Contract No. CM 04/2024 – Outlying Islands Sewerage Stage 2 – South
Lantau Sewerage Works – Environmental Team Services (2025 - 2027) |
||
|
Annual Environmental Monitoring, and Audit Report for: February
2025 to January 2026 Revision 5 |
||
|
|
Certified
By: ______________ Lau Hoi Wai,
Josephine Environmental
Team Leader Report
Date: 23
June 2026 |
|
|
|
|
|
Content:
1.2 Environmental
Monitoring & Audit Programme
1.3 Annual Environmental Monitoring & Audit Report
2. Basic project
Information and Environmental Status
2.3 Works
undertaken during the Reporting Period
3. Environmental
Monitoring and Audit (“EM&A”) Requirement
3.1 Summary of Monitoring Parameters
3.2 Environmental quality performance
limits (Action and Limit levels); and Results Summary
3.3 Implementation Status of
Environmental Mitigation Measures
3.4 Complaints, Non-Compliance, and
Notification of Summons and Prosecution
4.1 Environmental
Monitoring and Audits
4.2 Complaints,
Notification of Summons and Prosecution
4.3 Implementation
of Environmental Mitigation Measures
Tables:
Table 2.1 Contact Details of Key Personnel
Table 2.2 Summary of submission status under EP-538/2017
Table 3.1: Summary of Impact
EM&A Requirements
Table 3.2 Action and Limit Levels for Noise Monitoring
Table 3.4 Action and Limit Levels Level for Water Quality Monitoring
Table 3.7 Summary of Ecological Impact Monitoring
Table 3.9 Summary of Complaints in the Report Period
Figures:
Figure 2.1 Project Organization Chart
Figure
3.1 Locations of Noise Monitoring
Station
Figure
3.2 Locations of Water Quality
Monitoring Station
Appendices:
Appendix 3.1 Noise
Monitoring Graphical Presentations
Appendix
3.2 Final Investigation Report- Noise
exceedance on 24 December 2025
Appendix
3.3 Marine Water
Quality Monitoring Graphical and Summary of Exceedance Presentations
Appendix
3.4 Final Investigation Report- Water
Quality exceedance on May 2025
Appendix
3.5 Waste Material
in the reporting period
Appendix
3.6 Final Investigation Report- Oil
sheen complaint on 16 September 2025
Appendix
4.1 Implementation Schedule of Recommended Mitigation
Measures
This Annual Environmental Monitoring and Audit (“EM&A”)
Report summarises project monitoring, and auditing data, with full
interpretation illustrating the acceptability or otherwise of any environmental
impacts, and identification or assessment of the implementation status of
agreed mitigation measures, including monitoring results, and findings of the
EM&A Programme, along with findings recorded during the site Inspections,
and audits, reports of Complaints, Notifications of Summons, and Successful
Prosecutions, and other necessary observations obtained within this reporting period from 1 February 2025 to 31 January 2026.
Key Construction
Works in the Reporting Period
San Shek Wan Sewage Treatment
Works (“SSWSTW”)
·
Superstructure Reinforced Concrete (“RC”) works
·
Waterproofing Work
·
Excavation and Site formation
·
Retaining wall construction
·
Dredging and diffuser construction
·
Backfilling Work
·
Electrical and Mechanical (“E&M”) Installation
·
Slope Work along the Slope near SSWSTW
Pui O Sewage Pumping
Station (“POSPS”)
·
Excavation, sewer laying, construction of
manhole
·
Excavation and Excavation and Lateral Support (”ELS”) work
·
E&M
Installation
·
Architectural Builders Works and Finishes Work
(“ABWF”)
Lo Uk Tsuen,
Pui O
·
Excavation, sewer laying, construction of
manhole
South Lantau Road
·
Excavation, sewer laying, construction of
manhole
Chi Ma Wan Road
·
Excavation, sewer laying, construction of
manhole
·
Trenchless drilling works
Environmental Monitoring, and Audit Progress
The
EM&A Programme is implemented in accordance with the EM&A Manual under
the EIA Report. A summary of the monitoring activities during this
reporting period as below:
|
Monitoring Date/ Monitoring Activity |
Noise |
Water Quality |
Nursery visit for
transplanted trees |
Site Inspection |
|
February
2025 |
7,
15, 19-20 and 25 |
1,
4, 6, 8, 11, 13, 15, 18, 20, 22, 25 and 27 |
24 |
5,
12, 17, 24 |
|
March
2025 |
3-4,
15, 17, 21-22 and 27-28 |
1,
4, 6, 8, 11, 13, 15, 18, 20, 22, 25, 27, and 29 |
24 |
3,
10, 17, 24, and 31 |
|
April
2025 |
2-3,
8-9, 15-16, 22, and 28 |
1,
3, 5, 8, 10, 12, 15, 17, 22, 24, 26, and 29 |
23 |
7,
14, 23, and 28 |
|
May
2025 |
10,
16, 22 and 28 |
3,
6, 8, 10, 13, 15, 17, 20, 22, 24, 27 and 29 |
27 |
7,
12, 19 and 27 |
|
June
2025 |
3,
9, 20, 26 and 30 |
N/A |
30 |
2,
9, 16, 23 and 30 |
|
July
2025 |
11,
18-19, 24 and 30 |
N/A |
28 |
7,
14, 21 and 28 |
|
August
2025 |
7-8,
11, 22 and 28 |
N/A |
27 |
4,
11, 18 and 27 |
|
September
2025 |
3-4,
9-10, 15-16 and 25-26 |
N/A |
22 |
1,
9, 15, 22 and 30 |
|
October
2025 |
6,
9-10, 14-15, 23 and 31 |
N/A |
20 |
6,
13, 20 and 27 |
|
November
2025 |
7,
12, 18-20 and 25 |
N/A |
24 |
3,
10, 17 and 24 |
|
December
2025 |
1,
11-12, 18, 23-24 and 30 |
N/A |
15 |
1,
8, 15, 23 and 30 |
|
January
2026 |
5,
16, 22-23 and 28 |
N/A |
12
and 19 |
8,
12, 19 and 26 |
Breaches of Action, and Limit Levels
Noise Monitoring
Noise Monitoring has been conducted at 8 of
the designated monitoring locations (N12a, N12b, N13, N14, N15b, N16a, N16b,
and N17) where construction works has been conducted nearby during the
reporting month. Noise limit level exceedance of 75 dB(A) was recorded at N12a
on 24 December 2025. Site observation recorded a breaker operating at a
roadside works site on South Lantau Road during monitoring. Also, local traffic
noise, that comprises of heavy vehicles including trucks and buses, was
observed to be high. As such, the exceedance would be due to combination of
construction works and traffic flow. Hence, it is considered that the
exceedance maybe project-related.
Repeat monitoring was conducted on 30
December 2025 due to no construction works during the public holidays on 25–26
December. Corrected noise level of 72dB(A) at N12a was recorded. Site investigation
conducted on 30 December 2025 observed that no beaker was in operation at the
work site. Corresponding remedial actions, including reminding the Contractor
to maintain vigilance over construction noise and implemented proper
construction noise mitigation measures according to EM&A Manual and
Construction Noise Mitigation Plan. And formalizing the mandatory erection of
noise barriers for future concrete breaking activities to prevent the recurrence
of similar incidents. The Investigation report was submitted to EPD by 30
January 2026
Water Quality Monitoring
Action level exceedance was record for
dissolved oxygen on 17 to 29 May 2025. Investigations were conducted and site
investigation was conducted on 30 May 2025.
Marine works were completed on 24 May 2025.
The silt curtain was removed and cutting of casing on the same day in
accordance with the site curation deployment plan. No other marine works were
conducted in May 2025.
As the exceedances would be due to natural
fluctuation, and the marine works have been completed. Hence, the water quality
monitoring was not extended in spite of the exceedance
recorded on 29 May 2025.
Subsequent
to the completion of
marine work on 24 May 2025, water quality monitoring was considered completed
by 30 May 2025. No water quality monitoring is conducted in this reporting period. Should marine works resume, water quality monitoring
will be conducted in accordance with the requirement stipulated in the EM&A
Manual accordingly.
A summary of
environmental exceedances for this reporting period is as follows:
|
Environmental
Monitoring |
Parameters |
Action Level |
Limit Level |
|
Noise |
Leq
(30 min) |
0 |
1 |
|
Water
Quality |
Suspended
solids level (“SS”) |
0 |
0 |
|
Turbidity
level |
0 |
0 |
|
|
Dissolved
oxygen level (“DO”) |
24 |
0 |
Ecological Impact
Monitoring
Transplanting of the
trees of Aquilaris sinensis was completed
on 26 April 2022. Maintenance works for trees in holding nursery have
commenced.
4 trees found (1 no.
of Aquilaria sinensis, and 3 nos. of Gmelina chinensis) within
the site of SSWSTW which are considered to be the
plant species with conservative importance for temporarily transplanted to the
nursery at Kam Tin and eventually be transplanted to POSPS.
The weekly site
audit was carried out by ET include checking whether good site practices are
being properly implemented by the Contractor.
The extent of the
work site boundaries was checked by the ET during the weekly site audit.
Complaints,
Notification of Summons and Prosecution
On 16 September 2025, the received complaint
was related to a reported oil sheen observed in the wetland area near Pui O
Wetland, Lantau Island. On 25 September 2025, additional information from EPD
was received that oil signs spotted in the Pui O. Subsequent investigations
have been conducted.
An unannounced inspection conducted by ET on 17
September 2025, joint site investigation conducted by ET and the Contractor on
18 September 2025, and a joint site investigation conducted by ET, EPD, and the
Contractor on 25 September 2025, and the subsequent site inspection conducted
with ET, and Contractor on the same day.
Preliminary findings showed that the diesel
drum stored within the Project Sites were stored properly with no leakage or
spillage. No oil signs within the project sites were found during the inspections
conducted throughout the period of complaint investigation. Also, locations of
the identified oil sheen are not within proximity of the Project Site.
The Final Investigation Report was submitted
to EPD on 17 October 2025. Given that there is no evidence of oil leakage
within our project site, it is considered that the oil pollution was not caused
by our site operations. As such, the case is considered closed.
No notification of summons and successful prosecution
regarding construction works were recorded in the reporting period.
Reporting Changes
Upon conclusion of Contract No: SD 15/2022
Outlying Island Sewerage Stage 2 – South Lantau Sewage Works –
Environmental Team Services (2023 – 2024),
the subsequent contract, Contract No. CM 04/2024 Outlying Islands
Sewerage Stage 2 – South Lantau Sewerage
Works – Environmental Team Services (2025-2027), has been
awarded to Umwelt Consulting Limited (“UCL”) starting
1 February 2025. As such the environmental team leader
(“ETL”) appointed for the Project has been
updated to Mr. Ting Po Chung, Ivan since 1 February 2025. His contact
details has been
updated in Table 2.1.
1.1.1
The Environmental Protection Department (“EPD”)
completed the Outlying Islands Sewerage Master Plan (“SMP”) Study in 1994 and
drew up a SMP for Lantau Island and other outlying islands. The proposed
sewerage works of the SMP were divided into 2 stages. The Stage 2 Works of the SMP were
subsequently reviewed by EPD under the Outlying Islands Sewerage Master Plan
Stage 2 Review (SMP Review Study) in 2001.
1.1.2
The proposed sewerage works for South Lantau
were further reviewed in 2008 under the Review of Sewerage Scheme for South
Lantau (Review Study). According to the Review Study, the proposed sewerage
works for South Lantau would serve the unsewered areas of Shui Hau, Tong Fuk,
Cheung Sha, San Shek Wan, Pui O and Ham Tin.
1.1.3
The Outlying Islands Sewerage Stage 2 – South
Lantau Sewerage Works, herein referred to as “the Project”, referred to the
sewerage works for South Lantau that would serve the unsewered areas of Shui
Hau, Tong Fuk, Cheung Sha, San Shek Wan, Pui O and Ham Tin.
1.1.4
The Project mainly comprises of the following
items:
a)
Construction of a secondary sewage treatment
works (“STW”) at San Shek Wan in South Lantau;
b)
Construction of sewage pumping station (“SPS”)
at Pui O, San Shek Wan, Cheung Sha, Cheung Fu Street, Shui Hau and Tong Fuk;
c)
Construction of about 1.4km of twin submarine
outfalls with a diameter of 350mm for the disposal of treated effluent from the
STW at San Shek Wan;
d)
Construction of about 10.1km of gravity sewers
with diameters ranging from 150mm to 375mm along South Lantau Road and Chi Ma
Wan Road and at Pui O; and
e)
Construction of about 3.1km of twin rising mains
with a diameter of 200mm to 250mm along South Lantau Road and Chi Ma Wan Road.
1.2.1
An Environmental Impact Assessment (“EIA”) was
subsequently prepared to review the potential environmental impact that would
be due to the Project during its construction works and operational works. The
EIA Report was submitted and approved on 24 April 2017, and Environmental
Permit (“EP”) No. EP-538/2017 was subsequently granted on 13 July 2017.
1.2.2
The EM&A Programme is therefore implemented
in accordance with the EM&A Manual under the EIA Report.
1.2.3
Umwelt Consulting Limited (“UCL”) has been
appointed to work as the Environmental Team (“ET”) under EP No. EP-538/2017 to
implement the EM&A programme as stipulated in the EM&A Manual of the
approved EIA Report for the Outlying Islands Sewerage Stage 2 – South Lantau
Sewerage Works (Register No.: AEIAR-210/2017).
1.3.1
This Annual EM&A Report summarises project monitoring
and auditing data, with full interpretation illustrating the acceptability or otherwise
of any environmental impacts and identification or assessment of the
implementation status of agreed mitigation measures, including monitoring
results and findings of the EM&A Programme, along with findings recorded
during the site Inspections and audits, reports of Complaints, Notifications of
Summons and Successful Prosecutions, and other necessary observations obtained
within this reporting period form February 2025 to January 2026.
2.1.1
Drainage Services
Department (“DSD”) is the project proponent and the permit holder of the
Project. For the construction phase of the Project, Contractor(s), ET and
Independent Environmental Checker (“IEC”) are appointed to manage and control
environmental issues. Key personnel and contact particulars are summarized in Table 2.1.
2.1.2
Upon conclusion of
Contract No: SD 15/2022 Outlying Island Sewerage Stage 2 – South Lantau Sewage
Works – Environmental Team Services (2023 – 2024), the subsequent contract,
Contract No. CM 04/2024 Outlying Islands Sewerage Stage 2 – South Lantau
Sewerage Works – Environmental Team Services (2025-2027), has been awarded to
Umwelt Consulting Limited (“UCL”) starting 1 February 2025. As such the environmental
team leader (“ETL”) appointed for the Project has been updated to Mr. Ting Po
Chung, Ivan since 1 February 2025. His contact details has been updated in Figure 2.1 and Table 2.1.
Table
2.1: Contact
Details of Key Personnel
|
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
|
Drainage Services Department |
The Engineer for the Contract |
Engineer |
Mr. KK Chan |
2594 7297 |
3104 6426 |
|
Binnies Hong Kong Limited |
Engineer’s Representative |
Resident Engineer |
Mr. Kevin Chan |
3529 3003 |
- |
|
Kwan Lee – Chun Wo
Joint Venture |
Contractor |
Sub Agent |
Mr. Daniel Chu |
6737 6701 |
2744 6937 |
|
Environmental Supervisor |
Ms. Joey Pang |
6978 2876 |
|||
|
Environmental Supervisor |
Mr. Philip Wong |
6908 8920 |
|||
|
SMEC Hong Kong |
IEC |
IEC |
Ms. Kitty Lee |
3995 8140 |
3422 3631 |
|
Umwelt Consulting Limited |
ET |
ET Leader |
Mr. Ivan Ting |
3756 9590 |
3582 3310 |
2.2.1
The proposed sewerage
works will collect the sewage generated from the unsewered areas of Shui Hau,
Tong Fuk, Cheung Sha, San Shek Wan, Pui O and Ham Tin in South Lantau (i.e.
within the Project Catchment Area) and convey it to a proposed sewage treatment
works at San Shek Wan for treatment and disposal into outer bay of Pui O / Chi
Ma Wan via a submarine outfall.
2.2.2
The Project was divided into 3 contracts. The current contract, Contract No.
DC/2020/02 - Construction of San Shek Wan Sewage Treatment Works, Associated
Submarine Outfall and Pui O Sewerage Works (“the Contract”) would have the following implementations. The works site of the Contract
is also given in Figure 2.2.
2.2.3
The major components
of the Contract under Environmental Permit (“EP”) (EP No. EP-538/2017)
comprises:
a) Construction of a secondary sewage treatment works
(“STW”) at San Shek Wan in South Lantau;
b) Construction of a sewage pumping station (“SPS”) at
Pui O, San Shek Wan, Cheung Sha and Cheung Fu Street;
c) Construction of about 1.4km of submarine outfall
with a diameter of 350mm for the disposal of treated effluent from the STW at
San Shek Wan;
d) Construction of about 10.1km of gravity sewers with
diameters ranging from 150mm to 375mm along South Lantau Road and Chi Ma Wan road and at Pui O; and
e) Construction of about 3.1km twin rising mains with
a diameter of 200mm to 250mm along South Lantau Road and Chi Ma Wan Road.
2.3.1
A summary of the current
status on submissions and measures mentioned in Environmental Permit
(EP-538/2017) are shown in Table 2.2.
Table 2.2: Summary
of submission status under EP-538/2017
|
EP Condition |
Submission and Revision No. |
Date of Latest Submission |
|
2.10 |
Waste Management Plan (Rev. 5) (electronic copy) |
4 April 2022# |
|
2.11 |
Preservation and/or Transplantation Plan for Plant
Species of Conservation Importance (Rev. 23) |
9 September 2022# |
|
2.12 |
Compensatory Woodland Planting Plan (Rev. 23) |
15 May 2023^ |
|
2.13 |
Silt Curtain Deployment Plan (Rev. 11) |
1 June 2022# |
|
2.14 |
Landscape Mitigation Plan |
To be confirmed |
|
2.15 |
Construction Noise Mitigation Plan (Rev. 20) |
4 August 2022# |
Note:
^ Submission
was made to EPD
# Approval
from EPD was received
2.4.1
A summary of the current
status on licences and/or permits on environmental protection pertinent
to the Project is shown in Table 2.3.
Table 2.3: Summary
of the Current Status on Licenses and/or Permits on Environmental Protection
Pertinent to the Project
|
Permits and/or Licences |
Permit. No. / Account No. |
Issued Date |
Valid Period & Expiry Date |
Status |
|
Notification of Works Under APCO |
466408 |
14 Apr 2021 |
N/A |
Valid |
|
Wastewater Discharge Licence under Water Pollution
Control Ordinance |
SSWSTW: WT00039636-2021 |
30 Dec 2021 |
30 Dec 2021 to |
Valid |
|
POPS: WT00039820-2021 |
31 Dec 2021 |
31 Dec 2021 to |
Valid |
|
|
SSWSTW: Gravity Sewer & Raising Main:
WT00042613-2022 |
09 Jan 2023 |
09 Jan 2023 to |
Valid |
|
|
Billing account under Waste Disposal Ordinance |
Account No.: 7040411 |
05 May 2021 |
N/A |
Valid |
|
Registration as a Chemical Waste Producer |
0000-931-K3428-01 |
13 May 2021 |
N/A |
Valid |
|
Construction Noise Permit under Noise Control
Ordinance for SSWSTW |
GW-RS0658-24 |
17 July 2024 |
9 Aug 2024 to 8 Feb 2025 |
Expired on 9 Feb 2025 |
|
GW-RS0084-25 |
28 Jan 2025 |
9 Feb 2025 to 8 Aug 2025 |
Expired on 9 Aug 2025 |
|
|
GW-RS0836-25 |
13 Aug 2025 |
15 Aug 2025 to 12 Feb 2026 |
Valid |
|
|
GW-RS0836-25 |
13 Aug 2025 |
15 Aug 2025 to 12 Feb 2026 |
Valid |
|
|
Construction Noise Permit under Noise Control
Ordinance for POSPS |
GW-RS0856-24 |
17 Sep 2024 |
27 Sep 2024 to 26 Mar 2025 |
Expired on 27 Mar 2025 |
|
GW-RS0310-25 |
26 Mar 2025 |
28 Mar 2025 to 26 Sep 2025 |
Expired on 27 Sep 2025 |
|
|
GW-RS0993-25 |
18 Sep 2025 |
27 Sep 2025 to 26 Mar 2026 |
Valid |
|
|
Marine Dumping Permit (Dredged Sediment Requiring Type 1 – Open Sea Disposal |
EP/MD/25-024 |
19 Nov 2024 |
19 Nov 2024 to 18 May 2025 |
Expired on 19 May 2025 |
|
Construction Noise Permit under Noise Control
Ordinance for Chi Ma Wan Road |
GW-RS0834-25 |
13 Aug 2025 |
15 Aug 2025 to 12 Feb 2026 |
Valid |
2.5.1
In the reporting period, the principal work activities conducted
are as follow:
a)
Superstructure Reinforced Concrete (“RC”)
works
b)
Waterproofing Work
c)
Excavation and Site formation
d)
Retaining wall construction
e)
Dredging and diffuser construction
f)
Backfilling Work
g)
Electrical and
Mechanical (“E&M”) Installation
h)
Slope Work along the Slope near SSWSTW
a)
Excavation, sewer laying,
construction of manhole
a)
Excavation, Sewer Laying, and Construction of Manhole
a)
Excavation, Sewer Laying, and Construction of Manhole
b)
Trenchless drilling works
3.1.1
The EM&A programme requires environmental monitoring, noise
monitoring, water quality monitoring, and ecology as specified in the approved
EM&A Manual.
3.1.2
A summary of Impact EM&A requirements is presented in Table 3.1. The
locations of noise monitoring stations, and water quality monitoring stations are shown in Figure 3.1 and
Figure 3.2 respectively.
Table 3.1: Summary of Impact EM&A Requirements
|
Environmental
Monitoring Aspects |
Parameters and
Unit |
Monitoring Station |
Frequencies |
Remarks |
|
Noise |
Leq (30mins), L10 (30mins)
and L90 (30mins) |
N12a, N12b,
N13, N14, N15b, N16a, N16b, and N17 |
At least once per
week |
Daytime on normal
weekdays (0700-1900 hrs). |
|
Water Quality |
Dissolved Oxygen,
mg/L Temperature, °C Salinity, 0/00 Turbidity, NTU Suspended Solids,
mg/L pH |
CE, CF, SR4,
SR5, SR6, SR9, SR10, SR12, and SR15 |
Three times per
week during mid-ebb, and mid-flood tides |
Samples are
collected at 3 depths (1 m below water, mid-depth, and 1 m above seabed)
shall be collected. Where the water
depth is less than 6 m, in which case the mid-depth station may be omitted. Should the water depth
be less than 3 m, only the mid-depth station will be monitored |
Noise Monitoring
3.2.1
A-weighted equivalent continuous sound pressure level (“Leq”) over a period of 30 minutes Leq (30min) shall
be used as the monitoring parameter for construction noise monitoring.
Supplementary information for data auditing, statistical results such as L10,
and L90 should also be recorded for reference.
3.2.2
For impact monitoring of construction works, noise monitoring should be
undertaken on weekly basis. Six consecutive Leq
(5min) between 07:00-19:00 hours on normal weekdays is taken in this
EM&A Programme.
3.2.3
The Action and Limit Levels for noise monitoring are given as in Table 3.2.
Table 3.2: Action
and Limit Levels for Noise Monitoring
|
Monitoring
Station ID |
Monitoring
Location |
Action Level |
Limit Level |
|
N12a |
Lo Uk Tsuen |
When one documented complaint is received from
any one of the noise sensitive receivers |
75 dB(A) |
|
N12b |
Lo Uk Tsuen |
75 dB(A) |
|
|
N13 |
Pui O San Wai
Tsuen |
75 dB(A) |
|
|
N14 |
South Lantau
Community Centre |
75 dB(A) |
|
|
N15b |
Pui O Lo Wai
Tsuen |
75 dB(A) |
|
|
N16a |
Residences at Ham
Tin |
75 dB(A) |
|
|
N16b |
Residences at Ham
Tin |
75 dB(A) |
|
|
N17 |
Bui O Public
School |
70 dB(A) / 65
dB(A) 1 |
Note:
1. The Limit Level for N17 is 70 dB(A) for being
an educational institution. The Limit Level is reduced to 65 dB(A) during
school examination period.
3.2.4
In the reporting period, total 424 of
impact noise monitoring at proposed locations were carried out by Environmental
Team (ET). Detailed noise monitoring results measured in this reporting period
are reviewed and summarized. Details of noise monitoring results and graphical
presentation can be referred in Appendix 3.1. The
number of noise monitoring carried out in each month during the reporting period
are shown in Table 3.3.
Table 3.3: The
number of noise monitoring carried out in each month during the report period
(February 2025 to January 2026)
|
Reporting Month |
No. of Noise Monitoring |
|
February 2025 |
32 |
|
March 2025 |
32 |
|
April 2025 |
40 |
|
May 2025 |
32 |
|
June 2025 |
40 |
|
July 2025 |
32 |
|
August 2025 |
32 |
|
September 2025 |
32 |
|
October 2025 |
40 |
|
November 2025 |
32 |
|
December 2025 |
40 |
|
January 2026 |
40 |
3.2.5
Apart from the exceedance on 24 December 2025 described below, all noise
monitoring results complied with the relevant limit level.
3.2.6
Noise limit level exceedance of 75 dB(A) was recorded at N12a on 24
December 2025. Site observation recorded a breaker operating at a roadside
works site on South Lantau Road during monitoring. Also, local traffic noise,
that comprises of heavy vehicles including trucks and buses, was observed to be
high. As such, the exceedance would be due to combination of construction works
and traffic flow. Hence, it is considered that the exceedance maybe project-related.
3.2.7
Repeat monitoring was conducted on 30 December 2025 due to no
construction works during the public holidays on 25–26 December. Corrected
noise level of 72dB(A) at N12a was recorded. Site investigation conducted on 30
December 2025 observed that no beaker was in operation at the work site.
Corresponding remedial actions, including reminding the Contractor to maintain
vigilance over construction noise and implemented proper construction noise
mitigation measures according to EM&A Manual and Construction Noise
Mitigation Plan. And formalizing the mandatory erection of noise barriers for
future concrete breaking activities to prevent the recurrence of similar
incidents. The Investigation report is given in Appendix 3.2.
Water Quality Monitoring
3.2.8
In construction
phase, the levels of dissolved oxygen (“DO”), temperature, turbidity, and
salinity should be measured in-situ while suspended solids (“SS”) is determined
by laboratory analysis.
3.2.9
The Action and
Limit Levels for water quality monitoring are given as in Table 3.4.
Table 3.4: Action
and Limit Levels Level for Water Quality Monitoring
|
Parameters |
Action Level |
Limit Level |
|
DO in mg/L 1 |
Surface, and Middle Level: 5.8 mg/L Bottom: 5.9 mg/L |
Surface, and Middle Level: 4 mg/L, Bottom: 2 mg/L |
|
Turbidity in NTU (Depth-averaged 2) 3 |
14.4 NTU and 20% exceedance of value at any impact station compared with corresponding data from control station 4 |
23.5 NTU and 30% exceedance of value at any impact station compared with corresponding data from control station 4 |
|
SS in mg/L (Depth-averaged 2) 3 |
13.1 mg/L and 20% exceedance of value at any impact station compared with corresponding data from control station 4 |
30.4 mg/L and 30% exceedance of value at any impact station compared with corresponding data from control station 4 |
Notes (with proposed amendments in AL/LL in
underlined text):
For DO, non-compliance of the water quality
limits occurs when monitoring result is lower than the limits.
“Depth-averaged” is calculated by taking the
arithmetic means of reading of all 3 depths
For SS, and turbidity, non-compliance of the
water quality limits occurs when monitoring result is higher than the limits.
Action Level, and Limit Level with 95%-ile / 99%-ile derived from
baseline data “and” 20% / 30% exceedance of control station proposed in
Baseline Monitoring Report.
3.2.10
In the reporting
period, total 441 of water quality monitoring for ebb tide and 441 of water
quality monitoring for flood tide at proposed locations were carried out by The
ET details of marine water quality monitoring results and graphical
presentation can be referred in Appendix 3.3.
Table 3.5: The number of water quality monitoring carried out in each month during the report period (February 2025 to January 2026)
|
Reporting Month |
No. of Water Quality Monitoring |
||
|
Ebb |
Flood |
Total |
|
|
February 2025 |
108 |
108 |
216 |
|
March 2025 |
117 |
117 |
234 |
|
April 2025 |
108 |
108 |
216 |
|
May 2025 |
108 |
108 |
216 |
|
June 2025 to January 2026 |
N/A |
N/A |
N/A |
|
Total |
441 |
441 |
882 |
3.2.11
Subsequent to the completion of marine work on 24 May
2025, water quality monitoring was considered completed by 30 May 2025. No
water quality monitoring is conducted in June 2025 to January 2026.
3.2.12
Should marine work
resume, water quality monitoring will be conducted in accordance with the
requirement stipulated in the EM&A Manual accordingly.
3.2.13 In
accordance with the action level and limit level in Baseline Monitoring Report
Rev. 9.2 agreed by EPD on 2 September 2022, action level exceedances were recorded for
dissolved oxygen on 17 to 29 May 2025. Investigations have been conducted
accordingly and concluded the exceedances were not project related. The
detailed results and graphical plot for water quality monitoring are given in Appendix
3.3.
Table 3.6: The
number of water quality exceedances in each month during the report period
(February 2025 to January 2026)
|
Station |
|
Parameter |
DO (S&M) |
DO (Bottom) |
Turbidity |
SS |
Exceedance count |
|||||
|
Level exceeded |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
||
|
February 2025 |
Derived criteria in Baseline Monitoring Report Rev. 9.2 were agreed by
EPD on 2 September 2022 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
|
March 2025 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
|
April 2025 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
|
May 2025 |
Action |
1 |
2 |
10 |
12 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
3.2.14
The marine
construction works were completed in May 2025, with the silt curtain removed on
24 May 2025 in accordance with the approved Silt Curtain Deployment Plan.
3.2.15
Action level exceedances were recorded for dissolved oxygen on 17 to 29
May 2025. Investigations
have been conducted accordingly and concluded the exceedances were
not project related.
3.2.16
From 17 to 22 May 2025, no marine works were carried out, and the
sampling team did not
observe any abnormalities during water quality monitoring, so this DO
exceedance is
determined to be caused by natural fluctuations and unrelated to the project.
3.2.17
On 24 May 2025, marine works including removal of the silt curtain and
cutting of the casing
were conducted; however, such works would not introduce pollutants affecting
DO, and the sampling team found no
abnormalities in water quality monitoring, thus this
DO exceedance is also judged to result from
natural fluctuations and have no connection
with the project.
3.2.18
No marine works were performed on 27 and 29 May 2025, and the sampling
team did not
detect any abnormalities during water quality monitoring, leading to the
conclusion that
this DO exceedance is attributed to natural fluctuations and not related to the
project.
3.2.19
A site investigation was conducted on 30 May 2025, during which seawater
abnormalities were found, suspected to be an
algae bloom. In summary, this DO
exceedance is also determined to be caused by
natural fluctuations and unrelated to the project.
Ecological Impact Monitoring
3.2.20 Monitoring in the form of
regular site inspections should be carried out to ensure ecological measures in
the form of tree transplantation, and establishment are being implemented, and
effective for plant species of conservation importance (e.g. Aquilaria
sinensis).
3.2.21 Transplanting works for
plant species, Aquilaris sinensis, was
completed on 26 April 2022. Maintenance works for trees in holding nursery have
commenced.
3.2.22 Monitoring of maintenance
works for the transplanted plant species was conducted at the holding nursery
while in the reporting period.
3.2.23 As per latest version of
PTP, four trees found (1 no. of Aquilaria sinensis, and 3 nos. of Gmelina
chinensis) within the site of SSWSTW which are considered
to be the plant species with conservative importance for temporarily
transplanted to the nursery at Kam Tin and eventually be transplanted to POSPS.
3.2.24
Within this reporting
period, holding nursery visit for transplanted trees on 24 February, 24 March, 23
April, 27 May, 30 June, 28 July, 27 August, 22 September, 20 October, 24
November, 15 December 2025, 12 and 19 January 2026.
3.2.25
One non-compliance(exceedance) was record. Results and findings of
these inspections in this reporting period are listed below in Table 3.7.
Table 3.7: Summary
of Ecological Impact Monitoring
|
Inspection Date |
Reminder and Recommendations |
Close-out Date / Status |
|
24
February 2025 |
Nil |
-- |
|
24
March 2025 |
Nil |
-- |
|
23
April 2025 |
The
contractor is reminded to properly install the tree label. |
Contractor
has rectified the reminders on 7 May 2025 |
|
27
May 2025 |
The
contractor is reminded to clear the weeds. |
Contractor
has rectified the reminders on 2 June 2025. |
|
30
June 2025 |
The
contractor is reminded to properly install the tree tag. |
Contractor
has rectified the reminders on 15 July 2025 |
|
28
July 2025 |
The
contractor is reminded to replace faded tree tag. |
Contractor
has rectified the reminders on 13 August 2025. |
|
27
August 2025 |
Nil |
-- |
|
22
September 2025 |
Nil. |
-- |
|
20
October 2025 |
Nil. |
-- |
|
24
November 2025 |
Nil |
-- |
|
15
December 2025 |
Nil. |
-- |
|
12
January 2026 |
Nil. |
-- |
|
19
January 2026 |
Nil. |
-- |
Waste Management
3.2.26
The quantities of waste for disposal in
present period are summarized
in Table 3.8 and Waste Material in the reporting period is given in Appendix
3.5.
Table 3.8: Summary of Quantities of Waste Material in
the Reporting Period (February 2025 to January 2026)
|
Waste Type |
Quantity for Reporting Period |
Cumulative Quantity-to-Day |
|
Hard Rock and Large Broken Concrete (Inert), in ‘000m3 |
0 |
0 |
|
Reused in this Contract (Inert),in ‘000m3 |
0 |
0 |
|
Reused in other Projects
(Inert), in ‘000m3 |
0 |
0 |
|
Disposal as Public Fill
(Inert), in ‘000m3 |
4.35 |
31.398 |
|
Metals (in ‘000kg) |
118.179 |
115.146 |
|
Paper / Cardboard Packing, in
‘000kg |
0.601 |
1.519 |
|
Plastics in ‘000kg |
0.024 |
0.122 |
|
Chemical Waste in ‘000kg |
0 |
0 |
|
General Refuse in ‘000kg |
607.49 |
1353.990 |
Note:
1. The table is summary of
quantities of waste material of report
period.
2. The inert waste disposal record from 1
February 2025 up to 7 April 2025 was based on the onsite record from the
contractor instead of the official record from the Mui Wo Public Fill Reception
Facility due to the maintenance of the weighbridge.
3. The inert waste disposal records after 7
April 2025 reported in this reporting period are based on the recorded disposal
weights at the Mui Wo Public Fill Reception Facility.
3.3.1
The environmental
mitigation measures that recommended in the Implementation Status of
Recommended Mitigation Measure in the Project EM&A Manual covered
the issues of Air Quality, Noise, Water
Quality, Ecological Impact, Waste Management Implication,
Landscape &
Visual and Cultural Heritage and presented in Appendix 4.1.
3.3.2
The mitigation measures recommended in the
EIA Report has been implemented where applicable. The implemented mitigation
measures for the reporting period are listed below:
a)
Implementation of noise pollution control in
accordance with Construction Noise Mitigation Plan;
b)
Dust control during dust generating works;
c)
Silt curtain should be maintained in good
condition prior to and during dredging and related marine works;
d)
Adopt surface drainage and sediment control
facilities for sewage installation in village and public roads;
e)
Adopt temporary drainage and sediment control
facilities on Site;
f)
Vehicle wheel-washing and body washing
facilities should be provided at the site entrance;
g)
Regular water spraying on excavation works
for dust control;
h)
Proper waste handling, recycling and storage;
and
i)
Prevention of site runoff during heavy
rainstorms
3.3.3
The implemented mitigation measures are
considered effective.
Environmental Complaints Received
3.4.1
On 16 September 2025, the received complaint was
related to a reported oil sheen observed in the wetland area near Pui O Wetland, Lantau Island. On 25
September 2025, additional information from EPD was received that oil signs spotted in the Pui O. Subsequent
investigations have been conducted.
3.4.2
An unannounced inspection conducted by ET on 17
September 2025, joint site investigation conducted by ET and the Contractor on 18 September 2025, and a joint
site investigation conducted by ET, EPD, and the Contractor on 25 September 2025, and the subsequent site
inspection conducted with ET, and Contractor on the same day. Preliminary findings showed that the diesel drum
stored within the Project Sites were stored properly with no leakage or spillage. No oil signs within the project
sites were found during the inspections conducted throughout the period of complaint investigation. Also, locations of the
identified oil sheen are not within proximity of the Project Site.
3.4.3
The Final Investigation Report was submitted to
EPD on 17 October 2025. Given that there is no evidence of oil leakage within our project site, it is
considered that the oil pollution was not caused by our site operations. As
such,
the case is considered closed. The Final Investigation
Report is
given in Appendix 3.6.
3.4.4
One environmental complaint regarding the construction works was
recorded in the reporting period. The detail of complaint is shown in Table 3.9.
Table
3.9: Summary
of Complaints in the Report Period
|
Date of Incident |
Description of Instance/ Circumstances or change of Circumstances |
Action(s)/ Response(s) |
Close-Out Date/ Status |
|
16/9/2025 |
The complainants alleged
that there was oil sheen found at the wetland in Pui
O, leading to withering of plants. The complaint was referred from EPD to ETL
via email. |
Based on subsequent
inspections, the oil leakage to the Project. As such, the case is considered
closed. |
The Final Investigation
Report was submitted to EPD on 17 October 2025. |
3.4.5
No notification of summons and successful prosecution regarding
construction works
were
recorded in the reporting period.
3.4.6
Cumulative statistic on complaints and
successful prosecutions are summarized in Table
3.10 and Table 3.11 respectively.
Table 3.10: Cumulative Statistics on Complaints
|
Reporting Period |
No. of Complaints |
|
Project commencement to
the end of last reporting period |
3 |
|
February 2025 – January
2026 |
1 |
|
Total: |
4 |
Table 3.11: Cumulative
Statistics on Successful Prosecutions
|
Environmental Parameters |
Cumulative No. Brought
Forward |
No. of Successful
Prosecutions this month (Offence Date) |
Cumulative No.
Project-to-Date |
|
Air |
- |
0 |
0 |
|
Noise |
- |
0 |
0 |
|
Water |
- |
0 |
0 |
|
Waste |
- |
0 |
0 |
|
Other |
- |
0 |
0 |
|
Total |
- |
0 |
0 |
Environmental Non-Compliance(exceedance)
3.4.7
The detail of exceedance has been discussed in Section 3.2.6-3.2.7 and
3.2.15-3.2.19.
Notifications of Summons and Successful
Prosecutions
3.4.8
No notification of summons and successful
prosecution regarding construction works were recorded in the reporting period.
4.1.1
Environmental
monitoring and audits including Noise, Water Quality, Ecology, and Site audits
have been conducted in the reporting period in accordance
with the requirement stipulated in the EM&A Manual.
4.1.2
The environmental
mitigation measures that recommended in the Implementation Status of Recommended
Mitigation Measure in the Project EM&A Manual covered the issues of Air Quality, Noise, Water
Quality, Ecological Impact, Waste Management Implication, Landscape & Visual and Cultural Heritage and presented in Appendix 4.1.
Noise Monitoring
4.1.3
Noise Monitoring has
been conducted at 8 of the designated monitoring locations where construction works
has been conducted nearby during the reporting period.
4.1.4
Noise limit level
exceedance of 75 dB(A) was recorded at N12a on 24 December 2025. Site
observation recorded a breaker operating at a roadside works site on South
Lantau Road during monitoring. Also, local traffic noise, that comprises of
heavy vehicles including trucks and buses, was observed to be high. As such,
the exceedance would be due to combination of construction works and traffic
flow. Hence, it is considered that the exceedance maybe project-related.
4.1.5
Repeat monitoring was
conducted on 30 December 2025 due to no construction works during the public
holidays on 25–26 December. Corrected noise level of 72dB(A) at N12a was
recorded. Site investigation conducted on 30 December 2025 observed that no
beaker was in operation at the work site. Corresponding remedial actions,
including reminding the Contractor to maintain vigilance over construction
noise and implemented proper construction noise mitigation measures according
to EM&A Manual and Construction Noise Mitigation Plan. And formalizing the
mandatory erection of noise barriers for future concrete breaking activities to
prevent the recurrence of similar incidents. The final investigation report was
submitted to EPD by 30 January 2026, and the final investigation report is
given in Appendix 3.2.
Water Quality Monitoring
4.1.6
Subsequent to the completion of marine
work on 24 May 2025, water quality monitoring was considered completed by 30 May 2025.
No water quality monitoring is conducted in this reporting period.
Ecological Impact Monitoring
4.1.7
Transplanting of the trees of Aquilaris
sinensis was completed on 26 April 2022. Maintenance works for trees in
holding nursery have commenced.
4.1.8
As per latest version of PTP, 4 tree found (1
no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within
the site of SSWSTW which are considered to be the plant species with
conservative importance for temporarily transplanted to the nursery at Kam Tin and
eventually be transplanted to Pui O Pumping Station.
4.1.9
The weekly site audit was carried out by ET include checking whether
good site practices are being properly implemented by the Contractor.
4.1.10 The extent of the
work site boundaries was checked by the ET during the weekly site audit.
4.1.11 No
non-compliance was found during the site inspection while reminders on
environmental measures were recommended.
4.2.1
On 16 September 2025, the received complaint was
related to a reported oil sheen observed in the wetland area near Pui O
Wetland, Lantau Island. On 25 September 2025, additional information from EPD
was received that oil signs spotted in the Pui O. Subsequent investigations
have been conducted.
4.2.2
An unannounced inspection conducted by ET on 17
September 2025, joint site investigation conducted by ET and the Contractor on
18 September 2025, and a joint site investigation conducted by ET, EPD, and the
Contractor on 25 September 2025, and the subsequent site inspection conducted
with ET, and Contractor on the same day. Preliminary findings showed that the
diesel drum stored within the Project Sites were stored properly with no
leakage or spillage. No oil signs within the project sites were found during
the inspections conducted throughout the period of complaint investigation.
Also, locations of the identified oil sheen are not within proximity of the
Project Site.
4.2.3
The Final Investigation Report was submitted to
EPD on 17 October 2025. Given that there is no evidence of oil leakage within
our project site, it is considered that the oil pollution was not caused by our
site operations. As such, the case is considered closed.
4.2.4
No notification of summons and successful
prosecution regarding construction works were recorded in the reporting period.
4.3.1
The mitigation measures recommended in the EIA Report has been
implemented where applicable. The implemented mitigation measures are
considered effective.