed nature of the Lantau South Country Park and Green Belt placed high conservation value. The condition of LCA1 is consistent with the baseline conditions described in Section 10.6.3 of the approved EIA report. Photographic view of the existing conditions of LCA1 as shown in Table 4.1.

4.4.6       LCA2 � South Lantau Coastal Settled Valley: Scattered low-rise villages and buildings with easy access to the sea on a low-lying terrain were observed. Woodland with plantation of varying maturity, small areas of agricultural lands and marsh were also found in Lantau South Country Park, Green Belt and Coastal Protection Areas. The dominant backshore species in POSPS are Excoecaria agallocha, Thespesia populnea and Pandanus tectorius.The condition of LCA2 is generally similar with the baseline conditions described in Section 10.6.3 and 10.6.6 of the approved EIA report. Photographic view of the existing conditions of LCA2 as shown in Table 4.1.

4.4.7       The photographic record and monitoring results are shown in Table 4.1. Key plan showing the location and extent of existing landscape and visual resource is shown in Appendix H. Compared to the findings in the approved EIA report, the status of the LRs and LCAs covered in SSWSTW and pipe works remain unchanged; while the updated LR and LCA plans for the revised layout of POSPS is shown in Appendix I. And trees will be transplanted and compensated according to the approved TPRP. Since there is no major change in the landscape and visual baseline conditions comparing to those of the EIA stage, additional landscape and visual mitigation measures would be subjected to revised TPRP, if any. Details of mitigation measure will be covered in Landscape Mitigation Plan.

4.4.8       Baseline of other LR and LCA will be supplemented under separate submission(s) to capture the baseline condition of the corresponding part(s) under other contracts when corresponding work areas, detailed project works and landscape design become available for review as per EM&A manual Section 9.


Table 4.1 Baseline Result for Landscape Resources (LR) and Landscape Character Areas (LCA)

Existing Landscape Resources within Works Area

Photographic Record

LCA1 � South Lantau Coastal Uplands and Hillsides

LCA2 � South Lantau Coastal Settled Valley

LR1 � Woodland

04/01/2022

 

LR3 � Plantation

LR5 � Urban/ Village Area

 

 

 


 

5Revision for inclusion into EM&A Manual

 

5.1.1       Reveiwing the sensitivity analysis of control station criteria as referred to Section 3.8.2, the application of 20% / 30% exceedance of control station criteria alone would make in the derived Action/Limit Levels (ALs/LLs) over-sensitive and ineffective in monitoring the water quality impact for both construction and operation phases.� Adopting the �and� approach with 95%-ile / 99%-ile in the ALs/LLs could counter-balance the over-sensitivity effect.� In order to eliminate such over-sensitivity and the substantial numbers non-project related exceedances reported impairing the effectiveness of the EM&A programme, it is proposed to amend "or" to "and" for the AL/LL of turbidity and SS, AL of BOD5 and AL of E.coli respectively.

5.1.2       Standard method of APHA 2540E was mentioned in Table 5.2 of the EM&A Manual for testing suspended solid (SS); whereas, the APHA 2540E method is for testing volatile and fixed suspended solids rather than total suspended solid. Thus, the standard method of APHA 2540D for testing total suspended solid should be employed in Table 5.2 of the EM&A Manual.

5.1.3       In view of the above method update, reporting limit of SS in Table 5.2 of the EM&A Manual was reviewed. According to baseline water quality monitoring data, the vast majority of SS concentration is equal to or larger than 2 mg/L, only with around 7% of data ranging below 2 mg/L. Increase in reporting limit from 1 mg/L to 2 mg/L would not greatly influence the accuracy of SS result and implementation of event and action plan against action and limit levels. In addition, the reporting limit of 2 mg/L has been adopted in the project of Expansion of Hong Kong International Airport into a Three-Runway System. In light of precedent case, adoption of 2 mg/L as SS reporting limit in monitoring during construction phase and operational phase is proposed in Table 5.2 of the EM&A Manual.

5.1.4       Due to insufficient water for sampling and safety issue associated with hard rocks and shallow water, water quality monitoring stations of SR4, SR9 an SR12 were proposed to be fine adjusted as per EP Condition 3.1, and baseline water quality monitoring was conducted at the fine adjusted location accordingly. The proposal of fine adjustment of water quality monitoring stations was submitted in a separate proposal for EPD�s approval. In light of valid data as checked, the mentioned stations presented in Appendix E should be followed in the future monitoring during construction and operation phase under EM&A programme.

5.1.5       Baseline water quality monitoring was carried out in 4-week period which could not account for all site conditions under seasonal variation in particular the safety concern in marine navigation during windy conditions due to monsoon in winter (i.e. dry season) or weather conditions with typhoons/thunderstorm in summer (i.e. wet season) outside baseline monitoring period.� Safety consideration for conducting water sample �surrounding water quality monitoring station� are considered essential and necessary to allow minor adjustment on proposed monitoring locations for impact monitoring.

5.1.6       Reviewing the 3 monthly intervals throughout all stages of the water quality monitoring as per Section 3.2.7 in Appendix-D2: General Technical Requirements of Environmental Monitoring of Guidelines for Development Projects in Hong Kong and typical EM&A requirements of current projects with water quality monitoring (e.g. Expansion of Hong Kong International Airport into a Three-Runway System, Tung Chung New Town Extension), 3 monthly intervals calibration is proposed as re-calibration frequency for water quality monitoring.

5.1.7       With reference to Appendix C, fine adjusted noise monitoring locations as proposed per EP Condition 3.1 are suggested in Figure 4.1 to Figure 4.8 of the EM&A manual. The proposal of fine adjustment of noise monitoring stations was submitted in a separate proposal for EPD�s approval. It is also recommended that the noise and water quality monitoring station condition should be regularly reviewed and fine adjustment or relocation may be needed in order to obtain respective impact monitoring results.

5.1.8       Regarding Section 4.1.3 of the EM&A Manual, one set of Leq(15min) noise as three consecutive Leq(5min) shall be monitored during impact monitoring. However, since construction noise during night time and restricted hour is regulated under Construction Noise Permit (CNP) system rather than actual numerical criteria as per Table 1B of Annex 5 under Technical Memorandum on Environmental Impact Assessment Process. Hence, impact noise monitoring in restricted hours is suggested to be erased in the EM&A Manual, and implementation of CNP will be checked and audited during construction phase instead.

 


6              Comments, Recommendations and Conclusions

 

Water Quality

6.1.1       Baseline water quality monitoring was conducted at the dry season due to tight schedule of commencement of the Project. To account for more representative baseline water quality to cover the wet season and seasonal variations, it is recommended that baseline conditions should be reviewed quarterly when appropriate, through review the monitoring effectiveness and improve the EM&A programme as per Section 12.3(m) under the EM&A Manual for IEC verification.

6.1.2       Monitoring works shall not be conducted during adverse weather, including strong monsoon signal, tsunami warning, thunderstorm warning, amber / red / black rainstorm signal, tropical cyclone warning signal No. 3 or higher, in order to ensure personnel safety and avoid acquisition of unrepresentative data and subsequent false alarm.

 

Noise sources

6.1.3       The works area of Contract No. DC/2020/02 covers part of the assessment area (i.e. San Shek Wan and Pui O) of the Outlying Islands Sewerage Stage 2 � South Lantau Sewerage Works. Construction impact monitoring for the Contract will be at most conducted at Fine Adjusted N12a, Fine Adjusted N12b, Fine Adjusted N13, Fine Adjusted N15b, Fine Adjusted N16a, Fine Adjusted N16b and Fine Adjusted N17, because the above monitoring stations are located within a radius of 300m from contract-related works areas as illustrated in Appendix J. The above monitoring stations are expected representative for the works area of the Contract. Since contract-related construction activities would be carried out phase by phase, impact noise monitoring will be conducted at designated stations only when the activities fall within a radius of 300m from corresponding monitoring stations, according to Section 4.1.2 of the EM&A Manual.

6.1.4       For Fine Adjusted N14 (South Lantau Community Centre), during site visit on 9 Feb 2021 the door of the facility was observed broken and the facility was seemed vacant. The facility is considered abandoned. According to the Outline Zoning Plan and desktop study, there was no record for planning application and revitalization plan of South Lantau Community Centre. Thus, N14 does not consider as noise sensitive receiver, and impact noise monitoring for N14 would not be necessary unless occupants are observed in the future.

6.1.5       Baseline noise monitoring was conducted prior to commencement of construction works. During baseline monitoring period, no construction activities were observed. The major noise source was traffic noise and community noise nearby monitoring station. It is possible that same noise sources would be identified during impact monitoring period. It is recommended that noise monitoring station condition should be regularly reviewed when appropriate, and fine adjustment or relocation may be needed in order to obtain respective impact monitoring results.

 

Landscape and Visual

6.1.6       Although there is no major change in the landscape baseline conditions comparing to those presented in the EIA report and the TPRP, it is recommended to review landscape and visual mitigation measures regularly to ensure sufficient protection against project implementation.

 

Conclusion

 

6.1.7       In accordance with the Project EM&A Manual and EP, baseline monitoring has been undertaken prior to commencement of the construction works of the Contract for the following baseline monitoring components: Noise; Water Quality and Landscape.

6.1.8       As mentioned under Appendix C and Appendix E, several fine adjustments of locations were proposed for baseline noise and water quality monitoring. Nevertheless, given the fine adjusted location with similar pollution sources and similar condition to the original locations recommended in the EM&A manual, it is considered to be representative for the noise and water sensitive receiver identified in EM&A manual.�

6.1.9       Baseline noise monitoring was conducted at sixteen (16) monitoring stations in three batches from 2 March 2021 to 22 April 2021. The major noise sources identified at the monitoring station are traffic noise and community noise. The baseline monitoring results are considered representative of the ambient noise level.

6.1.10    Baseline water quality monitoring was conducted at nine (9) monitoring stations from 3 March to 29 March 2021. No observable pollution source was recorded at the monitoring stations and the baseline monitoring results are thus considered representative of the ambient water quality levels. Action and Limit Levels were established for parameters based on the baseline monitoring results.

6.1.11    Baseline monitoring for existing landscape and visual condition was conducted on 9 February 2021. The status of the LRs and LCAs covered in the works area of Contract No. DC/2020/02 generally in line with the approved EIA report. Baseline of other LR and LCA will be supplemented under separate submission(s) to capture the baseline condition of the corresponding part(s) under other contracts when corresponding work areas, detailed project works and landscape design become available for review as per EM&A manual Section 9.


 

 

 

 

 

������������������������������������������������������� Figure 1.0

 

Construction Programme

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Figure 1.1

�����������

Location of Project Site

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Figure 1.2

 

Location of Contract Site

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Figure 1.3����������������������

 

Master Layout Plan

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix A

Baseline Monitoring Schedule for

Noise and Water Quality Monitoring

 


 

Appendix B

Calibration Certificates of Monitoring Equipment

 


 

Appendix C

Location of Noise Monitoring Stations

 


 

Appendix D

Baseline Noise Monitoring Data

 


 

Appendix E

Location of Water Quality Monitoring Stations

 


 

Appendix F

Baseline Water Quality Monitoring Data and Wind data from Hong Kong Observatory

 


 

Appendix G

Key Plan of Contract Area

 


 

Appendix H

Key Plan of Landscape Resources and Landscape Character Areas

 

 

 


 

Appendix I

Landscape Resources and Landscape Character Areas showing on the Revised Layout of Proposed Pui O Sewage Pumping Station

 

Appendix J

Location of Noise Monitoring Locations and Construction Areas

 


 

Appendix K

Sensitivity Analysis of Control Station Criteria