CONTRACT NO: SD 15/2022
Outlying
Island Sewerage Stage 2 – South Lantau Sewage Works – Environmental Team Services (2023
– 2024) Under Environmental Permit no. EP-538/2017
quarterly Environmental Monitoring & Audit summary
Report
August to october 2023
Revision 1
|
|
CLIENTS: |
|
|
Drainage Services Department |
Lam Environmental Services Limited 19/F Remex Centre, 42 Wong Chuk Hang Road, Hong Kong Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
|
|
|
Certified
by: |
|
|
_______________________________ Environmental
Team Leader Derek
Lo |
|
|
DATE: |
|
|
6 December 2023 |
|
|
|
1.1.......... Scope of the Report
1.2.......... Structure of the Report
2.1.......... Project Organization
and Key Contact Personnel
2.2.......... Construction Programme
3. A Brief Summary of EM&A
Requirements
3.1.......... Monitoring Parameters
3.2.......... Environmental Quality
Performance Limits
4.2.......... Environmental
Mitigation Measures
4.3.......... Environmental
monitoring requirements and contractual requirements
5. Monitoring Results Analysis
5.1.......... Noise Monitoring
5.2.......... Water Quality
Monitoring
5.3 Ecological Impact Monitoring……………………………………………..
5.4.......... Waste Management
6. Complaints, Notification of Summons
and Prosecution
7. Comments and Recommendations
lIST OF TABLES
Table 2.1 Contact
Details of Key Personnel
Table 4.1 Summary of submission status under
EP-538/2017
Table 5.1 Summary of Quantities of Waste
Material (August, September and October 2023)
Table 6.2 Cumulative Statistics on
Complaints
Table 6.3 Cumulative Statistics on
Successful Prosecutions
Table 7.1 Construction Activities in Past 3
Months
lIST OF FIGUREs
Figure
2.1 Project Organization Chart
Figure
5.1 Locations of Noise Monitoring
Station
Figure
5.2 Locations of Water Quality Monitoring Stations
lIST OF APPENDIces
Appendix
5.1 Noise Monitoring Graphical
Presentations
Appendix 5.2 Marine Water Quality Monitoring Graphical and Summary of Exceedance Presentations
Appendix
5.3 Quarterly Summary Waste Flow Table
EXECUTIVE SUMMARY
i.
This
is the Quarterly Environmental Monitoring and Audit (EM&A) Summary Report
– August
to October 2023 of
Outlying Islands Sewerage Stage
2 – South Lantau Sewerage Works under Environmental Permit no. EP-538/2017
(Hereafter as “the Project”). The
construction works of the Project was commenced on 3 November 2021 and the tentative completion date is Q1 2026. The
Quarterly EM&A Summary Report presents the environmental monitoring
findings and information recorded during the period of 01 August to 31 October 2023.
ii.
In
the reporting period, the principal work activities conducted are as follow:
|
August 2023 |
September 2023 |
October 2023 |
|
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk
Tsuen, South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Horizontal Directional Drilling (HDD) works at marine and SSWSTW ·
Removal works of Excavation and Lateral Support (ELS) ·
Excavation and Lateral Support (ELS) works ·
Superstructure Reinforced Concrete (RC) Works |
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk
Tsuen, South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Horizontal Directional Drilling (HDD) works at marine and SSWSTW ·
Removal works of Excavation and Lateral Support (ELS) ·
Excavation and Lateral Support (ELS) works ·
Superstructure Reinforced Concrete (RC) Works |
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk
Tsuen, South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Horizontal Directional Drilling (HDD) works at marine and SSWSTW ·
Removal works of Excavation and Lateral Support (ELS) ·
Excavation and Lateral Support (ELS) works ·
Superstructure Reinforced Concrete (RC) Works |
Exceedances of Action/Limit Levels
Noise Monitoring
iii.
Noise monitoring was conducted at eight (8) noise monitoring stations
(N12a, N12b, N13, N14, N15b, N16a, N16b and N17) once per week in the reporting
period.
iv.
No school examination was taken place at N17 – Bui O Public School in
the reporting period.
v.
No action and limit level exceedances were recorded in construction
noise level in the reporting period.
Water Quality Monitoring
vii.
Water quality monitoring on 1 and 8 September 2023 were cancelled due to
Typhoon Signal no. 8 and Black Rainstorm Signal respectively. Water quality monitoring on 7, 9 and 18
Oct 2023 were cancelled due to Strong Wind Signal no. 8, no. 3 and Strong
Monsoon Signal respectively. No substitution would be arranged for such
cancellation since it is impossible to maintain the monitoring frequency as
three times a week for the event of marine water quality monitoring
cancellation in between time with respect to the fact that not less than 36
hours interval shall be followed for two monitoring days as required by the
EM&A Manual Clause 5.1.6 (b) for the project.
viii.
In accordance with the action level and limit level in Baseline Monitoring
Report Rev. 9.2 agreed by EPD on 2 September 2022, 15 action level and 0 limit
level exceedances was recorded in the reporting period. 1 Action Level
exceedance on SS during flood tide on 9 August 2023 was recorded; 3 action
level exceedances on turbidity and SS during ebb tide on 20 October 2023 were
recorded; 2 action level exceedances on turbidity and 4 action level
exceedances on SS during flood tide were recorded on 23 October 2023, 1 action
level exceedances on turbidity and SS during ebb tide was recorded on 23
October 2023. It can be
concluded that the turbidity and SS exceedances were possibly due to natural
runoff from streams to the sea or sudden changed of water body in the reporting
period and non-project related.
Ecological Impact Monitoring
ix.
Transplanting works for plant species, Aquilaris sinensis, was completed on 26 April 2022. Maintenance
works for trees in holding nursery have commenced.
x.
As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of
SSWSTW which are considered to be the plant species with conservative
importance for temporarily transplanted to the nursery at Kam Tin and
eventually be transplanted to Pui O Pumping Station.
xi.
The weekly
site audit was carried out by ET include checking whether good site practices
are being properly implemented by the Contractor.
xii.
The extent of the work site boundaries was checked by the ET during the
weekly site audit.
xiii.
The retained tree (T035) Dalbergia assamica(南嶺黃檀) located within
the site boundary of the Construction of San Shek Wan Sewage Treatments Works
was collapsed on 2 Sep 2023 afternnon after typhoon “Saola”( Signal No.10). No
injury and significant damage were caused in the tree collapse incident. To
minimize obstruction to the public, the tree were subsequently sawn and
removed. Incident report for this case has been provided by the Contractor on
11 October 2023.
Complaint log
Notifications
of Any Summons and Successful Prosecutions
xv.
No environmental notification of any summons and
successful prosecution regarding the construction works was recorded in present quarter.
1.1.1.
Lam Environmental Services Limited (LES) has been appointed to work as
the Environmental Team (ET) under Environmental Permit (EP) no. EP-538/2017 to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Outlying Islands Sewerage Stage 2 - South Lantau
Sewerage Works (Register No.: AEIAR-210/2017).
1.1.2.
The Quarterly EM&A Summary Report was prepared according to Section 12.3
of the Project EM&A Manual.
Section 1 Introduction – details the scope and structure of the report
Section 2 Basic
Project Information – a synopsis of project
organization, programme contacts of key management, and a synopsis of work undertaken
in the reporting period.
Section 3 A
Brief Summary of EM&A requirements – including monitoring parameters, environmental quality
performance limits (Action and Limit levels); and environmental mitigation
measure, as recommended in the EIA Report.
Section 4 Implementation
Status – Advice on the implementation
status of environmental protection and pollution control/mitigation measures,
as recommended in the EIA Report and summarised in the updated implementation
schedule.
Section 5 Monitoring
Results Analysis – the trends of the
monitoring parameters in present quarter; advice on the solid and liquid waste
management status.
Section 6 Summary
of Non-Compliance (exceedances) of the environmental quality performance
limits, Complaints,
Notification of Summons and Successful Prosecutions
A
brief review of the reasons for and the implications of non-compliance and a
summary description of the actions taken and any follow-up procedures related
to earlier non-compliance.
A summary record
of all complaints received (written or verbal) for each media, liaison and
consultation undertaken, actions and follow-up procedures taken;
A summary record of
notifications of summons and successful prosecutions for breaches of the
current environmental protection/pollution control legislations, including
locations and nature of the breaches, investigation, follow-up actions taken
and results.
Section 7 Comments and Recommendations – such as effectiveness and efficiency of the mitigation
measures, improvement in the EM&A programme, if any.
Section 8 Conclusion
and Project Proponent’s contacts and hotline telephone number for the public to
make enquiries
2.1.1
Drainage Services Department is the overall project controllers for the
Project. For the construction phase of the Project, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues. Key personnel and contact particulars are
summarised in Figure
2.1 and Table 2.1:
Table 2.1 Contact Details of Key Personnel
|
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
|
Drainage
Services Department (DSD) |
The Engineer for the
Contract |
Engineer |
Mr. Silas Chan |
2594 7272 |
3104 6426 |
|
Binnies
Hong Kong Limited |
Engineer’s
Representative |
Resident
Engineer |
Mr. Kevin Chan |
3529 3013 |
- |
|
Kwan
Lee – Chun Wo Joint Venture |
Contractor
|
Site
Agent |
Mr. Charles Tse |
9270 3384 |
2744 6937 |
|
Environmental
Officer |
Ms. Shirley Kong |
5162 5933 |
|||
|
SMEC Hong Kong |
Independent Environmental
Checker (IEC) |
Independent Environmental Checker (IEC) |
Ms. Kitty Lee |
3995 8140 |
3995 8101 |
|
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Derek Lo |
2882 3939 |
2882 3331 |
2.2.1
The proposed sewerage works will collect the sewage generated from
the unsewered areas of Shui Hau, Tong Fuk,
Cheung Sha, San Shek Wan, Pui O and Ham Tin in South
Lantau (i.e. within the Project Catchment Area) and convey it to a proposed
sewage treatment works at San Shek Wan for treatment and disposal
into outer bay of Pui O/ Chi Ma Wan via a submarine outfall.
2.2.2
The entire Project are divided into three contracts. Contract No.
DC/2020/20 (the Contract) would have the following implementations as
demonstrated in Figure 2.2.
2.2.3
The major components of the Project under Environmental Permit (EP) (EP
No. EP-538/2017) comprises: (i) construction of sewage treatment works at San
Shek Wan (SSWSTW) and associated submarine outfall; (ii) construction of sewage
pumping station at Pui O (POSPS); (iii) village sewage works at Pui O; and (iv)
trunk sewers and rising mains on carriageways.
Noise
Monitoring
3.1.1 The construction noise level shall
be measured in terms of the A-weighted equivalent continuous sound pressure
level (Leq). Leq (30min) should be used as the monitoring
parameter. Supplementary information for data auditing, statistical results
such as L10 and L90 shall also be obtained for reference.
3.1.2 For impact monitoring for
construction of village sewers / rising main, noise monitoring should be
undertaken on weekly basis. One set of Leq
(30min) noise level as six consecutive Leq (5min) between
07:00-19:00 hours on normal weekdays.
Water Quality Monitoring
3.1.3 In construction phase, the levels
of dissolved oxygen (DO), temperature, turbidity and salinity should be measured
in-situ while suspended solids (SS)
is determined by laboratory analysis.
Ecological Impact Monitoring
3.1.4 Monitoring in the form of regular
site inspections should be carried out to ensure ecological measures in the
form of tree transplantation and establishment are being implemented and
effective for plant species of conservation importance (e.g. Aquilaria sinensis).
Noise
Monitoring
3.2.1 No action and limit level exceedances were
recorded in construction noise level in the reporting period.
Water
Quality Monitoring
3.2.2 Marine-based construction works had been
commenced since 19 April 2022, marine water quality monitoring was initialised
since 12 April 2022.
3.2.3 To support water quality monitoring, the
silt curtain deployment plan has minor updates to include an additional brand
of geosynthetic material as alternative for selection and adopt underwater
robot for inspecting condition of silt curtain.
3.2.4
Water quality monitoring on 1 and 8 September 2023 were cancelled due to
Typhoon Signal no. 8 and Black Rainstorm Signal respectively. Water quality
monitoring on 7, 9 and 18 October 2023 were cancelled due to Strong Wind Signal
no. 8, no. 3 and Strong Monsoon Signal respectively. No substitution would be
arranged for such cancellation since it is impossible to maintain the
monitoring frequency as three times a week for the event of marine water
quality monitoring cancellation in between time with respect to the fact that
not less than 36 hours interval shall be followed for two monitoring days as
required by the EM&A Manual Clause 5.1.6 (b) for the project.
3.2.5 Water quality monitoring is evaluated
against Action and Limit Levels. The derived Action and Limit Level proposed in
Baseline Monitoring Report Rev. 9.2 was agreed by EPD on 2 September 2022.
Action and Limit Levels of marine water quality monitoring have been set with
reference to the derived criteria as shown in Table 3.1 below.
Table 3.1 Action and Limit Levels of Water Quality
|
Parameters |
Action
Level |
Limit
Level |
|
Construction Phase Marine Water
Monitoring - derived criteria |
||
|
DO in mg/L B |
Surface and Middle:
5.8 mg/L Bottom: 5.9 mg/L |
Surface and Middle:
4 mg/L Bottom: 2 mg/L |
|
Turbidity in NTU (Depth-averaged A) C |
14.4 NTU and 20% exceedance of
value at any impact station compared with corresponding data from control
station D |
23.5 NTU and 30% exceedance of
value at any impact station compared with corresponding data from control
station D |
|
SS in mg/L (Depth-averaged A) C |
13.1 mg/L and 20% exceedance of
value at any impact station compared with corresponding data from control
station D |
30.4 mg/L and 30% exceedance of
value at any impact station compared with corresponding data from control
station D |
Notes
(with proposed amendments in AL/LL in underlined text):
A. “Depth-averaged”
is calculated by taking the arithmetic means of reading of all three depths.
B. For
DO, non-compliance of the water quality limits occurs when monitoring result is
lower than the limits.
C. For
SS and turbidity, non-compliance of the water quality limits occurs when
monitoring result is higher than the limits.
D. Action
Level and Limit Level with 95%-ile / 99%-ile derived from baseline data “and”
20% / 30% exceedance of control station proposed in Baseline Monitoring Report.
3.2.6 In accordance
with the action level and limit level in Baseline Monitoring Report Rev. 9.2
agreed by EPD on 2 September 2022, no action and limit level exceedance was
recorded in September 2023. 15 action level and 0 limit level exceedances was
recorded in the reporting period. 1 Action Level exceedance on SS during flood
tide on 9 August 2023 was recorded; 3 action level exceedances on turbidity and
SS during ebb tide on 20 October 2023 were recorded; 2 action level exceedances
on turbidity and 4 action level exceedances on SS during flood tide were
recorded on 23 October 2023, 1 action level exceedances on turbidity and SS
during ebb tide was recorded on 23 October 2023. It can be concluded that the
turbidity and SS exceedances were possibly due to natural runoff from streams
to the sea or sudden changed of water body in the reporting period and
non-project related.
3.2.7 Checked with contractors and RSS on the
marine works activities in the reporting period, the following activities were
recorded:
|
Date |
Marine-based construction
activities undertaken |
Mitigation measures implemented |
|
2/8/2023 |
No activity |
Nil |
|
4/8/2023 |
No activity |
Nil |
|
7/8/2023 |
No activity |
Nil |
|
9/8/2023 |
No activity |
Nil |
|
11/8/2023 |
No activity |
Nil |
|
14/8/2023 |
No activity |
Nil |
|
16/8/2023 |
Pilot hole reaming works |
Working area was enclosed by
silt curtain. |
|
18/8/2023 |
Pilot hole reaming works |
Working area was enclosed by
silt curtain. |
|
21/8/2023 |
Pilot hole reaming works |
Working area was enclosed by
silt curtain. |
|
23/8/2023 |
Tripping out works for marine
HDD2 works |
Working area was enclosed by
silt curtain. |
|
25/8/2023 |
Tripping out works for marine
HDD2 works |
Working area was enclosed by
silt curtain. |
|
28/8/2023 |
Smoothing for marine HDD2 works |
Working area was enclosed by
silt curtain. |
|
30/8/2023 |
Smoothing for marine HDD2 works |
Working area was enclosed by
silt curtain. |
|
1/9/2023 |
No
activities |
N/A |
|
4/9/2023 |
No
activities |
N/A |
|
6/9/2023 |
No
activities |
N/A |
|
8/9/2023 |
No
activities |
N/A |
|
11/9/2023 |
Repair
silt curtain |
Remove
debris on the barges. |
|
13/9/2023 |
Smoothing
for marine HDD2 works |
Working
area was enclosed by silt curtain. |
|
15/9/2023 |
Smoothing
for marine HDD2 works |
Working
area was enclosed by silt curtain. |
|
18/9/2023 |
Smoothing
for marine HDD2 works |
Working
area was enclosed by silt curtain. |
|
20/9/2023 |
Smoothing
for marine HDD2 works |
Working
area was enclosed by silt curtain. |
|
22/9/2023 |
Smoothing
for marine HDD2 works |
Working
area was enclosed by silt curtain. |
|
25/9/2023 |
Pull
out drill pipe for marine HDD2 works |
Working
area was enclosed by silt curtain. |
|
27/9/2023 |
Repair
drilling rig |
Remove
debris on the barge. |
|
29/9/2023 |
Trip
in at sea side for marine HDD2 works |
Working
area was enclosed by silt curtain. |
|
3/10/2023 |
Push in drill pipe |
Working area was enclosed by
silt curtain. |
|
5/10/2023 |
No activities |
Nil |
|
7/10/2023 |
No activities |
Nil |
|
11/10/2023 |
Push in drill pipe |
Working area was enclosed by
silt curtain. |
|
13/10/2023 |
Push in drill pipe |
Working area was enclosed by
silt curtain. |
|
16/10/2023 |
Maintenance |
Remove debris on the barges. |
|
20/10/2023 |
Smoothening |
Working area was enclosed by
silt curtain. |
|
23/10/2023 |
Holiday |
Nil |
|
25/10/2023 |
Smoothening |
Working area was enclosed by
silt curtain. |
|
27/10/2023 |
Smoothening |
Working area was enclosed by
silt curtain. |
|
30/10/2023 |
Smoothening |
Working area was enclosed by
silt curtain. |
3.2.8 Co-related the monitoring dates with
those days with recorded marine works activities, no marine dredging works were
active during the reporting period.
3.2.9 For the exceedances recorded in August
2023, no marine works during 17 July 2023 to 11 Aug 2023 due to the silt
curtain was found broken after Typhoon No. 8 on 17 July 2023 and repaired on 12
August 2023. No exceedance was recorded on same day during ebb tide from 07:13
to 07:16 and in the subsequent monitoring on 11 August 2023 both ebb and flood
tide.
3.2.10 For the exceedances recorded in October
2023, smoothening works within enclosed silt curtain on 20 October 2023. Higher
turbidity was recorded (>10 NTU) at all stations including control stations
during ebb and flood tide. No exceedances was recorded in the subsequent
monitoring at these stations on 23 Oct 2023, No marine works conducted on 23
October 2023. No exceedances was recorded in the subsequent monitoring at these
stations on 25 Oct 2023.
3.2.11 Reviewed the overall work situation and
the mitigation measures was implemented by the Contractor, it can be concluded
that the turbidity and SS exceedances in the reporting period was possibly due
to natural runoff from streams to the sea or sudden changed of water body.
Ecological monitoring
3.2.12 Transplanting works for plant species, Aquilaris sinensis, was completed on 26
April 2022. Maintenance works for trees in holding nursery have commenced.
3.2.13 Monitoring of maintenance works for the
transplanted plant species was conducted at the holding nursery while in the
reporting period.
3.2.14
The retained tree (T035) Dalbergia
assamica (南嶺黃檀) located
within the site boundary of the Construction of San Shek Wan Sewage Treatment
Works was collapsed on 2 Sep 2023 afternoon after typhoon “Saola” (Signal No.
10). Incident report for this case was provided by the Contractor on 11 October
2023. To minimize obstruction to the public, the collapsed tree has been
removed and delivered to Y Park.
3.2.15
As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of
SSWSTW which are considered to be the plant species with conservative
importance for temporarily transplanted to the nursery at Kam Tin and
eventually be transplanted to Pui O Pumping Station.
4.1.1
Mitigation measures according to the environmental mitigation
implementation schedule in Annex A of EM&A Manual were generally
implemented by the Contractor. Hence,
the EM&A programme was considered effective and shall be maintained.
4.2.1
Environmental mitigation measures mentioned the EIA Report were weekly
reviewed and recorded in Weekly Environmental Site Audit Checklist. Also, a summary of the submission status of
the reporting quarter on submissions and measures mentioned in Environmental
Permit (EP-538/2017) are shown in Table 4.1.
Table 4.1 Summary of
submission status under EP-538/2017
|
EP Condition |
Submission |
Date of Latest Submission to EPD^ / EPD Approval# |
|
Condition 2.10 |
Waste Management Plan (Rev. 5) (electronic copy) |
4 April 2022# |
|
Condition 2.11 |
Submission of Preservation and/or Transplantation Plan for Plant
Species of Conservation Importance (Rev. 23) |
9 September 2022# |
|
Condition 2.12 |
Submission of Compensatory Woodland Planting Plan (Rev. 23) |
15 May 2023^ |
|
Condition 2.13 |
Silt Curtain Deployment Plan (Rev. 11) |
1 June 2022# |
|
Condition 2.14 |
Landscape Mitigation Plan |
To be confirmed |
|
Condition 2.15 |
Construction Noise Mitigation Plan (Rev. 20) |
4 August 2022# |
4.3.1
A summary of the submission status for the reporting period on licences
and/or permits on environmental protection pertinent to the Project is shown in
Table 4.2.
Table 4.2 Summary of the
current status on licences and/or permits on environmental protection pertinent
to the Project
|
Permits and/or Licences |
Permit. No. / Account No. |
Issued Date |
Valid Period & Expiry Date |
Status |
|
Notification
of Works Under APCO |
466408 |
14 Apr
2021 |
N/A |
Valid |
|
Wastewater Discharge Licence under Water Pollution Control Ordinance |
SSWSTW: WT00039636-2021 |
30 Dec
2021 |
30-12-2021
to 31-12-2026 |
Valid |
|
POPS: WT00039820-2021 |
31 Dec
2021 |
31-12-2021
to 31-12-2026 |
Valid |
|
|
SSWSTW:
Gravity Sewer & Raising Main: WT00042613-2022 |
09 Jan
2023 |
09-01-2023
to 31-01-2028 |
Valid |
|
|
Billing
account under Waste Disposal Ordinance |
Account
No.: 7040411 |
05 May
2021 |
N/A |
Valid |
|
Registration
as a Chemical Waste Producer |
0000-931-K3428-01 |
13 May
2021 |
N/A |
Valid |
|
Construction
Noise Permit under Noise Control Ordinance for SSWSTW |
GW-RS0039-23 |
20 Jan 2023 |
03-02-2023 to 02-08-2023 |
Expired on 02 Aug 2023 |
|
GW-RS0657-23 |
9 Aug 2023 |
11-08-2023 to 08-02-2024 |
Valid |
|
|
Construction
Noise Permit under Noise Control Ordinance for POSPS |
GW-RS0230-23 |
7 Mar
2023 |
27-03-2023
to 26-09-2023 |
Expired
on 26 Sep 2023 |
|
GW-RS0822-23 |
25 Sep
2023 |
27-09-2023
to 26-03-2024 |
Valid |
|
|
Marine Dumping Permit (Dredged Sediment Requiring
Type 1 – Open Sea Disposal |
EP/MD/23-117 |
16 Oct 2023 |
17-10-2023 to 15-11-2023 |
Valid |
Note:
Only include those valid or under application; fill in “N/A” for non-applicable
item(s).
5.1.1
Noise monitoring was conducted at eight (8) noise monitoring stations (N12a, N12b, N13, N14, N15b, N16a, N16b and
N17) once per week in the reporting period.
5.1.2
No school examination was taken place at N17 – Bui O Public School in
the reporting period.
5.1.4
Noise monitoring results measured in the reporting period were reviewed
and summarised. Noise monitoring
graphical presentation can be referred to Appendix 5.1.
5.1.5
No action and limit level exceedances were recorded
in construction noise level in the reporting period.
5.2.1
Marine Water quality monitoring involves nine (9)
monitoring stations (seven impact & two control stations) three days per
week in the reporting period starting from 12 April 2022.
|
Date |
Marine-based construction
activities undertaken |
Mitigation measures implemented |
|
2/8/2023 |
No activity |
Nil |
|
4/8/2023 |
No activity |
Nil |
|
7/8/2023 |
No activity |
Nil |
|
9/8/2023 |
No activity |
Nil |
|
11/8/2023 |
No activity |
Nil |
|
14/8/2023 |
No activity |
Nil |
|
16/8/2023 |
Pilot hole reaming works |
Working area was enclosed by
silt curtain. |
|
18/8/2023 |
Pilot hole reaming works |
Working area was enclosed by
silt curtain. |
|
21/8/2023 |
Pilot hole reaming works |
Working area was enclosed by
silt curtain. |
|
23/8/2023 |
Tripping out works for marine
HDD2 works |
Working area was enclosed by
silt curtain. |
|
25/8/2023 |
Tripping out works for marine
HDD2 works |
Working area was enclosed by
silt curtain. |
|
28/8/2023 |
Smoothing for marine HDD2 works |
Working area was enclosed by
silt curtain. |
|
30/8/2023 |
Smoothing for marine HDD2 works |
Working area was enclosed by
silt curtain. |
|
1/9/2023 |
No
activities |
N/A |
|
4/9/2023 |
No
activities |
N/A |
|
6/9/2023 |
No
activities |
N/A |
|
8/9/2023 |
No
activities |
N/A |
|
11/9/2023 |
Repair
silt curtain |
Remove
debris on the barges. |
|
13/9/2023 |
Smoothing
for marine HDD2 works |
Working
area was enclosed by silt curtain. |
|
15/9/2023 |
Smoothing
for marine HDD2 works |
Working
area was enclosed by silt curtain. |
|
18/9/2023 |
Smoothing
for marine HDD2 works |
Working
area was enclosed by silt curtain. |
|
20/9/2023 |
Smoothing
for marine HDD2 works |
Working
area was enclosed by silt curtain. |
|
22/9/2023 |
Smoothing
for marine HDD2 works |
Working
area was enclosed by silt curtain. |
|
25/9/2023 |
Pull
out drill pipe for marine HDD2 works |
Working
area was enclosed by silt curtain. |
|
27/9/2023 |
Repair
drilling rig |
Remove
debris on the barge. |
|
29/9/2023 |
Trip
in at sea side for marine HDD2 works |
Working
area was enclosed by silt curtain. |
|
3/10/2023 |
Push in drill pipe |
Working area was enclosed by
silt curtain. |
|
5/10/2023 |
No activities |
Nil |
|
7/10/2023 |
No activities |
Nil |
|
11/10/2023 |
Push in drill pipe |
Working area was enclosed by
silt curtain. |
|
13/10/2023 |
Push in drill pipe |
Working area was enclosed by
silt curtain. |
|
16/10/2023 |
Maintenance |
Remove debris on the barges. |
|
20/10/2023 |
Smoothening |
Working area was enclosed by
silt curtain. |
|
23/10/2023 |
Holiday |
Nil |
|
25/10/2023 |
Smoothening |
Working area was enclosed by
silt curtain. |
|
27/10/2023 |
Smoothening |
Working area was enclosed by
silt curtain. |
|
30/10/2023 |
Smoothening |
Working area was enclosed by
silt curtain. |
5.3.1
Transplanting of the trees of Aquilaris sinensis was completed on 26 April 2022. Maintenance
works for trees in holding nursery have commenced.
5.4.1
The quantities of waste for disposal in present
quarter are summarized in Table 5.1. The Quarterly Summary
Waste Flow Table is shown in Appendix
5.3.
Table 5.1 Summary of
Quantities of Waste Material (August, September and October 2023)
|
Waste Type |
Quantity for reporting quarter |
Cumulative Quantity-to-Date |
|
Hard Rock and Large Broken Concrete (Inert) (in ‘000m3) |
0 |
0 |
|
Reused in this Contract (Inert) (in ‘000m3) |
0 |
0 |
|
Reused in other Projects (Inert) (in ‘000m3) |
0 |
0 |
|
Disposal as Public Fill (Inert) (in ‘000m3) |
2.14286 |
11.79968 |
|
Metals (in ‘000kg) |
0.009 |
7.51050 |
|
Paper / Cardboard Packing (in ‘000kg) |
0.0875 |
0.39678 |
|
Plastics (in ‘000kg) |
0.0068 |
0.03866 |
|
Chemical Wastes (in ‘000kg) |
0 |
0 |
|
General Refuses (in ‘000kg) |
38.36 |
506.56 |
|
*: Further breakdown into sub-group if considered applicable; |
||
6.1.1
No environmental complaint, notification of summons and successful
prosecution regarding construction works was recorded in the reporting period. Table
6.1 summarized the complaints from project commencement till now.
Table 6.1 Summary of
Complaints
|
Date
of Notification from EPD |
Date
of Complaint |
Description
of Complaint |
Validity
of Complaint |
Close-Out
Date / Status |
|
26 May 2022 |
22 May 2022 |
A complaint is regarding noise
nuisance from marine site of San Shek Wan, Lantau Island. |
Based on the investigation, the works
activities of marine works did not result in any noise nuisance to Noise
Sensitive Receivers (NSRs), noise nuisance from the Project is unlikely to be
valid. |
The interim report was submitted to
EPD in June 2022. EPD replied no further comments on the final investigation
report on 13 July 2022. |
|
23 Dec 2022 |
21 Dec 2022 |
A complaint is regarding to the water quality for Pui O Beach, Lantau
Island. |
Based on the investigation, the works activities at POPS did not
result in any water quality impacts to the Pui O Beach. |
The interim report was submitted to EPD on 4 Jan 2023. |
6.1.2
No notification of summons and successful prosecution regarding
construction works were recorded in the reporting period.
6.1.3
Cumulative statistic on complaints and successful prosecutions are
summarized in Table 6.2 and Table 6.3 respectively.
Table 6.2 Cumulative
Statistics on Complaints
|
Reporting
Period |
No.
of Complaints |
|
Aug
to Oct 2023 |
0 |
|
Project
commencement to the end of last reporting quarter |
2 |
|
Total |
2 |
Table 6.3 Cumulative
Statistics on Successful Prosecutions
|
Environmental
Parameters |
Cumulative
No. Brought Forward |
No.
of Successful Prosecutions this month (Offence Date) |
Cumulative
No. Project-to-Date |
|
Air |
- |
0 |
0 |
|
Noise |
- |
0 |
0 |
|
Water |
- |
0 |
0 |
|
Waste |
- |
0 |
0 |
|
Other |
- |
0 |
0 |
|
Total |
- |
0 |
0 |
7.1.1
In the reporting period, the principal work activities conducted are as
follow.
Table 7.1 Construction
Activities in Past 3 Months
|
August 2023 |
September 2023 |
October 2023 |
|
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk
Tsuen, South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Horizontal Directional Drilling (HDD) works at marine and SSWSTW ·
Removal works of Excavation and Lateral Support (ELS) ·
Excavation and Lateral Support (ELS) works ·
Superstructure Reinforced Concrete (RC) Works |
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk
Tsuen, South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Horizontal Directional Drilling (HDD) works at marine and SSWSTW ·
Removal works of Excavation and Lateral Support (ELS) ·
Excavation and Lateral Support (ELS) works ·
Superstructure Reinforced Concrete (RC) Works |
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk
Tsuen, South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Horizontal Directional Drilling (HDD) works at marine and SSWSTW ·
Removal works of Excavation and Lateral Support (ELS) ·
Excavation and Lateral Support (ELS) works ·
Superstructure Reinforced Concrete (RC) Works |
7.1.2
The recommended mitigation measures for the past 3 months are listed
below:
·
Provide caring measures for the health, form and structural conditions for
transplant trees including Aquilaris sinensis in holding nursery;
·
Fully implement tree preservation works on site and holding nursery to
ensure compliance of relevant legislation and guidelines stated in EM&A
Manual.
·
Implementation of noise pollution control in accordance with
Construction Noise Mitigation Plan;
·
Dust control during dust generating works;
·
Adopt surface
drainage and sediment control facilities for sewage installation in village and
public roads;
·
Adopt temporary
drainage and sediment control facilities on Site;
·
Vehicle wheel-washing and body washing facilities should be provided at
the site entrance;
·
Regular water spraying on drilling and excavation works for dust
control; and
·
Proper waste handling, recycling and storage.
·
To inspect the
condition of silt curtains on regular basis, and after adverse weather
including any rainstorms and typhoons in wet season.
The implemented mitigation
measures are considered effective.
8.1.1
Noise monitoring was conducted at eight (8) noise monitoring stations
(N12a, N12b, N13, N14, N15b, N16a, N16b and N17) once per week in the reporting
period.
8.1.2
No action or limit level exceedance was recorded in construction noise
level in this present quarter.
8.2.1
Marine-based construction works commenced on 19 April 2022, water
quality monitoring was commenced on 12 April 2022.
8.2.2
Water quality monitoring on 1 September 2023 and 8 September 2023 were
cancelled due to Typhoon Signal no. 8 and Black Rainstorm Signal respectively.
Water quality monitoring on 9 October 2023 and 18 October 2023 were cancelled
due to Strong Wind Signal no. 8 and Strong Monsoon Signal respectively.
8.2.3
In accordance with the action level and limit
level in Baseline Monitoring Report Rev. 9.2 agreed by EPD on 2 September 2022,
15 action level and 0 limit level exceedances was recorded in the reporting
period. 1 Action Level exceedance on SS during flood tide on 9 August 2023 was
recorded. 3 action level
exceedances on turbidity and SS during ebb tide on 20 October 2023 were
recorded; 2 action level exceedances on turbidity and 4 action level
exceedances on SS during flood tide were recorded on 23 October 2023, 1 action
level exceedances on turbidity and SS during ebb tide was recorded on 23
October 2023. Reviewed the overall work situation and the mitigation measures
was implemented by the Contractor, it can be concluded that the turbidity and
SS exceedances in the reporting period was possibly due to natural runoff from
streams to the sea or sudden changed of water body and non-project related.
8.3.1
Transplanting works for plant species, Aquilaris sinensis, was completed on 26 April 2022. Maintenance
works for trees in holding nursery have commenced.
8.3.2
Monitoring of maintenance works for the transplanted plant species was
conducted at the holding nursery while in the reporting period.
8.3.3
As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of
SSWSTW which are considered to be the plant species with conservative
importance for temporarily transplanted to the nursery at Kam Tin and
eventually be transplanted to Pui O Pumping Station.
8.3.4
The retained tree (T035) Dalbergia
assamica (南嶺黃檀) located within the site boundary of the
Construction of San Shek Wan Sewage Treatment Works was collapsed on 2 Sep 2023
afternoon after typhoon “Saola” (Signal No. 10). Incident report for this case
was provided by the Contractor on 11 October 2023. To minimize obstruction to
the public, the collapsed tree has been removed and delivered to Y Park.
8.4.1
No environmental non-compliance was recorded in present quarter.
8.5.1
There was no particular action taken since no non-compliance was
recorded in present quarter.
Appendix 5.3
Quarterly Summary Waste Flow Table