CONTRACT NO: SD 15/2022
Outlying
Island Sewerage Stage 2 – South Lantau Sewage Works – Environmental Team Services (2023
– 2024) Under Environmental Permit no. EP-538/2017
quarterly Environmental Monitoring & Audit summary
Report
November 2023 to January 2024
Revision 1
|
|
CLIENTS: |
|
|
Drainage Services Department |
Lam Environmental Services Limited 19/F Remex Centre, 42 Wong Chuk Hang Road, Hong Kong Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
|
|
|
Certified
by: |
|
|
_______________________________ Environmental
Team Leader Derek
Lo |
|
|
DATE: |
|
|
5 April 2024 |
|
|
|
1.1.......... Scope of the Report
1.2.......... Structure of the Report
2.1.......... Project Organization
and Key Contact Personnel
2.2.......... Construction Programme
3. A Brief Summary of EM&A
Requirements
3.1.......... Monitoring Parameters
3.2.......... Environmental Quality
Performance Limits
4.2.......... Environmental
Mitigation Measures
4.3.......... Environmental
monitoring requirements and contractual requirements
5. Monitoring Results Analysis
5.1.......... Noise Monitoring
5.2.......... Water Quality
Monitoring
5.3 Ecological Impact Monitoring……………………………………………..
5.4.......... Waste Management
6. Complaints, Notification of Summons
and Prosecution
7. Comments and Recommendations
lIST OF TABLES
Table 2.1 Contact
Details of Key Personnel
Table 4.1 Summary of submission status under
EP-538/2017
Table 5.1 Summary of Quantities of Waste
Material (August, September and October 2023)
Table 6.2 Cumulative Statistics on
Complaints
Table 6.3 Cumulative Statistics on
Successful Prosecutions
Table 7.1 Construction Activities in Past 3
Months
lIST OF FIGUREs
Figure 2.1 Project Organization Chart
Figure
5.1 Locations of Noise Monitoring
Station
Figure
5.2 Locations of Water Quality Monitoring Stations
lIST OF APPENDIces
Appendix
5.1 Noise Monitoring Graphical
Presentations
Appendix 5.2 Marine Water Quality Monitoring Graphical and
Summary of Exceedance Presentations
Appendix
5.3 Quarterly Summary Waste Flow Table
EXECUTIVE SUMMARY
i.
This
is the Quarterly Environmental Monitoring and Audit (EM&A) Summary Report
– November
2023 to January 2024 of
Outlying Islands Sewerage Stage
2 – South Lantau Sewerage Works under Environmental Permit no. EP-538/2017
(Hereafter as “the Project”). The
construction works of the Project was commenced on 3 November 2021 and the tentative completion date is Q1 2026. The
Quarterly EM&A Summary Report presents the environmental monitoring
findings and information recorded during the period of 1 November 2023 to 31 January 2024.
ii.
In
the reporting period, the principal work activities conducted are as follow:
|
November 2023 |
December 2023 |
January 2024 |
|
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk
Tsuen, South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Horizontal Directional Drilling (HDD) works at marine and SSWSTW ·
Removal works of Excavation and Lateral Support (ELS) ·
Excavation and Lateral Support (ELS) works ·
Superstructure Reinforced Concrete (RC) Works ·
Marine dredging |
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk
Tsuen, South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Horizontal Directional Drilling (HDD) works at marine and SSWSTW ·
Removal works of Excavation and Lateral Support (ELS) ·
Excavation and Lateral Support (ELS) works ·
Superstructure Reinforced Concrete (RC) Works |
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk
Tsuen, South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Horizontal Directional Drilling (HDD) works at marine and SSWSTW ·
Removal works of Excavation and Lateral Support (ELS) ·
Excavation and Lateral Support (ELS) works ·
Superstructure Reinforced Concrete (RC) Works |
Exceedances of Action/Limit Levels
Noise Monitoring
iii.
Noise monitoring was conducted at eight (8) noise monitoring stations
(N12a, N12b, N13, N14, N15b, N16a, N16b and N17) once per week in the reporting
period.
iv.
School examination was taken place at N17 – Bui O Public School from 8
to 17 November
2023 in the
reporting period. The limit level of noise monitoring station N17-Bui O Public
School was adjusted to 65dB(A) accordingly during the period.
v.
No action and limit level exceedances were recorded in construction
noise level in the reporting period.
Water Quality Monitoring
vii.
Water quality monitoring on 17 & 24 Nov 2023, 20 & 22 Dec 2023
and 8 (mid-ebb) & 22 (mid-ebb and mid-flood) Jan 2024 were cancelled due to
Strong Monsoon Signal. Water quality monitoring on 24 January 2024 (mid ebb and
mid-flood) was cancelled due to sea condition taking personnel safety into
consideration. No substitution would be arranged for such cancellation since it
is impossible to maintain the monitoring frequency as three times a week for
the event of marine water quality monitoring cancellation in between time with
respect to the fact that not less than 36 hours interval shall be followed for
two monitoring days as required by the EM&A Manual Clause 5.1.6 (b) for the
Project.
viii.
In accordance with the action level and limit level in Baseline
Monitoring Report Rev. 9.2 agreed by EPD on 2 September 2022, 5 action level
and 0 limit level exceedances was recorded in the reporting period. 1 action
level exceedances on SS at SR9 during flood tide on 15 November 2023 was
recorded. 4 action level exceedances on SS at SR9, SR10, SR12 and SR15 during flood
tide on 1 December 2023 were recorded. It can be concluded that the SS exceedances
were possibly due to natural variation or changes of water quality in the
vicinity of water quality monitoring station and considered that the exceedance
was not related to Project works.
Ecological Impact Monitoring
ix.
Transplanting works for plant species, Aquilaris sinensis, was completed on 26 April 2022. Maintenance
works for trees in holding nursery have commenced.
x.
As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of
SSWSTW which are considered to be the plant species with conservative
importance for temporarily transplanted to the nursery at Kam Tin and
eventually be transplanted to Pui O Pumping Station.
xi.
The weekly
site audit was carried out by ET include checking whether good site practices
are being properly implemented by the Contractor.
xii.
The extent of the work site boundaries was checked by the ET during the
weekly site audit.
Complaint log
Notifications
of Any Summons and Successful Prosecutions
xiv.
No environmental notification of any summons and
successful prosecution regarding the construction works was recorded in present quarter.
1.1.1.
Lam Environmental Services Limited (LES) has been appointed to work as
the Environmental Team (ET) under Environmental Permit (EP) no. EP-538/2017 to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Outlying Islands Sewerage Stage 2 - South Lantau
Sewerage Works (Register No.: AEIAR-210/2017).
1.1.2.
The Quarterly EM&A Summary Report was prepared according to Section 12.3
of the Project EM&A Manual.
Section 1 Introduction – details the scope and structure of the report
Section 2 Basic
Project Information – a synopsis of project
organization, programme contacts of key management, and a synopsis of work undertaken
in the reporting period.
Section 3 A
Brief Summary of EM&A requirements – including monitoring parameters, environmental quality
performance limits (Action and Limit levels); and environmental mitigation
measure, as recommended in the EIA Report.
Section 4 Implementation
Status – Advice on the implementation
status of environmental protection and pollution control/mitigation measures,
as recommended in the EIA Report and summarised in the updated implementation
schedule.
Section 5 Monitoring
Results Analysis – the trends of the
monitoring parameters in present quarter; advice on the solid and liquid waste
management status.
Section 6 Summary
of Non-Compliance (exceedances) of the environmental quality performance
limits, Complaints,
Notification of Summons and Successful Prosecutions
A
brief review of the reasons for and the implications of non-compliance and a
summary description of the actions taken and any follow-up procedures related
to earlier non-compliance.
A summary record
of all complaints received (written or verbal) for each media, liaison and
consultation undertaken, actions and follow-up procedures taken;
A summary record of
notifications of summons and successful prosecutions for breaches of the
current environmental protection/pollution control legislations, including
locations and nature of the breaches, investigation, follow-up actions taken
and results.
Section 7 Comments and Recommendations – such as effectiveness and efficiency of the mitigation
measures, improvement in the EM&A programme, if any.
Section 8 Conclusion
and Project Proponent’s contacts and hotline telephone number for the public to
make enquiries
2.1.1
Drainage Services Department is the overall project controllers for the
Project. For the construction phase of the Project, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues. Key personnel and contact particulars are
summarised in Figure 2.1 and Table 2.1:
Table 2.1 Contact Details of Key Personnel
|
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
|
Drainage
Services Department (DSD) |
The Engineer for the
Contract |
Engineer |
Mr. Silas Chan |
2594 7272 |
3104 6426 |
|
Binnies
Hong Kong Limited |
Engineer’s
Representative |
Resident
Engineer |
Mr. Kevin Chan |
3529 3013 |
- |
|
Kwan
Lee – Chun Wo Joint Venture |
Contractor
|
Site
Agent |
Mr. Charles Yeung |
6128 2606 |
2744 6937 |
|
Environmental
Officer |
Ms. Shirley Kong |
5162 5933 |
|||
|
SMEC Hong Kong |
Independent Environmental
Checker (IEC) |
Independent Environmental Checker (IEC) |
Ms. Kitty Lee |
3995 8140 |
3995 8101 |
|
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Derek Lo |
2882 3939 |
2882 3331 |
2.2.1
The proposed sewerage works will collect the sewage generated from
the unsewered areas of Shui Hau, Tong Fuk,
Cheung Sha, San Shek Wan, Pui O and Ham Tin in South
Lantau (i.e. within the Project Catchment Area) and convey it to a proposed
sewage treatment works at San Shek Wan for treatment and disposal
into outer bay of Pui O/ Chi Ma Wan via a submarine outfall.
2.2.2
The entire Project are divided into three contracts. Contract No.
DC/2020/20 (the Contract) would have the following implementations as
demonstrated in Figure 2.2.
2.2.3
The major components of the Project under Environmental Permit (EP) (EP
No. EP-538/2017) comprises: (i) construction of sewage treatment works at San
Shek Wan (SSWSTW) and associated submarine outfall; (ii) construction of sewage
pumping station at Pui O (POSPS); (iii) village sewage works at Pui O; and (iv)
trunk sewers and rising mains on carriageways.
Noise
Monitoring
3.1.1 The construction noise level shall
be measured in terms of the A-weighted equivalent continuous sound pressure
level (Leq). Leq (30min) should be used as the monitoring
parameter. Supplementary information for data auditing, statistical results
such as L10 and L90 shall also be obtained for reference.
3.1.2 For impact monitoring for
construction of village sewers / rising main, noise monitoring should be
undertaken on weekly basis. One set of Leq
(30min) noise level as six consecutive Leq (5min) between
07:00-19:00 hours on normal weekdays.
Water Quality Monitoring
3.1.3 In construction phase, the levels
of dissolved oxygen (DO), temperature, turbidity and salinity should be measured
in-situ while suspended solids (SS)
is determined by laboratory analysis.
Ecological Impact Monitoring
3.1.4 Monitoring in the form of regular
site inspections should be carried out to ensure ecological measures in the
form of tree transplantation and establishment are being implemented and effective
for plant species of conservation importance (e.g. Aquilaria sinensis).
Noise
Monitoring
3.2.1 No action and limit level exceedances were
recorded in construction noise level in the reporting period.
Water
Quality Monitoring
3.2.2 Marine-based construction works had been
commenced since 19 April 2022, marine water quality monitoring was initialised
since 12 April 2022.
3.2.3 To support water quality monitoring, the
silt curtain deployment plan has minor updates to include an additional brand
of geosynthetic material as alternative for selection and adopt underwater
robot for inspecting condition of silt curtain.
3.2.4
Water quality monitoring on 17 & 24 Nov 2023, 20 & 22 Dec 2023
and 8 (mid-ebb) & 22 (mid-ebb and mid-flood) Jan 2024 were cancelled due to
Strong Monsoon Signal. Water quality monitoring on 24 January 2024 (mid ebb and
mid-flood) was cancelled due to sea condition taking personnel safety into
consideration. No substitution would be arranged for such cancellation since it
is impossible to maintain the monitoring frequency as three times a week for
the event of marine water quality monitoring cancellation in between time with
respect to the fact that not less than 36 hours interval shall be followed for
two monitoring days as required by the EM&A Manual Clause 5.1.6 (b) for the
Project.
3.2.5 Water quality monitoring is
evaluated against Action and Limit Levels. The derived Action and Limit Level
proposed in Baseline Monitoring Report Rev. 9.2 was agreed by EPD on 2
September 2022. Action and Limit Levels of marine water quality monitoring have
been set with reference to the derived criteria as shown in Table
3.1 below.
Table 3.1 Action and Limit Levels of Water Quality
|
Parameters |
Action
Level |
Limit
Level |
|
Construction Phase Marine Water
Monitoring - derived criteria |
||
|
DO in mg/L B |
Surface and Middle:
5.8 mg/L Bottom: 5.9 mg/L |
Surface and Middle:
4 mg/L Bottom: 2 mg/L |
|
Turbidity in NTU (Depth-averaged A) C |
14.4 NTU and 20% exceedance of
value at any impact station compared with corresponding data from control
station D |
23.5 NTU and 30% exceedance of
value at any impact station compared with corresponding data from control
station D |
|
SS in mg/L (Depth-averaged A) C |
13.1 mg/L and 20% exceedance of
value at any impact station compared with corresponding data from control
station D |
30.4 mg/L and 30% exceedance of
value at any impact station compared with corresponding data from control
station D |
Notes
(with proposed amendments in AL/LL in underlined text):
A. “Depth-averaged”
is calculated by taking the arithmetic means of reading of all three depths.
B. For
DO, non-compliance of the water quality limits occurs when monitoring result is
lower than the limits.
C. For
SS and turbidity, non-compliance of the water quality limits occurs when
monitoring result is higher than the limits.
D. Action
Level and Limit Level with 95%-ile / 99%-ile derived from baseline data “and”
20% / 30% exceedance of control station proposed in Baseline Monitoring Report.
3.2.6
In accordance with the action level and limit level in Baseline
Monitoring Report Rev. 9.2 agreed by EPD on 2 September 2022, 5 action level
and 0 limit level exceedances was recorded in the reporting period. 1 action
level exceedances on SS at SR9 during flood tide on 15 November 2023 was recorded.
4 action level exceedances on SS at SR9,
SR10, SR12 and SR15 during flood tide on 1 December 2023 were recorded. No
action level and limit level exceedance was recorded in January 2024.
3.2.7 It can be
concluded that the SS exceedances recorded in November and December 2023 were
possibly due to natural variation or changes of water quality in the vicinity
of water quality monitoring station and considered that the exceedance was not
related to Project works.
3.2.8 Checked with contractors and RSS on the
marine works activities in the reporting period, the following activities were
recorded:
|
Date |
Marine-based construction
activities undertaken |
Mitigation measures implemented |
|
1/11/2023 |
No activity |
Nil |
|
3/11/2023 |
No activity |
Nil |
|
6/11/2023 |
No activity |
Nil |
|
8/11/2023 |
No activity |
Nil |
|
10/11/2023 |
Reparation
of Silt Curtain |
Remove
debris on the barges |
|
13/11/2023 |
Dredging |
Working
area was enclosed by silt curtain. |
|
15/11/2023 |
Borehole
Cleaning |
Working area was enclosed by
silt curtain. |
|
20/11/2023 |
Borehole
Cleaning |
Working area was enclosed by
silt curtain. |
|
22/11/2023 |
Borehole
Cleaning |
Working area was enclosed by
silt curtain. |
|
27/11/2023 |
No
Activity |
Nil |
|
29/11/2023 |
Pipe
Pulling |
Working area was enclosed by
silt curtain. |
|
1/12/2023 |
Pipe
Pulling |
Working area was enclosed by
silt curtain. |
|
5/12/2023 |
No
activities |
N/A |
|
7/12/2023 |
No
activities |
N/A |
|
9/12/2023 |
No
activities |
N/A |
|
11/12/2023 |
No
activities |
N/A |
|
13/12/2023 |
No
activities |
N/A |
|
15/12/2023 |
No
activities |
N/A |
|
18/12/2023 |
No
activities |
N/A |
|
20/12/2023 |
No
activities |
N/A |
|
22/12/2023 |
No
activities |
N/A |
|
25/12/2023 |
No
activities |
N/A |
3.2.9 For November 2023, borehole cleaning was
conducted within fully enclosed silt curtain at around 9:00 - 11:00 and 15:00 -
17:00 on 15 November 2023, despite there was dredging works on 13 Nov 2023 at
around 10:10 to 11:30, no exceedances was recorded during mid-ebb (12:18) and
mid-flood (17:40) tide on 13 Nov 2023. No dredging works on 15 Nov 2023, no
exceedance was recorded on same day during ebb tide from 13:08 to 13:12 at SR9.
No exceedances was recorded at the monitoring stations close to the marine
works area e.g. SR4, SR5 and SR6, no exceedances was recorded at the monitoring
stations closed to SR9 e.g. SR10 and SR12 on 13 and 15 Nov 2023. No exceedances
was recorded in the subsequent monitoring on 20 Nov 2023 both ebb and flood
tide.
3.2.10 For December 2023, action level
exceedances of Depth-averaged on suspended solids (SS) was recorded at SR9,
SR10, SR12 and SR15 on 1 Dec 2023 from 09:39 to 10:33 during flood tide on 1
Dec 2023, checking with contractor, pipe pulling was conducted within fully
enclosed silt curtain from 07:00 to 23:00, no damage recorded on the silt
curtain, no dredging works on 1 Dec 2023. Higher SS during flood tide was
recorded from 9.5mg/L (SR6) to 18.3mg/L (CE), no exceedance was recorded on
same day during ebb tide from 15:00 to 15:53 at SR9, SR10, SR12 and SR15. No
exceedances was recorded at the monitoring stations close to the marine works
area e.g. SR4, SR5 and SR6 on 1 Dec 2023.
3.2.11
Reviewed the overall work situation and the mitigation measures
implemented by the Contactor, It can be concluded that the SS exceedances were
possibly due to natural variation or changes of water quality in the vicinity
of water quality monitoring station and considered that the all exceedances
were not related to Project works.
Ecological monitoring
3.2.12 Transplanting works for plant species, Aquilaris sinensis, was completed on 26
April 2022. Maintenance works for trees in holding nursery have commenced.
3.2.13 Monitoring of maintenance works for the
transplanted plant species was conducted at the holding nursery while in the
reporting period.
3.2.14
As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of
SSWSTW which are considered to be the plant species with conservative
importance for temporarily transplanted to the nursery at Kam Tin and
eventually be transplanted to Pui O Pumping Station.
4.1.1
Mitigation measures according to the environmental mitigation
implementation schedule in Annex A of EM&A Manual were generally
implemented by the Contractor. Hence,
the EM&A programme was considered effective and shall be maintained.
4.2.1
Environmental mitigation measures mentioned the EIA Report were weekly
reviewed and recorded in Weekly Environmental Site Audit Checklist. Also, a summary of the submission status of
the reporting quarter on submissions and measures mentioned in Environmental
Permit (EP-538/2017) are shown in Table 4.1.
Table 4.1 Summary of
submission status under EP-538/2017
|
EP Condition |
Submission |
Date of Latest Submission to EPD^ / EPD Approval# |
|
Condition 2.10 |
Waste Management Plan (Rev. 5) (electronic copy) |
4 April 2022# |
|
Condition 2.11 |
Submission of Preservation and/or Transplantation Plan for Plant
Species of Conservation Importance (Rev. 23) |
9 September 2022# |
|
Condition 2.12 |
Submission of Compensatory Woodland Planting Plan (Rev. 23) |
15 May 2023^ |
|
Condition 2.13 |
Silt Curtain Deployment Plan (Rev. 11) |
1 June 2022# |
|
Condition 2.14 |
Landscape Mitigation Plan |
To be confirmed |
|
Condition 2.15 |
Construction Noise Mitigation Plan (Rev. 20) |
4 August 2022# |
4.3.1
A summary of the submission status for the reporting period on licences
and/or permits on environmental protection pertinent to the Project is shown in
Table 4.2.
Table 4.2 Summary of the
current status on licences and/or permits on environmental protection pertinent
to the Project
|
Permits and/or Licences |
Permit. No. / Account No. |
Issued Date |
Valid Period & Expiry Date |
Status |
|
Notification
of Works Under APCO |
466408 |
14 Apr
2021 |
N/A |
Valid |
|
Wastewater Discharge Licence under Water Pollution Control Ordinance |
SSWSTW: WT00039636-2021 |
30 Dec
2021 |
30-12-2021
to 31-12-2026 |
Valid |
|
POPS: WT00039820-2021 |
31 Dec
2021 |
31-12-2021
to 31-12-2026 |
Valid |
|
|
SSWSTW:
Gravity Sewer & Raising Main: WT00042613-2022 |
09 Jan
2023 |
09-01-2023
to 31-01-2028 |
Valid |
|
|
Billing
account under Waste Disposal Ordinance |
Account
No.: 7040411 |
05 May
2021 |
N/A |
Valid |
|
Registration
as a Chemical Waste Producer |
0000-931-K3428-01 |
13 May
2021 |
N/A |
Valid |
|
Construction
Noise Permit under Noise Control Ordinance for SSWSTW |
GW-RS0657-23 |
9 Aug 2023 |
11-08-2023 to 08-02-2024 |
Valid |
|
Construction
Noise Permit under Noise Control Ordinance for POSPS |
GW-RS0822-23 |
25 Sep
2023 |
27-09-2023
to 26-03-2024 |
Valid |
|
Marine Dumping Permit (Dredged Sediment Requiring
Type 1 – Open Sea Disposal |
EP/MD/23-117 |
16 Oct
2023 |
17-10-2023
to 15-11-2023 |
Expired
after
15 Nov
2023 |
|
Ref. no.: 500024 |
23 Nov 2023 |
Nil |
In progress |
Note:
Only include those valid or under application; fill in “N/A” for non-applicable
item(s).
5.1.1
Noise monitoring was conducted at eight (8) noise monitoring stations (N12a, N12b, N13, N14, N15b, N16a, N16b and
N17) once per week in the reporting period.
5.1.2
School examination was taken place at N17 – Bui O Public School from 8
to 17 November 2023 in the reporting period. The limit level of noise
monitoring station N17-Bui O Public School was adjusted to 65dB(A) accordingly
during the period.
5.1.4
Noise monitoring results measured in the reporting period were reviewed
and summarised. Noise monitoring
graphical presentation can be referred to Appendix 5.1.
5.1.5
No action and limit level exceedances were recorded
in construction noise level in the reporting period.
5.2.1
Marine Water quality monitoring involves nine (9)
monitoring stations (seven impact & two control stations) three days per
week in the reporting period starting from 12 April 2022.
|
Date |
Marine-based construction
activities undertaken |
Mitigation measures implemented |
|
1/11/2023 |
No activity |
Nil |
|
3/11/2023 |
No activity |
Nil |
|
6/11/2023 |
No activity |
Nil |
|
8/11/2023 |
No activity |
Nil |
|
10/11/2023 |
Reparation
of Silt Curtain |
Remove
debris on the barges |
|
13/11/2023 |
Dredging |
Working
area was enclosed by silt curtain. |
|
15/11/2023 |
Borehole
Cleaning |
Working area was enclosed by
silt curtain. |
|
20/11/2023 |
Borehole
Cleaning |
Working area was enclosed by
silt curtain. |
|
22/11/2023 |
Borehole
Cleaning |
Working area was enclosed by
silt curtain. |
|
27/11/2023 |
No
Activity |
Nil |
|
29/11/2023 |
Pipe
Pulling |
Working area was enclosed by
silt curtain. |
|
1/12/2023 |
Pipe
Pulling |
Working area was enclosed by
silt curtain. |
|
5/12/2023 |
No
activities |
N/A |
|
7/12/2023 |
No
activities |
N/A |
|
9/12/2023 |
No
activities |
N/A |
|
11/12/2023 |
No
activities |
N/A |
|
13/12/2023 |
No
activities |
N/A |
|
15/12/2023 |
No
activities |
N/A |
|
18/12/2023 |
No
activities |
N/A |
|
20/12/2023 |
No
activities |
N/A |
|
22/12/2023 |
No
activities |
N/A |
|
25/12/2023 |
No
activities |
N/A |
5.2.7
For November 2023, borehole cleaning was conducted within fully enclosed
silt curtain at around 9:00 - 11:00 and 15:00 - 17:00 on 15 November 2023,
despite there was dredging works on 13 Nov 2023 at around 10:10 to 11:30, no
exceedances was recorded during mid-ebb (12:18) and mid-flood (17:40) tide on
13 Nov 2023. No dredging works on 15 Nov 2023, no exceedance was recorded on
same day during ebb tide from 13:08 to 13:12 at SR9. No exceedances was
recorded at the monitoring stations close to the marine works area e.g. SR4,
SR5 and SR6, no exceedances was recorded at the monitoring stations closed to
SR9 e.g. SR10 and SR12 on 13 and 15 Nov 2023. No exceedances was recorded in
the subsequent monitoring on 20 Nov 2023 both ebb and flood tide.
5.2.8
For December 2023, action level exceedances of Depth-averaged on
suspended solids (SS) was recorded at SR9, SR10, SR12 and SR15 on 1 Dec 2023
from 09:39 to 10:33 during flood tide on 1 Dec 2023, checking with contractor,
pipe pulling was conducted within fully enclosed silt curtain from 07:00 to
23:00, no damage recorded on the silt curtain, no dredging works on 1 Dec 2023.
Higher SS during flood tide was recorded from 9.5mg/L (SR6) to 18.3mg/L (CE),
no exceedance was recorded on same day during ebb tide from 15:00 to 15:53 at
SR9, SR10, SR12 and SR15. No exceedances was recorded at the monitoring
stations close to the marine works area e.g. SR4, SR5 and SR6 on 1 Dec 2023.
5.2.9
Reviewed the overall work situation and the mitigation measures
implemented by the Contactor, It can be concluded that the SS exceedances were
possibly due to natural variation or changes of water quality in the vicinity
of water quality monitoring station and considered that the all exceedances
were not related to Project works.
5.3.1
Transplanting of the trees of Aquilaris sinensis was completed on 26 April 2022. Maintenance
works for trees in holding nursery have commenced.
5.4.1
The quantities of waste for disposal in present
quarter are summarized in Table 5.1. The Quarterly Summary
Waste Flow Table is shown in Appendix
5.3.
Table 5.1 Summary of
Quantities of Waste Material (November, December 2023,
and January 2024)
|
Waste Type |
Quantity for reporting quarter |
Cumulative Quantity-to-Date |
|
Hard Rock and Large Broken Concrete (Inert) (in ‘000m3) |
0 |
0 |
|
Reused in this Contract (Inert) (in ‘000m3) |
0 |
0 |
|
Reused in other Projects (Inert) (in ‘000m3) |
0 |
0 |
|
Disposal as Public Fill (Inert) (in ‘000m3) |
2.85 |
16.62581 |
|
Metals (in ‘000kg) |
0.01 |
7.52830 |
|
Paper / Cardboard Packing (in ‘000kg) |
0.07 |
0.58868 |
|
Plastics (in ‘000kg) |
0.01 |
0.06726 |
|
Chemical Wastes (in ‘000kg) |
0 |
0 |
|
General Refuses (in ‘000kg) |
30.93 |
569.51 |
|
Marine Sediment (Type 1 – Open Sea Disposal) , m3 |
60.2 |
60.2 |
|
*: Further breakdown into sub-group if considered applicable; |
||
6.1.1
No environmental complaint, notification of summons and successful
prosecution regarding construction works was recorded in the reporting period. Table
6.1 summarized the complaints from project commencement till now.
Table 6.1 Summary of
Complaints
|
Date
of Notification from EPD |
Date
of Complaint |
Description
of Complaint |
Validity
of Complaint |
Close-Out
Date / Status |
|
26 May 2022 |
22 May 2022 |
A complaint is regarding noise
nuisance from marine site of San Shek Wan, Lantau Island. |
Based on the investigation, the works
activities of marine works did not result in any noise nuisance to Noise
Sensitive Receivers (NSRs), noise nuisance from the Project is unlikely to be
valid. |
The interim report was submitted to
EPD in June 2022. EPD replied no further comments on the final investigation
report on 13 July 2022. |
|
23 Dec 2022 |
21 Dec 2022 |
A complaint is regarding to the water quality for Pui O Beach, Lantau
Island. |
Based on the investigation, the works activities at POPS did not
result in any water quality impacts to the Pui O Beach. |
The interim report was submitted to EPD on 4 Jan 2023. |
6.1.2
No notification of summons and successful prosecution regarding
construction works were recorded in the reporting period.
6.1.3
Cumulative statistic on complaints and successful prosecutions are
summarized in Table 6.2 and Table 6.3 respectively.
Table 6.2 Cumulative
Statistics on Complaints
|
Reporting
Period |
No.
of Complaints |
|
Nov
2023 to Jan 2024 |
0 |
|
Project
commencement to the end of last reporting quarter |
2 |
|
Total |
2 |
Table 6.3 Cumulative
Statistics on Successful Prosecutions
|
Environmental
Parameters |
Cumulative
No. Brought Forward |
No.
of Successful Prosecutions this month (Offence Date) |
Cumulative
No. Project-to-Date |
|
Air |
- |
0 |
0 |
|
Noise |
- |
0 |
0 |
|
Water |
- |
0 |
0 |
|
Waste |
- |
0 |
0 |
|
Other |
- |
0 |
0 |
|
Total |
- |
0 |
0 |
7.1.1
In the reporting period, the principal work activities conducted are as
follow.
Table 7.1 Construction
Activities in Past 3 Months
|
November 2023 |
December 2023 |
January 2024 |
|
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk
Tsuen, South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Horizontal Directional Drilling (HDD) works at marine and SSWSTW ·
Removal works of Excavation and Lateral Support (ELS) ·
Excavation and Lateral Support (ELS) works ·
Superstructure Reinforced Concrete (RC) Works ·
Marine dredging |
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk
Tsuen, South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Horizontal Directional Drilling (HDD) works at marine and SSWSTW ·
Removal works of Excavation and Lateral Support (ELS) ·
Excavation and Lateral Support (ELS) works ·
Superstructure Reinforced Concrete (RC) Works |
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk
Tsuen, South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Horizontal Directional Drilling (HDD) works at marine and SSWSTW ·
Removal works of Excavation and Lateral Support (ELS) ·
Excavation and Lateral Support (ELS) works ·
Superstructure Reinforced Concrete (RC) Works |
7.1.2
The recommended mitigation measures for the past 3 months are listed
below:
·
Provide caring measures for the health, form and structural conditions for
transplant trees including Aquilaris sinensis in holding nursery;
·
Fully implement tree preservation works on site and holding nursery to
ensure compliance of relevant legislation and guidelines stated in EM&A
Manual.
·
Implementation of noise pollution control in accordance with
Construction Noise Mitigation Plan;
·
Dust control during dust generating works;
·
Adopt surface
drainage and sediment control facilities for sewage installation in village and
public roads;
·
Adopt temporary
drainage and sediment control facilities on Site;
·
Vehicle wheel-washing and body washing facilities should be provided at
the site entrance;
·
Regular water spraying on drilling and excavation works for dust
control; and
·
Proper waste handling, recycling and storage.
·
To inspect the
condition of silt curtains on regular basis, and after adverse weather
including any rainstorms and typhoons in wet season.
The implemented mitigation
measures are considered effective.
8.1.1
Noise monitoring was conducted at eight (8) noise monitoring stations
(N12a, N12b, N13, N14, N15b, N16a, N16b and N17) once per week in the reporting
period.
8.1.2
No action or limit level exceedance was recorded in construction noise
level in this present quarter.
8.2.1
Marine-based construction works commenced on 19 April 2022, water
quality monitoring was commenced on 12 April 2022.
8.2.2
Water quality monitoring on 17 & 24 Nov 2023, 20 & 22 Dec 2023
and 8 (mid-ebb) & 22 (mid-ebb and mid-flood) Jan 2024 were cancelled due to
Strong Monsoon Signal. Water quality monitoring on 24 January 2024 (mid ebb and
mid-flood) was cancelled due to sea condition taking personnel safety into
consideration.
8.2.3
In accordance with
the action level and limit level in Baseline Monitoring Report Rev. 9.2 agreed
by EPD on 2 September 2022, 5 action level and 0 limit level exceedances was
recorded in the reporting period. 1 action level exceedances on SS at SR9
during flood tide on 15 November 2023 was recorded. 4 action level
exceedances on SS at SR9, SR10, SR12 and SR15 during flood tide on 1 December
2023 were recorded. It can be concluded that the SS exceedances were possibly
due to natural variation or changes of water quality in the vicinity of water
quality monitoring station and considered that the exceedance was not related
to Project works.
8.3.1
Transplanting works for plant species, Aquilaris sinensis, was completed on 26 April 2022. Maintenance
works for trees in holding nursery have commenced.
8.3.2
Monitoring of maintenance works for the transplanted plant species was
conducted at the holding nursery while in the reporting period.
8.3.3
As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of
SSWSTW which are considered to be the plant species with conservative importance
for temporarily transplanted to the nursery at Kam Tin and eventually be
transplanted to Pui O Pumping Station.
8.4.1
No environmental non-compliance was recorded in present quarter.
8.5.1
There was no particular action taken since no non-compliance was
recorded in present quarter.