CONTRACT NO: SD 15/2022
Outlying
Island Sewerage Stage 2 – South Lantau Sewage Works – Environmental Team Services (2023
– 2024) Under Environmental Permit no. EP-538/2017
quarterly Environmental Monitoring & Audit summary
Report
February to april 2023
Revision 2
|
|
CLIENTS: |
|
|
Drainage Services Department |
Lam Environmental Services Limited 19/F Remex Centre, 42 Wong Chuk Hang Road, Hong Kong Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
|
|
|
Certified
by: |
|
|
_______________________________ Environmental
Team Leader Derek
Lo |
|
|
DATE: |
|
|
1 June 2023 |
|
|
|
1.1.......... Scope of the Report
1.2.......... Structure of the Report
2.1.......... Project Organization
and Key Contact Personnel
2.2.......... Construction Programme
3. A Brief Summary of EM&A
Requirements
3.1.......... Monitoring Parameters
3.2.......... Environmental Quality
Performance Limits
4.2.......... Environmental
Mitigation Measures
4.3.......... Environmental
monitoring requirements and contractual requirements
5. Monitoring Results Analysis
5.1.......... Noise Monitoring
5.2.......... Water Quality
Monitoring
5.3 Ecological Impact Monitoring……………………………………………..
5.4.......... Waste Management
6. Complaints, Notification of Summons
and Prosecution
7. Comments and Recommendations
lIST OF TABLES
Table 2.1 Contact
Details of Key Personnel
Table 4.1 Summary of submission status under
EP-538/2017
Table 5.1 Summary of Quantities of Waste
Material (November, December
2022 and January 2023)
Table 6.1
Summary of Complaints
Table 6.2 Cumulative Statistics on
Complaints
Table 6.3 Cumulative Statistics on
Successful Prosecutions
Table 7.1 Construction Activities in Past 3
Months
lIST OF FIGUREs
Figure 2.1 Project Organization Chart
Figure
5.1 Locations of Noise Monitoring
Station
Figure
5.2 Locations of Water Quality Monitoring Stations
lIST OF APPENDIces
Appendix
5.1 Noise Monitoring Graphical
Presentations
Appendix 5.2 Marine Water Quality Monitoring Graphical and Summary of Exceedance Presentations
Appendix
5.3 Quarterly Summary Waste Flow Table
EXECUTIVE SUMMARY
i.
This
is the Quarterly Environmental Monitoring and Audit (EM&A) Summary Report
– February
to April 2023 of Outlying Islands Sewerage Stage 2 – South Lantau
Sewerage Works under Environmental Permit no. EP-538/2017 (Hereafter as “the
Project”). The construction works of the
Project was commenced on 3
November 2021 and the tentative
completion date is Q1 2026. The Quarterly EM&A Summary
Report presents the environmental monitoring findings and information recorded
during the period of 01 February to 30 April 2023.
ii.
In
the reporting period, the principal work activities conducted are as follow:
|
February 2023 |
March 2023 |
April 2023 |
|
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk
Tsuen, South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Horizontal Directional Drilling (HDD) works at marine and SSWSTW ·
Superstructure Reinforced Concrete (RC) Works |
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk
Tsuen, South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Horizontal Directional Drilling (HDD) works at marine and SSWSTW ·
Removal works of Excavation and Lateral Support (ELS) ·
Superstructure Reinforced Concrete (RC) Works |
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk
Tsuen, South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Horizontal Directional Drilling (HDD) works at marine and SSWSTW ·
Removal works of Excavation and Lateral Support (ELS) ·
Superstructure Reinforced Concrete (RC) Works |
Exceedances of Action/Limit Levels
Noise Monitoring
iii.
Noise monitoring was conducted at eight (8) noise monitoring stations
(N12a, N12b, N13, N14, N15b, N16a, N16b and N17) once per week in the reporting
period.
iv.
School examination was taken place at N17 – Bui O Public School from 27,
28 February and 1 March 2023 in the reporting period, the limit level shall be
adjusted to 65dB(A) during this period.
v.
No action and limit level exceedances were recorded in construction
noise level in the reporting period.
Water Quality Monitoring
vii.
Water quality monitoring on 22 and 27 Feb 2023, 27 March 2023, and 22
April 2023 was cancelled due to adverse weather. No substitution would be arranged
for such cancellation since it is impossible to maintain the monitoring
frequency as three times a week for the event of marine water quality
monitoring cancellation in between time with respect to the fact that not less
than 36 hours interval shall be followed for two monitoring days as required by
the EM&A Manual Clause 5.1.6 (b) for the project.
viii.
In accordance with the action level and limit level in Baseline
Monitoring Report Rev. 9.2 agreed by EPD on 2 September 2022, no action level
and limit level exceedances were recorded in the reporting period.
Ecological Impact Monitoring
ix.
Transplanting works for plant species, Aquilaris sinensis, was completed on 26 April 2022. Maintenance
works for trees in holding nursery have commenced.
x.
As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of
SSWSTW which are considered to be the plant species with conservative
importance for temporarily transplanted to the nursery at Kam Tin and
eventually be transplanted to Pui O Pumping Station.
xi.
The weekly
site audit was carried out by ET include checking whether good site practices
are being properly implemented by the Contractor.
xii.
The extent of the work site boundaries was checked by the ET during the
weekly site audit.
Complaint log
Notifications
of Any Summons and Successful Prosecutions
xiv.
No environmental notification of any summons and
successful prosecution regarding the construction works was recorded in present quarter.
1.1.1.
Lam Environmental Services Limited (LES) has been appointed to work as
the Environmental Team (ET) under Environmental Permit (EP) no. EP-538/2017 to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Outlying Islands Sewerage Stage 2 - South Lantau
Sewerage Works (Register No.: AEIAR-210/2017).
1.1.2.
The Quarterly EM&A Summary Report was prepared according to Section 12.3
of the Project EM&A Manual.
Section 1 Introduction – details the scope and structure of the report
Section 2 Basic
Project Information – a synopsis of project
organization, programme contacts of key management, and a synopsis of work undertaken
in the reporting period.
Section 3 A
Brief Summary of EM&A requirements – including monitoring parameters, environmental quality
performance limits (Action and Limit levels); and environmental mitigation
measure, as recommended in the EIA Report.
Section 4 Implementation
Status – Advice on the implementation
status of environmental protection and pollution control/mitigation measures,
as recommended in the EIA Report and summarised in the updated implementation
schedule.
Section 5 Monitoring
Results Analysis – the trends of the
monitoring parameters in present quarter; advice on the solid and liquid waste management
status.
Section 6 Summary
of Non-Compliance (exceedances) of the environmental quality performance
limits, Complaints,
Notification of Summons and Successful Prosecutions
A
brief review of the reasons for and the implications of non-compliance and a
summary description of the actions taken and any follow-up procedures related
to earlier non-compliance.
A summary record
of all complaints received (written or verbal) for each media, liaison and
consultation undertaken, actions and follow-up procedures taken;
A summary record of
notifications of summons and successful prosecutions for breaches of the
current environmental protection/pollution control legislations, including
locations and nature of the breaches, investigation, follow-up actions taken
and results.
Section 7 Comments and Recommendations – such as effectiveness and efficiency of the mitigation
measures, improvement in the EM&A programme, if any.
Section 8 Conclusion
and Project Proponent’s contacts and hotline telephone number for the public to
make enquiries
2.1.1
Drainage Services Department is the overall project controllers for the
Project. For the construction phase of the Project, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues. Key personnel and contact particulars are
summarised in Figure
2.1 and Table 2.1:
Table 2.1 Contact Details of Key Personnel
|
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
|
Drainage
Services Department (DSD) |
The Engineer for the
Contract |
Engineer |
Mr. Silas Chan |
2594 7272 |
3104 6426 |
|
Binnies
Hong Kong Limited |
Engineer’s
Representative |
Resident
Engineer |
Mr. Kevin Chan* |
3529 3013 |
- |
|
Kwan
Lee – Chun Wo Joint Venture |
Contractor
|
Site
Agent |
Mr. Charles Tse |
9270 3384 |
2744 6937 |
|
Environmental
Officer |
Ms. Shirley Kong |
5162 5933 |
|||
|
SMEC Hong Kong |
Independent Environmental
Checker (IEC) |
Independent Environmental Checker (IEC) |
Ms. Kitty Lee |
3995 8140 |
3995 8101 |
|
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Derek Lo |
2882 3939 |
2882 3331 |
*Engineer’s Representative of Binnies change
from Mr. Clayton Lei to Mr. Kevin Chan start from 1 March 2023.
2.2.1
The proposed sewerage works will collect the sewage generated from
the unsewered areas of Shui Hau, Tong Fuk,
Cheung Sha, San Shek Wan, Pui O and Ham Tin in South
Lantau (i.e. within the Project Catchment Area) and convey it to a proposed
sewage treatment works at San Shek Wan for treatment and disposal
into outer bay of Pui O/ Chi Ma Wan via a submarine outfall.
2.2.2
The entire Project are divided into three contracts. Contract No.
DC/2020/20 (the Contract) would have the following implementations as
demonstrated in Figure 2.2.
2.2.3
The major components of the Project under Environmental Permit (EP) (EP
No. EP-538/2017) comprises: (i) construction of sewage treatment works at San
Shek Wan (SSWSTW) and associated submarine outfall; (ii) construction of sewage
pumping station at Pui O (POSPS); (iii) village sewage works at Pui O; and (iv)
trunk sewers and rising mains on carriageways.
Noise
Monitoring
3.1.1 The construction noise level shall
be measured in terms of the A-weighted equivalent continuous sound pressure
level (Leq). Leq (30min) should be used as the monitoring
parameter. Supplementary information for data auditing, statistical results
such as L10 and L90 shall also be obtained for reference.
3.1.2 For impact monitoring for
construction of village sewers / rising main, noise monitoring should be
undertaken on weekly basis. One set of Leq
(30min) noise level as six consecutive Leq (5min) between
07:00-19:00 hours on normal weekdays.
Water Quality Monitoring
3.1.3 In construction phase, the levels
of dissolved oxygen (DO), temperature, turbidity and salinity should be measured
in-situ while suspended solids (SS)
is determined by laboratory analysis.
Ecological Impact Monitoring
3.1.4 Monitoring in the form of regular
site inspections should be carried out to ensure ecological measures in the
form of tree transplantation and establishment are being implemented and
effective for plant species of conservation importance (e.g. Aquilaria sinensis).
Noise
Monitoring
3.2.1 No action and limit level exceedances were
recorded in construction noise level in the reporting period.
Water
Quality Monitoring
3.2.2 Marine-based construction works had been
commenced since 19 April 2022, marine water quality monitoring was initialised
since 12 April 2022.
3.2.3 To support water quality monitoring, the
silt curtain deployment plan has minor updates to include an additional brand
of geosynthetic material as alternative for selection and adopt underwater
robot for inspecting condition of silt curtain.
3.2.4
Water quality monitoring on 22 and 27 Feb 2023, 27 March 2023, and 22
April 2023 was cancelled due to adverse weather. No substitution would be
arranged for such cancellation since it is impossible to maintain the
monitoring frequency as three times a week for the event of marine water
quality monitoring cancellation in between time with respect to the fact that
not less than 36 hours interval shall be followed for two monitoring days as required
by the EM&A Manual Clause 5.1.6 (b) for the project.
3.2.5 Water quality monitoring is evaluated
against Action and Limit Levels. The derived Action and Limit Level proposed in
Baseline Monitoring Report Rev. 9.2 was agreed by EPD on 2 September 2022. Action
and Limit Levels of marine water quality monitoring have been set with
reference to the derived criteria as shown in Table 3.1 below.
Table 3.1 Action and Limit Levels of Water Quality
|
Parameters |
Action
Level |
Limit
Level |
|
Construction Phase Marine Water
Monitoring - derived criteria |
||
|
DO in mg/L B |
Surface and Middle:
5.8 mg/L Bottom: 5.9 mg/L |
Surface and Middle:
4 mg/L Bottom: 2 mg/L |
|
Turbidity in NTU (Depth-averaged A) C |
14.4 NTU and 20% exceedance of
value at any impact station compared with corresponding data from control
station D |
23.5 NTU and 30% exceedance of
value at any impact station compared with corresponding data from control
station D |
|
SS in mg/L (Depth-averaged A) C |
13.1 mg/L and 20% exceedance of
value at any impact station compared with corresponding data from control
station D |
30.4 mg/L and 30% exceedance of
value at any impact station compared with corresponding data from control
station D |
Notes
(with proposed amendments in AL/LL in underlined text):
A. “Depth-averaged”
is calculated by taking the arithmetic means of reading of all three depths.
B. For
DO, non-compliance of the water quality limits occurs when monitoring result is
lower than the limits.
C. For
SS and turbidity, non-compliance of the water quality limits occurs when
monitoring result is higher than the limits.
D. Action
Level and Limit Level with 95%-ile / 99%-ile derived from baseline data “and”
20% / 30% exceedance of control station proposed in Baseline Monitoring Report.
3.2.6 In accordance with the action level and
limit level in Baseline Monitoring Report Rev. 9.2 agreed by EPD on 2 September
2022, no action level and limit level exceedances were recorded in the
reporting period.
Ecological monitoring
3.2.7 Transplanting works for plant species, Aquilaris sinensis, was completed on 26
April 2022. Maintenance works for trees in holding nursery have commenced.
3.2.8 Monitoring of maintenance works for the
transplanted plant species was conducted at the holding nursery while in the
reporting period.
3.2.9
As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of
SSWSTW which are considered to be the plant species with conservative
importance for temporarily transplanted to the nursery at Kam Tin and
eventually be transplanted to Pui O Pumping Station.
4.1.1
Mitigation measures according to the environmental mitigation
implementation schedule in Annex A of EM&A Manual were generally
implemented by the Contractor. Hence,
the EM&A programme was considered effective and shall be maintained.
4.2.1
Environmental mitigation measures mentioned the EIA Report were weekly
reviewed and recorded in Weekly Environmental Site Audit Checklist. Also, a summary of the submission status of
the reporting quarter on submissions and measures mentioned in Environmental
Permit (EP-538/2017) are shown in Table 4.1.
Table 4.1 Summary of
submission status under EP-538/2017
|
EP Condition |
Submission |
Date of Latest Submission to EPD^ / EPD Approval# |
|
Condition 2.10 |
Waste Management Plan (Rev. 5) (electronic copy) |
4 April 2022# |
|
Condition 2.11 |
Submission of Preservation and/or Transplantation Plan for Plant
Species of Conservation Importance (Rev. 23) |
9 September 2022# |
|
Condition 2.12 |
Submission of Compensatory Woodland Planting Plan (Rev. 19) |
8 February 2023^ |
|
Condition 2.13 |
Silt Curtain Deployment Plan (Rev. 11) |
1 June 2022# |
|
Condition 2.14 |
Landscape Mitigation Plan |
To be confirmed |
|
Condition 2.15 |
Construction Noise Mitigation Plan (Rev. 20) |
4 August 2022# |
4.3.1
A summary of the submission status for the reporting period on licences
and/or permits on environmental protection pertinent to the Project is shown in
Table 4.2.
Table 4.2 Summary of the
current status on licences and/or permits on environmental protection pertinent
to the Project
|
Permits and/or Licences |
Permit. No. / Account No. |
Issued Date |
Valid Period & Expiry Date |
Status |
|
Notification
of Works Under APCO |
466408 |
14 Apr
2021 |
N/A |
Valid |
|
Wastewater Discharge Licence under Water Pollution Control Ordinance |
SSWSTW: WT00039636-2021 |
30 Dec
2021 |
30-12-2021
to 31-12-2026 |
Valid |
|
POPS: WT00039820-2021 |
31 Dec
2021 |
31-12-2021
to 31-12-2026 |
Valid |
|
|
SSWSTW:
Gravity Sewer & Raising Main: WT00042613-2022 |
09 Jan
2023 |
09-01-2023
to 31-01-2028 |
Valid |
|
|
Billing
account under Waste Disposal Ordinance |
Account
No.: 7040411 |
05 May
2021 |
N/A |
Valid |
|
Registration
as a Chemical Waste Producer |
0000-931-K3428-01 |
13 May
2021 |
N/A |
Valid |
|
Construction
Noise Permit under Noise Control Ordinance for SSWSTW |
GW-RS0642-22 |
3 Aug 2022 |
05-08-2022 to 02-02-2023 |
Valid |
|
GW-RS0039-23 |
20 Jan 2023 |
03-02-2023 to 02-08-2023 |
Valid |
|
|
Construction
Noise Permit under Noise Control Ordinance for POSPS |
GW-RS0840-22 |
3 Oct
2022 |
05-10-2022
to 26-03-2023 |
Valid |
|
GW-RS0230-23 |
7 Mar
2023 |
27-03-2023
to 26-09-2023 |
Valid |
Note:
Only include those valid or under application; fill in “N/A” for non-applicable
item(s).
5.1.1
Noise monitoring was conducted at eight (8) noise monitoring stations (N12a, N12b, N13, N14, N15b, N16a, N16b and
N17) once per week in the reporting period.
5.1.2
School examination was taken place at N17 – Bui O Public School on 27,
28 February and 1 March 2023 in the reporting period, the limit level shall be
adjusted to 65dB(A) during this period.
5.1.4
Noise monitoring results measured in the reporting period were reviewed
and summarised. Noise monitoring
graphical presentation can be referred to Appendix 5.1.
5.1.5
No action and limit level exceedances were recorded
in construction noise level in the reporting period.
5.2.1
Marine Water quality monitoring involves nine (9)
monitoring stations (seven impact & two control stations) three days per
week in the reporting period starting from 12 April 2022.
5.3.1
Transplanting of the trees of Aquilaris sinensis was completed on 26 April 2022. Maintenance
works for trees in holding nursery have commenced.
5.4.1
The quantities of waste for disposal in present
quarter are summarized in Table 5.1. The Quarterly Summary
Waste Flow Table is shown in Appendix
5.3.
Table 5.1 Summary of
Quantities of Waste Material (February, March and April 2023)
|
Waste Type |
Quantity for reporting quarter |
Cumulative Quantity-to-Date |
|
Hard Rock and Large Broken Concrete (Inert) (in ‘000m3) |
0 |
0 |
|
Reused in this Contract (Inert) (in ‘000m3) |
0 |
0 |
|
Reused in other Projects (Inert) (in ‘000m3) |
0 |
0 |
|
Disposal as Public Fill (Inert) (in ‘000m3) |
0.46641 |
9.65683 |
|
Metals (in ‘000kg) |
0.00390 |
7.50150 |
|
Paper / Cardboard Packing (in ‘000kg) |
0.01930 |
0.30928 |
|
Plastics (in ‘000kg) |
0.00210 |
0.03186 |
|
Chemical Wastes (in ‘000kg) |
0 |
0 |
|
General Refuses (in ‘000kg) |
38.17 |
468.20 |
|
*: Further breakdown into sub-group if considered applicable; |
||
6.1.1
No environmental complaint, notification of summons and successful
prosecution regarding construction works was recorded in the reporting period. Table
6.1 summarized the complaints from project commencement till now.
Table 6.1 Summary of
Complaints
|
Date
of Notification from EPD |
Date
of Complaint |
Description
of Complaint |
Validity
of Complaint |
Close-Out
Date / Status |
|
26 May 2022 |
22 May 2022 |
A complaint is regarding noise
nuisance from marine site of San Shek Wan, Lantau Island. |
Based on the investigation, the works
activities of marine works did not result in any noise nuisance to Noise
Sensitive Receivers (NSRs), noise nuisance from the Project is unlikely to be
valid. |
The interim report was submitted to
EPD in June 2022. EPD replied no further comments on the final investigation
report on 13 July 2022. |
|
23 Dec 2022 |
21 Dec 2022 |
A complaint is regarding to the water quality for Pui O Beach, Lantau
Island. |
Based on the investigation, the works activities at POPS did not
result in any water quality impacts to the Pui O Beach. |
The interim report was submitted to EPD on 4 Jan 2023. |
6.1.2
No notification of summons and successful prosecution regarding
construction works were recorded in the reporting period.
6.1.3
Cumulative statistic on complaints and successful prosecutions are
summarized in Table 6.2 and Table 6.3 respectively.
Table 6.2 Cumulative
Statistics on Complaints
|
Reporting
Period |
No.
of Complaints |
|
February
to April 2023 |
0 |
|
Project
commencement to the end of last reporting quarter |
2 |
|
Total |
2 |
Table 6.3 Cumulative
Statistics on Successful Prosecutions
|
Environmental
Parameters |
Cumulative
No. Brought Forward |
No.
of Successful Prosecutions this month (Offence Date) |
Cumulative
No. Project-to-Date |
|
Air |
- |
0 |
0 |
|
Noise |
- |
0 |
0 |
|
Water |
- |
0 |
0 |
|
Waste |
- |
0 |
0 |
|
Other |
- |
0 |
0 |
|
Total |
- |
0 |
0 |
7.1.1
In the reporting period, the principal work activities conducted are as
follow.
Table 7.1 Construction
Activities in Past 3 Months
|
February 2023 |
March 2023 |
April 2023 |
|
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk
Tsuen, South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Horizontal Directional Drilling (HDD) works at marine and SSWSTW ·
Superstructure Reinforced Concrete (RC) Works |
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk
Tsuen, South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Horizontal Directional Drilling (HDD) works at marine and SSWSTW ·
Removal works of Excavation and Lateral Support (ELS) ·
Superstructure Reinforced Concrete (RC) Works |
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk
Tsuen, South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Horizontal Directional Drilling (HDD) works at marine and SSWSTW ·
Removal works of Excavation and Lateral Support (ELS) ·
Superstructure Reinforced Concrete (RC) Works |
7.1.2
The recommended mitigation measures for the past 3 months are listed
below:
·
Provide caring measures for the health, form and structural conditions for
transplant trees including Aquilaris sinensis in holding nursery;
·
Fully implement tree preservation works on site and holding nursery to
ensure compliance of relevant legislation and guidelines stated in EM&A
Manual.
·
Implementation of noise pollution control in accordance with
Construction Noise Mitigation Plan;
·
Dust control during dust generating works;
·
Adopt surface
drainage and sediment control facilities for sewage installation in village and
public roads;
·
Adopt temporary
drainage and sediment control facilities on Site;
·
Vehicle wheel-washing and body washing facilities should be provided at
the site entrance;
·
Regular water spraying on drilling and excavation works for dust
control; and
·
Proper waste handling, recycling and storage.
·
To inspect the
condition of silt curtains on regular basis, and after adverse weather including
any rainstorms and typhoons in wet season.
The implemented mitigation
measures are considered effective.
8.1.1
Noise monitoring was conducted at eight (8) noise monitoring stations
(N12a, N12b, N13, N14, N15b, N16a, N16b and N17) once per week in the reporting
period.
8.1.2
No action or limit level exceedance was recorded in construction noise
level in this present quarter.
8.2.1
Marine-based construction works commenced on 19 April 2022, water
quality monitoring was commenced on 12 April 2022.
8.2.2
Water quality monitoring on 22 and 27 Feb 2023, 27 March 2023, and 22
April 2023 was cancelled due to adverse weather.
8.2.3
Water quality monitoring is evaluated against
Action and Limit Levels. The derived Action and Limit Level proposed in
Baseline Monitoring Report Rev. 9.2 was agreed by EPD on 2 September 2022. No action and limit
level exceedances were recorded in the reporting period.
8.3.1
Transplanting works for plant species, Aquilaris sinensis, was completed on 26 April 2022. Maintenance
works for trees in holding nursery have commenced.
8.3.2
Monitoring of maintenance works for the transplanted plant species was
conducted at the holding nursery while in the reporting period.
8.3.3
As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of
SSWSTW which are considered to be the plant species with conservative
importance for temporarily transplanted to the nursery at Kam Tin and
eventually be transplanted to Pui O Pumping Station.
8.4.1
No environmental non-compliance was recorded in present quarter.
8.5.1
There was no particular action taken since no non-compliance was
recorded in present quarter.
Figure 2.1
Project Organisation Chart
Figure 2.2
Master Layout Plan
Figure 5.1
Locations of Noise Monitoring Station
Figure 5.2
Locations of Water Quality Monitoring Stations
Appendix 5.1
Noise Monitoring Graphical Presentations
Appendix 5.2
Marine Water Quality Monitoring Graphical and
Summary of Exceedance Presentations
Appendix 5.3
Quarterly Summary Waste Flow Table