CONTRACT NO: SD 15/2022

Outlying Island Sewerage Stage 2 – South Lantau Sewage    Works – Environmental Team Services (2023 – 2024)

 

Under Environmental Permit no. EP-538/2017
 
quarterly Environmental Monitoring & Audit summary Report
 
May to july 2023
Revision 1


CLIENTS:

PREPARED BY:

 

 

Drainage Services Department

 

 

 

Lam Environmental Services Limited

 

19/F Remex Centre,

42 Wong Chuk Hang Road,

Hong Kong

 

 

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

_______________________________

 

Environmental Team Leader

 

Derek Lo

 

 

DATE:

 

 

17 August 2023

 

 


Table of contents

 

1      Introduction.. 6

1.1.......... Scope of the Report 6

1.2.......... Structure of the Report 6

2.     Basic Project Information.. 8

2.1.......... Project Organization and Key Contact Personnel 8

2.2.......... Construction Programme. 8

3.     A Brief Summary of EM&A Requirements. 10

3.1.......... Monitoring Parameters. 10

3.2.......... Environmental Quality Performance Limits. 10

4.     Implementation Status. 13

4.1.......... Advice on the implementation status of environmental protection and pollution control/mitigation measures. 13

4.2.......... Environmental Mitigation Measures. 13

4.3.......... Environmental monitoring requirements and contractual requirements. 13

5.     Monitoring Results Analysis. 15

5.1.......... Noise Monitoring. 15

5.2.......... Water Quality Monitoring. 15

5.3            Ecological Impact Monitoring……………………………………………..16

5.4.......... Waste Management 16

6.     Complaints, Notification of Summons and Prosecution.. 18

7.     Comments and Recommendations. 20

8.     Conclusion.. 22


lIST OF TABLES

 

Table 2.1       Contact Details of Key Personnel

Table 4.1       Summary of submission status under EP-538/2017

Table 4.2       Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 5.1       Summary of Quantities of Waste Material (May, June and July 2023)

Table 6.2       Cumulative Statistics on Complaints

Table 6.3       Cumulative Statistics on Successful Prosecutions

Table 7.1       Construction Activities in Past 3 Months

 

 

lIST OF FIGUREs

 

Figure 2.1    Project Organization Chart

Figure 2.2    Master Layout Plan

Figure 5.1   Locations of Noise Monitoring Station

Figure 5.2   Locations of Water Quality Monitoring Stations

 

 

lIST OF APPENDIces

 

Appendix 5.1    Noise Monitoring Graphical Presentations

Appendix 5.2   Marine Water Quality Monitoring Graphical and Summary of Exceedance Presentations

Appendix 5.3    Quarterly Summary Waste Flow Table

 


 

EXECUTIVE SUMMARY

       i.        This is the Quarterly Environmental Monitoring and Audit (EM&A) Summary Report – May to July 2023 of Outlying Islands Sewerage Stage 2 – South Lantau Sewerage Works under Environmental Permit no. EP-538/2017 (Hereafter as “the Project”).  The construction works of the Project was commenced on 3 November 2021 and the tentative completion date is Q1 2026.  The Quarterly EM&A Summary Report presents the environmental monitoring findings and information recorded during the period of 01 May to 31 July 2023.  

 

      ii.        In the reporting period, the principal work activities conducted are as follow:

May 2023

June 2023

July 2023

·         Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau road, Pui O Beach

·         Excavation and site formation at San Shek Wan Sewage Treatment Works (SSWSTW) and Pui O Sewage Pumping Station (POSPS)

·         Horizontal Directional Drilling (HDD) works at marine and SSWSTW

·         Removal works of Excavation and Lateral Support (ELS)

·         Superstructure Reinforced Concrete (RC) Works

 

·         Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau road, Pui O Beach

·         Excavation and site formation at San Shek Wan Sewage Treatment Works (SSWSTW) and Pui O Sewage Pumping Station (POSPS)

·         Horizontal Directional Drilling (HDD) works at marine and SSWSTW

·         Removal works of Excavation and Lateral Support (ELS)

·         Excavation and Lateral Support (ELS) works

·         Superstructure Reinforced Concrete (RC) Works

 

·         Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau road, Pui O Beach

·         Excavation and site formation at San Shek Wan Sewage Treatment Works (SSWSTW) and Pui O Sewage Pumping Station (POSPS)

·         Horizontal Directional Drilling (HDD) works at marine and SSWSTW

·         Removal works of Excavation and Lateral Support (ELS)

·         Excavation and Lateral Support (ELS) works

·         Superstructure Reinforced Concrete (RC) Works

 

 

Exceedances of Action/Limit Levels

Noise Monitoring

     iii.        Noise monitoring was conducted at eight (8) noise monitoring stations (N12a, N12b, N13, N14, N15b, N16a, N16b and N17) once per week in the reporting period.

     iv.        School examination was taken place at N17 – Bui O Public School from 12 to 14 June 2023 in the reporting period, the limit level shall be adjusted to 65dB(A) during this period.

      v.        No action and limit level exceedances were recorded in construction noise level in the reporting period.

Water Quality Monitoring

     vi.        Marine-based construction works commenced on 19 April 2022. Water quality monitoring was conducted at nine (9) monitoring stations (seven impact & two control stations) three days per week in the reporting period starting from 12 April 2022. HDD casing works commenced on 30 May 2022.

    vii.        Water quality monitoring on 17 July 2023 was cancelled due to Typhoon Signal no. 8. No substitution would be arranged for such cancellation since it is impossible to maintain the monitoring frequency as three times a week for the event of marine water quality monitoring cancellation in between time with respect to the fact that not less than 36 hours interval shall be followed for two monitoring days as required by the EM&A Manual Clause 5.1.6 (b) for the project.

   viii.        In accordance with the action level and limit level in Baseline Monitoring Report Rev. 9.2 agreed by EPD on 2 September 2022, 1 action level at SR4 and 0 limit level exceedances on SS was recorded in the reporting period. It can be concluded that the SS exceedances were possibly due to natural runoff from streams to the sea in the reporting period.

     ix.        Action Level exceedances at SR4 was recorded on 12 June 2023 on SS during ebb tide. No Limit Level exceedances recorded in the reporting period. Co-related the monitoring dates with those days with recorded marine works activities, no marine dredging works were active during the reporting period. Pilot hole drilling on 12 June 2023 within the fully enclosed silt curtain started from 09:20 to 09:36 and 16:00 to 18:40. Water quality monitoring at SR4 was conducted at 07:59 to 08:02 which was before the pilot hole drilling works. No exceedance was recorded on same day during flood tide at 13:12 to 13:15 and in the subsequent monitoring on 14 June 2023 both ebb and flood tide. Reviewed the overall work situation and the mitigation measures was implemented by the Contractor, it can be concluded that the SS exceedances at SR4 was possibly due to natural runoff from streams to the sea or sudden changed of water body as a result of frequent rainfall as recorded in the reporting month (Amber rainstorm warning signal recorded on 10 June 2023, heavy showers recorded on 11 June 2023 and rainstorm recorded during water quality monitoring on 12 June 2023).

 

Ecological Impact Monitoring

      x.        Transplanting works for plant species, Aquilaris sinensis, was completed on 26 April 2022. Maintenance works for trees in holding nursery have commenced.

     xi.        As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of SSWSTW which are considered to be the plant species with conservative importance for temporarily transplanted to the nursery at Kam Tin and eventually be transplanted to Pui O Pumping Station.

    xii.        The weekly site audit was carried out by ET include checking whether good site practices are being properly implemented by the Contractor.

   xiii.        The extent of the work site boundaries was checked by the ET during the weekly site audit.

Complaint log

   xiv.        No environmental complaint regarding the construction works was recorded in the reporting period..

 

Notifications of Any Summons and Successful Prosecutions

    xv.        No environmental notification of any summons and successful prosecution regarding the construction works was recorded in present quarter.

 

1      Introduction

1.1          Scope of the Report

1.1.1.     Lam Environmental Services Limited (LES) has been appointed to work as the Environmental Team (ET) under Environmental Permit (EP) no. EP-538/2017 to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Outlying Islands Sewerage Stage 2 - South Lantau Sewerage Works (Register No.: AEIAR-210/2017).

1.1.2.     The Quarterly EM&A Summary Report was prepared according to Section 12.3 of the Project EM&A Manual.

1.2          Structure of the Report

Section 1        Introduction – details the scope and structure of the report

 

Section 2        Basic Project Information – a synopsis of project organization, programme contacts of key management, and a synopsis of work undertaken in the reporting period.

           

Section 3        A Brief Summary of EM&A requirements – including monitoring parameters, environmental quality performance limits (Action and Limit levels); and environmental mitigation measure, as recommended in the EIA Report.

                      

Section 4        Implementation Status – Advice on the implementation status of environmental protection and pollution control/mitigation measures, as recommended in the EIA Report and summarised in the updated implementation schedule.

 

Section 5        Monitoring Results Analysis – the trends of the monitoring parameters in present quarter; advice on the solid and liquid waste management status.

                      

Section 6        Summary of Non-Compliance (exceedances) of the environmental quality performance limits, Complaints, Notification of Summons and Successful Prosecutions

A brief review of the reasons for and the implications of non-compliance and a summary description of the actions taken and any follow-up procedures related to earlier non-compliance.

A summary record of all complaints received (written or verbal) for each media, liaison and consultation undertaken, actions and follow-up procedures taken;

A summary record of notifications of summons and successful prosecutions for breaches of the current environmental protection/pollution control legislations, including locations and nature of the breaches, investigation, follow-up actions taken and results.

                      

Section 7        Comments and Recommendations – such as effectiveness and efficiency of the mitigation measures, improvement in the EM&A programme, if any.

 

Section 8        Conclusion and Project Proponent’s contacts and hotline telephone number for the public to make enquiries

2.         Basic Project Information

2.1          Project Organization and Key Contact Personnel

2.1.1       Drainage Services Department is the overall project controllers for the Project. For the construction phase of the Project, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.  Key personnel and contact particulars are summarised in Figure 2.1 and Table 2.1:

Table 2.1 Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

Drainage Services Department (DSD)

The Engineer for the Contract

Engineer

Mr. Silas Chan

2594 7272

3104 6426

Binnies Hong Kong Limited

Engineer’s Representative

Resident Engineer

Mr. Kevin Chan

3529 3013

-

Kwan Lee – Chun Wo Joint Venture

Contractor

Site Agent

Mr. Charles Tse

9270 3384

2744 6937

Environmental Officer

Ms. Shirley Kong

5162 5933

SMEC Hong Kong

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Ms. Kitty Lee

3995 8140

3995 8101

Lam Environmental Services Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Derek Lo

2882 3939

2882 3331

 

2.2          Construction Programme

2.2.1       The proposed sewerage works will collect the sewage generated from the unsewered areas of Shui Hau, Tong Fuk, Cheung Sha, San Shek Wan, Pui O and Ham Tin in South Lantau (i.e. within the Project Catchment Area) and convey it to a proposed sewage treatment works at San Shek Wan for treatment and disposal into outer bay of Pui O/ Chi Ma Wan via a submarine outfall.

2.2.2       The entire Project are divided into three contracts. Contract No. DC/2020/20 (the Contract) would have the following implementations as demonstrated in Figure 2.2.

2.2.3       The major components of the Project under Environmental Permit (EP) (EP No. EP-538/2017) comprises: (i) construction of sewage treatment works at San Shek Wan (SSWSTW) and associated submarine outfall; (ii) construction of sewage pumping station at Pui O (POSPS); (iii) village sewage works at Pui O; and (iv) trunk sewers and rising mains on carriageways.

 

3.      A Brief Summary of EM&A Requirements

3.1  Monitoring Parameters

Noise Monitoring

3.1.1       The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30min) should be used as the monitoring parameter. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

3.1.2       For impact monitoring for construction of village sewers / rising main, noise monitoring should be undertaken on weekly basis.  One set of Leq (30min) noise level as six consecutive Leq (5min) between 07:00-19:00 hours on normal weekdays.

Water Quality Monitoring

3.1.3       In construction phase, the levels of dissolved oxygen (DO), temperature, turbidity and salinity should be measured in-situ while suspended solids (SS) is determined by laboratory analysis.

Ecological Impact Monitoring

3.1.4       Monitoring in the form of regular site inspections should be carried out to ensure ecological measures in the form of tree transplantation and establishment are being implemented and effective for plant species of conservation importance (e.g. Aquilaria sinensis).

3.2  Environmental Quality Performance Limits

Noise Monitoring

3.2.1       No action and limit level exceedances were recorded in construction noise level in the reporting period.

Water Quality Monitoring

3.2.2       Marine-based construction works had been commenced since 19 April 2022, marine water quality monitoring was initialised since 12 April 2022.

3.2.3       To support water quality monitoring, the silt curtain deployment plan has minor updates to include an additional brand of geosynthetic material as alternative for selection and adopt underwater robot for inspecting condition of silt curtain.

3.2.4       Water quality monitoring on 17 July 2023 was cancelled due to Typhoon Signal no. 8. No substitution would be arranged for such cancellation since it is impossible to maintain the monitoring frequency as three times a week for the event of marine water quality monitoring cancellation in between time with respect to the fact that not less than 36 hours interval shall be followed for two monitoring days as required by the EM&A Manual Clause 5.1.6 (b) for the project.

3.2.5       Water quality monitoring is evaluated against Action and Limit Levels. The derived Action and Limit Level proposed in Baseline Monitoring Report Rev. 9.2 was agreed by EPD on 2 September 2022. Action and Limit Levels of marine water quality monitoring have been set with reference to the derived criteria as shown in Table 3.1 below.

Table 3.1     Action and Limit Levels of Water Quality

Parameters

Action Level

Limit Level

Construction Phase Marine Water Monitoring - derived criteria

DO in mg/L B

Surface and Middle: 5.8 mg/L

Bottom: 5.9 mg/L

Surface and Middle: 4 mg/L

Bottom: 2 mg/L

Turbidity in NTU

(Depth-averaged A) C

14.4 NTU and

20% exceedance of value at any impact station compared with corresponding data from control station D

23.5 NTU and

30% exceedance of value at any impact station compared with corresponding data from control station D

SS in mg/L

(Depth-averaged AC

13.1 mg/L and

20% exceedance of value at any impact station compared with corresponding data from control station D

30.4 mg/L and

30% exceedance of value at any impact station compared with corresponding data from control station D

Notes (with proposed amendments in AL/LL in underlined text):

A. “Depth-averaged” is calculated by taking the arithmetic means of reading of all three depths.

B.  For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

C. For SS and turbidity, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

D. Action Level and Limit Level with 95%-ile / 99%-ile derived from baseline data “and” 20% / 30% exceedance of control station proposed in Baseline Monitoring Report.

3.2.6       In accordance with the action level and limit level in Baseline Monitoring Report Rev. 9.2 agreed by EPD on 2 September 2022, 1 action level at SR4 and 0 limit level exceedances on SS was recorded in the reporting period. It can be concluded that the SS exceedances were possibly due to natural runoff from streams to the sea in the reporting period.

3.2.7       Action Level exceedances at SR4 was recorded on 12 June 2023 on SS during ebb tide. No Limit Level exceedances recorded in the reporting period. Co-related the monitoring dates with those days with recorded marine works activities, no marine dredging works were active during the reporting period. Pilot hole drilling on 12 June 2023 within the fully enclosed silt curtain started from 09:20 to 09:36 and 16:00 to 18:40. Water quality monitoring at SR4 was conducted at 07:59 to 08:02 which was before the pilot hole drilling works. No exceedance was recorded on same day during flood tide at 13:12 to 13:15 and in the subsequent monitoring on 14 June 2023 both ebb and flood tide. Reviewed the overall work situation and the mitigation measures was implemented by the Contractor, it can be concluded that the SS exceedances at SR4 was possibly due to natural runoff from streams to the sea or sudden changed of water body as a result of frequent rainfall as recorded in the reporting month (Amber rainstorm warning signal recorded on 10 June 2023, heavy showers recorded on 11 June 2023 and rainstorm recorded during water quality monitoring on 12 June 2023).

Ecological monitoring

3.2.8       Transplanting works for plant species, Aquilaris sinensis, was completed on 26 April 2022. Maintenance works for trees in holding nursery have commenced.

3.2.9       Monitoring of maintenance works for the transplanted plant species was conducted at the holding nursery while in the reporting period.

3.2.10    As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of SSWSTW which are considered to be the plant species with conservative importance for temporarily transplanted to the nursery at Kam Tin and eventually be transplanted to Pui O Pumping Station.

4.      Implementation Status

4.1  Advice on the implementation status of environmental protection and pollution control/mitigation measures

4.1.1       Mitigation measures according to the environmental mitigation implementation schedule in Annex A of EM&A Manual were generally implemented by the Contractor.  Hence, the EM&A programme was considered effective and shall be maintained.               

4.2  Environmental Mitigation Measures

4.2.1       Environmental mitigation measures mentioned the EIA Report were weekly reviewed and recorded in Weekly Environmental Site Audit Checklist.  Also, a summary of the submission status of the reporting quarter on submissions and measures mentioned in Environmental Permit (EP-538/2017) are shown in Table 4.1.

Table 4.1 Summary of submission status under EP-538/2017

EP Condition

Submission

Date of Latest Submission to EPD^ / EPD Approval#

Condition 2.10

Waste Management Plan (Rev. 5)

(electronic copy)

4 April 2022#

Condition 2.11

Submission of Preservation and/or Transplantation Plan for Plant Species of Conservation Importance (Rev. 23)

9 September 2022#

Condition 2.12

Submission of Compensatory Woodland Planting Plan (Rev. 23)

15 May 2023^

Condition 2.13

Silt Curtain Deployment Plan (Rev. 11)

1 June 2022#

Condition 2.14

Landscape Mitigation Plan

To be confirmed

Condition 2.15

Construction Noise Mitigation Plan (Rev. 20)

4 August 2022#

 

4.3  Environmental monitoring requirements and contractual requirements

4.3.1       A summary of the submission status for the reporting period on licences and/or permits on environmental protection pertinent to the Project is shown in Table 4.2.

Table 4.2 Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Permit. No. / Account No.

Issued Date

Valid Period & Expiry Date

Status

Notification of Works Under APCO

466408

14 Apr 2021

N/A

Valid

Wastewater Discharge Licence under Water Pollution Control Ordinance

SSWSTW:

WT00039636-2021

30 Dec 2021

30-12-2021 to 31-12-2026

Valid

POPS:

WT00039820-2021

31 Dec 2021

31-12-2021 to 31-12-2026

Valid

SSWSTW: Gravity Sewer & Raising Main:

WT00042613-2022

09 Jan 2023

09-01-2023 to 31-01-2028

Valid

Billing account under Waste Disposal Ordinance

Account No.: 7040411

05 May 2021

N/A

Valid

Registration as a Chemical Waste Producer

0000-931-K3428-01

13 May 2021

N/A

Valid

Construction Noise Permit under Noise Control Ordinance for SSWSTW

GW-RS0039-23

20 Jan 2023

03-02-2023 to 02-08-2023

Valid

Construction Noise Permit under Noise Control Ordinance for POSPS

GW-RS0230-23

7 Mar 2023

27-03-2023 to 26-09-2023

Valid

  Note: Only include those valid or under application; fill in “N/A” for non-applicable item(s).

 

 

5.      Monitoring Results Analysis

5.1    Noise Monitoring

5.1.1       Noise monitoring was conducted at eight (8) noise monitoring stations (N12a, N12b, N13, N14, N15b, N16a, N16b and N17) once per week in the reporting period.

5.1.2       School examination was taken place at N17 – Bui O Public School from 12 to 14 June 2023 in the reporting period, the limit level shall be adjusted to 65dB(A) during this period.

5.1.3       Noise monitoring location plans with sensitive receivers are shown in Figure 5.1.

5.1.4       Noise monitoring results measured in the reporting period were reviewed and summarised.  Noise monitoring graphical presentation can be referred to Appendix 5.1.

5.1.5       No action and limit level exceedances were recorded in construction noise level in the reporting period.

5.2    Marine Water Quality Monitoring

5.2.1       Marine Water quality monitoring involves nine (9) monitoring stations (seven impact & two control stations) three days per week in the reporting period starting from 12 April 2022.

5.2.2       Marine Water monitoring location plans with sensitive receivers are shown in Figure 5.2.

5.2.3       Water quality monitoring is evaluated against Action and Limit Levels. The derived Action and Limit Level proposed in Baseline Monitoring Report Rev. 9.2 was agreed by EPD on 2 September 2022.

5.2.4       Water quality monitoring 17 July 2023 was cancelled due to Typhoon Signal no. 8. No substitution would be arranged for such cancellation since it is impossible to maintain the monitoring frequency as three times a week for the event of marine water quality monitoring cancellation in between time with respect to the fact that not less than 36 hours interval shall be followed for two monitoring days as required by the EM&A Manual Clause 5.1.6 (b) for the project.

5.2.5       In accordance with the action level and limit level in Baseline Monitoring Report Rev. 9.2 agreed by EPD on 2 September 2022, 1 action level at SR4 and 0 limit level exceedances on SS was recorded in the reporting period. It can be concluded that the SS exceedances were possibly due to natural runoff from streams to the sea in the reporting period.

5.2.6       Action Level exceedances at SR4 was recorded on 12 June 2023 on SS during ebb tide. No Limit Level exceedances recorded in the reporting period. Co-related the monitoring dates with those days with recorded marine works activities, no marine dredging works were active during the reporting period. Pilot hole drilling on 12 June 2023 within the fully enclosed silt curtain started from 09:20 to 09:36 and 16:00 to 18:40. Water quality monitoring at SR4 was conducted at 07:59 to 08:02 which was before the pilot hole drilling works. No exceedance was recorded on same day during flood tide at 13:12 to 13:15 and in the subsequent monitoring on 14 June 2023 both ebb and flood tide. Reviewed the overall work situation and the mitigation measures was implemented by the Contractor, it can be concluded that the SS exceedances at SR4 was possibly due to natural runoff from streams to the sea or sudden changed of water body as a result of frequent rainfall as recorded in the reporting month (Amber rainstorm warning signal recorded on 10 June 2023, heavy showers recorded on 11 June 2023 and rainstorm recorded during water quality monitoring on 12 June 2023).

5.2.7       Marine water quality monitoring results measured in this reporting period are reviewed and summarized. Details of marine water quality monitoring graphical presentation and the summary of exceedance of action and /limit levels of WQM can be referred to Appendix 5.2.

 

5.3    Ecological Impact Monitoring

5.3.1       Transplanting of the trees of Aquilaris sinensis was completed on 26 April 2022. Maintenance works for trees in holding nursery have commenced.

5.3.2       Monitoring of maintenance works for the transplanted plant species was conducted at the holding nursery while in the reporting period.

5.3.3       As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of SSWSTW which are considered to be the plant species with conservative importance for temporarily transplanted to the nursery at Kam Tin and eventually be transplanted to Pui O Pumping Station.

 

5.4       Waste Management

5.4.1       The quantities of waste for disposal in present quarter are summarized in Table 5.1. The Quarterly Summary Waste Flow Table is shown in Appendix 5.3.

 

Table 5.1 Summary of Quantities of Waste Material (May, June and July 2023)

Waste Type

Quantity for reporting quarter

Cumulative Quantity-to-Date

Hard Rock and Large Broken Concrete (Inert)

(in ‘000m3)

0

0

Reused in this Contract (Inert)

(in ‘000m3)

0

0

Reused in other Projects (Inert)

(in ‘000m3)

0

0

Disposal as Public Fill (Inert)

(in ‘000m3)

2.14286

11.79968

Metals (in ‘000kg)

0.009

 

7.51050

Paper / Cardboard Packing

(in ‘000kg)

0.0875

0.39678

Plastics

(in ‘000kg)

0.0068

0.03866

Chemical Wastes

(in ‘000kg)

0

0

General Refuses

(in ‘000kg)

38.36

506.56

*: Further breakdown into sub-group if considered applicable;

 

 

6.      Complaints, Notification of Summons and Prosecution

6.1.1       No environmental complaint, notification of summons and successful prosecution regarding construction works was recorded in the reporting period. Table 6.1 summarized the complaints from project commencement till now.

Table 6.1      Summary of Complaints

Date of Notification from EPD

Date of Complaint

Description of Complaint

Validity of Complaint

Close-Out Date / Status

26 May 2022

22 May 2022

A complaint is regarding noise nuisance from marine site of San Shek Wan, Lantau Island.

Based on the investigation, the works activities of marine works did not result in any noise nuisance to Noise Sensitive Receivers (NSRs), noise nuisance from the Project is unlikely to be valid.

The interim report was submitted to EPD in June 2022. EPD replied no further comments on the final investigation report on 13 July 2022.

23 Dec 2022

21 Dec 2022

A complaint is regarding to the water quality for Pui O Beach, Lantau Island.

Based on the investigation, the works activities at POPS did not result in any water quality impacts to the Pui O Beach.

The interim report was submitted to EPD on 4 Jan 2023.

6.1.2       No notification of summons and successful prosecution regarding construction works were recorded in the reporting period.

6.1.3       Cumulative statistic on complaints and successful prosecutions are summarized in Table 6.2 and Table 6.3 respectively.

Table 6.2 Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

May to July 2023

0

Project commencement to the end of last reporting quarter

2

Total

2

 

Table 6.3 Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this month (Offence Date)

Cumulative No. Project-to-Date

Air

-

0

0

Noise

-

0

0

Water

-

0

0

Waste

-

0

0

Other

-

0

0

Total

-

0

0

 

7.      Comments and Recommendations

7.1.1       In the reporting period, the principal work activities conducted are as follow.

Table 7.1 Construction Activities in Past 3 Months

May 2023

June 2023

July 2023

·         Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau road, Pui O Beach

·         Excavation and site formation at San Shek Wan Sewage Treatment Works (SSWSTW) and Pui O Sewage Pumping Station (POSPS)

·         Horizontal Directional Drilling (HDD) works at marine and SSWSTW

·         Removal works of Excavation and Lateral Support (ELS)

·         Superstructure Reinforced Concrete (RC) Works

 

·         Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau road, Pui O Beach

·         Excavation and site formation at San Shek Wan Sewage Treatment Works (SSWSTW) and Pui O Sewage Pumping Station (POSPS)

·         Horizontal Directional Drilling (HDD) works at marine and SSWSTW

·         Removal works of Excavation and Lateral Support (ELS)

·         Excavation and Lateral Support (ELS) works

·         Superstructure Reinforced Concrete (RC) Works

 

·         Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau road, Pui O Beach

·         Excavation and site formation at San Shek Wan Sewage Treatment Works (SSWSTW) and Pui O Sewage Pumping Station (POSPS)

·         Horizontal Directional Drilling (HDD) works at marine and SSWSTW

·         Removal works of Excavation and Lateral Support (ELS)

·         Excavation and Lateral Support (ELS) works

·         Superstructure Reinforced Concrete (RC) Works

 

7.1.2       The recommended mitigation measures for the past 3 months are listed below:

·         Provide caring measures for the health, form and structural conditions for transplant trees including Aquilaris sinensis in holding nursery;

·         Fully implement tree preservation works on site and holding nursery to ensure compliance of relevant legislation and guidelines stated in EM&A Manual.

·         Implementation of noise pollution control in accordance with Construction Noise Mitigation Plan;

·         Dust control during dust generating works;

·         Adopt surface drainage and sediment control facilities for sewage installation in village and public roads;

·         Adopt temporary drainage and sediment control facilities on Site;

·         Vehicle wheel-washing and body washing facilities should be provided at the site entrance;

·         Regular water spraying on drilling and excavation works for dust control; and

·         Proper waste handling, recycling and storage.

·         To inspect the condition of silt curtains on regular basis, and after adverse weather including any rainstorms and typhoons in wet season.

The implemented mitigation measures are considered effective.

8.      Conclusion

8.1  Noise Monitoring.

8.1.1       Noise monitoring was conducted at eight (8) noise monitoring stations (N12a, N12b, N13, N14, N15b, N16a, N16b and N17) once per week in the reporting period.

8.1.2       No action or limit level exceedance was recorded in construction noise level in this present quarter.

 

8.2  Water Quality Monitoring

8.2.1       Marine-based construction works commenced on 19 April 2022, water quality monitoring was commenced on 12 April 2022.

8.2.2       Water quality monitoring 17 July 2023 was cancelled due to Typhoon Signal no. 8.

8.2.3       In accordance with the action level and limit level in Baseline Monitoring Report Rev. 9.2 agreed by EPD on 2 September 2022, 1 action level at SR4 and 0 limit level exceedances on SS was recorded in the reporting period. It can be concluded that the SS exceedances were possibly due to natural runoff from streams to the sea in the reporting period.

8.2.4       Action Level exceedances at SR4 was recorded on 12 June 2023 on SS during ebb tide. No Limit Level exceedances recorded in the reporting period. Co-related the monitoring dates with those days with recorded marine works activities, no marine dredging works were active during the reporting period. Pilot hole drilling on 12 June 2023 within the fully enclosed silt curtain started from 09:20 to 09:36 and 16:00 to 18:40. Water quality monitoring at SR4 was conducted at 07:59 to 08:02 which was before the pilot hole drilling works. No exceedance was recorded on same day during flood tide at 13:12 to 13:15 and in the subsequent monitoring on 14 June 2023 both ebb and flood tide. Reviewed the overall work situation and the mitigation measures was implemented by the Contractor, it can be concluded that the SS exceedances at SR4 was possibly due to natural runoff from streams to the sea or sudden changed of water body as a result of frequent rainfall as recorded in the reporting month (Amber rainstorm warning signal recorded on 10 June 2023, heavy showers recorded on 11 June 2023 and rainstorm recorded during water quality monitoring on 12 June 2023).

 

8.3  Ecological Impact Monitoring

8.3.1       Transplanting works for plant species, Aquilaris sinensis, was completed on 26 April 2022. Maintenance works for trees in holding nursery have commenced.

8.3.2       Monitoring of maintenance works for the transplanted plant species was conducted at the holding nursery while in the reporting period.

8.3.3       As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of SSWSTW which are considered to be the plant species with conservative importance for temporarily transplanted to the nursery at Kam Tin and eventually be transplanted to Pui O Pumping Station.

 

8.4  Review of the Reasons for and the Implications of Non-compliance

8.4.1       No environmental non-compliance was recorded in present quarter.

 

8.5  Summary of action taken in the event of and follow-up on non-compliance

8.5.1       There was no particular action taken since no non-compliance was recorded in present quarter.