CONTRACT NO: SD 6/2020
Construction of San Shek Wan Sewage Treatment Works,
Associated
Submarine Outfall and Pui O Sewerage Works Under Environmental Permit no. EP-538/2017
quarterly Environmental Monitoring & Audit summary
Report
august to October 2022
Revision 2
|
|
CLIENTS: |
|
|
Drainage Services Department |
Lam Environmental Services Limited 19/F Remex Centre, 42 Wong Chuk Hang Road, Hong Kong Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
|
|
|
Certified
by: |
|
|
_______________________________ Environmental
Team Leader Derek
Lo |
|
|
DATE: |
|
|
8 December 2022 |
|
|
|
1.1.......... Scope of the Report
1.2.......... Structure of the Report
2.1.......... Project Organization
and Key Contact Personnel
2.2.......... Construction Programme
3. A Brief Summary of EM&A
Requirements
3.1.......... Monitoring Parameters
3.2.......... Environmental Quality
Performance Limits
4.2.......... Environmental
Mitigation Measures
4.3.......... Environmental
monitoring requirements and contractual requirements
5. Monitoring Results Analysis
5.1.......... Noise Monitoring
5.2.......... Water Quality
Monitoring
5.3 Ecological Impact Monitoring……………………………………………..
5.4.......... Waste Management
6. Complaints, Notification of Summons
and Prosecution
7. Comments and Recommendations
lIST OF TABLES
Table 2.1 Contact
Details of Key Personnel
Table 4.1 Summary of submission status under
EP-538/2017
Table 5.1 Summary of Quantities of Waste
Material (May 2022 to July
2022)
Table 6.1 Cumulative Statistics on
Complaints
Table 6.2 Cumulative Statistics on Successful
Prosecutions
Table 7.1 Construction Activities in Past 3
Months
lIST OF FIGUREs
Figure 2.1 Project Organization Chart
Figure
5.1 Locations of Noise Monitoring
Station
Figure
5.2 Locations of Water Quality Monitoring Stations
lIST OF APPENDIces
Appendix
5.1 Noise Monitoring Graphical
Presentations
Appendix 5.2 Marine Water Quality Monitoring Graphical and Summary of Exceedance Presentations
Appendix
5.3 Quarterly Summary Waste Flow Table
EXECUTIVE SUMMARY
i.
This
is the Quarterly Environmental Monitoring and Audit (EM&A) Summary Report
– August
to October 2022 of
Outlying Islands Sewerage Stage
2 – South Lantau Sewerage Works under Environmental Permit no. EP-538/2017
(Hereafter as “the Project”). The
construction works of the Project was commenced on 3 November 2021 and the tentative completion date is Q1 2026. The
Quarterly EM&A Summary Report presents the environmental monitoring
findings and information recorded during the period of 01 August to 31 October 2022. The cut-off
date of reporting is at the end of each month within the reporting period.
ii.
In
the reporting period, the principal work activities conducted are as follow:
|
August 2022 |
September 2022 |
October 2022 |
|
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Excavation at South Lantau Road ·
SSWSTW and HDD works ·
Site formation works at POSPS ·
ELS works at POSPS |
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Excavation at South Lantau Road ·
SSWSTW and HDD works ·
ELS works at POSPS |
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen,
South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
HDD works at marine and SSWSTW ·
ELS works at POSPS |
Exceedances of Action/Limit Levels
Noise Monitoring
iii.
With respect to the commencement of construction works at South Lantau
Road near WSD Pui O No.2 Raw Water Pumping Station, the weekly noise monitoring
at N15b – Pui O Lo Wai Tsuen was started from 11 October 2022 onwards.
iv.
Weekly noise monitoring was conducted at Seven
(7) noise monitoring stations (N12a, N12b, N13, N14, N16a, N16b and N17) from 1
August to 10 October 2022 and Eight (8) noise
monitoring stations (N12a, N12b, N13, N14, N15b, N16a, N16b and N17) started
from 11 October 2022 once per week in the reporting period.
v.
No examination was taken place at N17 – Bui O Public School in the
reporting period.
vi.
No action and limit level exceedances were recorded in construction
noise level in the reporting period.
Water Quality Monitoring
viii.
Water quality monitoring on 9 August 2022, flood tide on 24 August 2022,
28 September 2022, ebb tide on 30 September 2022 and 10, 18 and 20 October 2022 was cancelled due to
adverse weather.
ix.
In accordance with the EM&A Manual, 19 action level and 0 limit
level exceedances on DO, 27 action level and 16 limit level exceedances on
turbidity, 13 action level and 30 limit level exceedances on SS were recorded
in the reporting period of 1 August 2022 to 1 September 2022.
x.
Action Level exceedances were recorded on 11 August 2022 on DO, reviewed
the overall work situation with no marine works and sea condition, it can be
concluded that the DO exceedances were possibly due to Tropical Storm MULAN
during 9 – 10 August 2022.
xi.
Overall exceedances on turbidity and SS during 1 August 2022 to 1
September 2022 (i.e. SR4, SR15 downstream to the construction site during
mid-ebb, SR5, SR6, SR9, SR10 and SR12 exceedances downstream to the
construction site during mid-flood,) in the reporting period were referred to
the 20% / 30% of control station criteria only whereas there were no exceedance
as referred to 95%-ile / 99%-ile criteria, indicating that the exceedance is
due to the localized water quality better than baseline range were captured at
the control station whereas the impact station are still within the baseline
ranges.
xii.
Co-related the monitoring dates with those days with recorded marine
works activities, no marine dredging works were active during the reporting period
of 1 August to 1 September 2022.
Majority of recorded marine works activities were maintenance on working
barge not in contact with water, except casing installation for marine HDD
works on 2 - 6 and 15 -19 August 2022 within the replaced fully enclosed silt
curtain. Reviewed the overall work
situation with limited marine works, it can be concluded that all the turbidity
and SS exceedances were possibly due to natural runoff from streams to the sea
as a result of frequent rainfall as recorded in the reporting period. (tropical
cyclone warning signals recorded on 3 - 4, 9 - 10 and 23 – 25 August 2022.
There was also typhoon no. 8 on 24 – 25 August 2022).
xiii.
Reviewing the “and“ approach, no exceedance in turbidity and SS during 1
August 2022 to 1 September 2022 would be recorded on adopting the ‘and’
criteria in the Action and Limit Level as proposed in submitted Baseline
Monitoring Report Rev. 9.2.
xiv.
In accordance with the action level and limit level in Baseline
Monitoring Report Rev. 9.2 agreed by EPD on 2 September 2022, 3 action level
and 0 limit level exceedances on turbidity and 6 action level and 0 limit level
exceedances on SS were recorded in the reporting period of 2 September 2022 to
31 October 2022. It can be concluded that all the SS exceedances were possibly
due to natural runoff from streams to the sea as a result of frequent rainfall
as recorded in the reporting period.
xv.
Action Level exceedances were recorded on 30 September 2022 on turbidity
and Action Level exceedances were recorded on 7 and 26 October 2022 on SS.
Strong current with brownish yellow in colour on surface of sea was observed on
7 and 26 October 2022. Co-related the monitoring dates with those days with
recorded marine works activities, no marine dredging works were active during the
reporting month. Majority of recorded
marine works activities were maintenance on working barge not in contact with
water, except casing installation for marine HDD works between 9-21 September
2022 and 7-14 October 2022 within the replaced fully enclosed silt
curtain. Reviewed the overall work
situation with limited marine works, it can be concluded that all the turbidity
and SS exceedances were possibly due to natural runoff from streams to the sea
as a result of frequent rainfall as recorded in the reporting period of 2
September 2022 to 31 October 2022 (Strong Monsoon Signal during 27 – 29
September 2022 and Amber Rainstorm Warning Signal on 30 September 2022;
Tropical Cyclone Warning Signals recorded on 16-17 Oct 2022. There was also
Strong Monsoon Signal on 9, 16, 18, 19, 23, 25 and 26 Oct 2022).
xvi.
All action and limit level exceedances under “or” criteria as stated in
the EM&A Manual and the derived criteria proposed in Baseline Monitoring
Report Rev. 9.2 agreed by EPD on 2 September 2022 were concluded as non-project
related upon investigation.
Ecological Impact Monitoring
xvii.
Transplanting works for plant species, Aquilaris sinensis, was completed on 26 April 2022. Maintenance
works for trees in holding nursery have commenced.
xviii.
As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of
SSWSTW which are considered to be the plant species with conservative
importance for temporarily transplanted to the nursery at Kam Tin and
eventually be transplanted to Pui O Pumping Station.
xix.
The weekly
site audit was carried out by ET include checking whether good site practices
are being properly implemented by the Contractor.
xx.
The extent of the work site boundaries was checked by the ET during the
weekly site audit.
Complaint log
xxi.
No environmental complaint regarding the construction works
was recorded in present quarter.
Notifications
of Any Summons and Successful Prosecutions
xxii.
No environmental notification of any summons and successful
prosecution regarding the construction works was recorded in present quarter.
1.1.1.
Lam Environmental Services Limited (LES) has been appointed to work as
the Environmental Team (ET) under Environmental Permit (EP) no. EP-538/2017 to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Outlying Islands Sewerage Stage 2 - South Lantau
Sewerage Works (Register No.: AEIAR-210/2017).
1.1.2.
The Quarterly EM&A Summary Report was prepared according to Section 12.3
of the Project EM&A Manual.
Section 1 Introduction – details the scope and structure of the report
Section 2 Basic
Project Information – a synopsis of project
organization, programme contacts of key management, and a synopsis of work undertaken
in the reporting period.
Section 3 A
Brief Summary of EM&A requirements – including monitoring parameters, environmental quality performance
limits (Action and Limit levels); and environmental mitigation measure, as recommended in the EIA
Report.
Section 4 Implementation
Status – Advice on the implementation
status of environmental protection and pollution control/mitigation measures,
as recommended in the EIA Report and summarised in the updated implementation
schedule.
Section 5 Monitoring
Results Analysis – the trends of the
monitoring parameters in present quarter; advice on the solid and liquid waste
management status.
Section 6 Summary
of Non-Compliance (exceedances) of the environmental quality performance
limits, Complaints,
Notification of Summons and Successful Prosecutions
A
brief review of the reasons for and the implications of non-compliance and a
summary description of the actions taken and any follow-up procedures related
to earlier non-compliance.
A summary record
of all complaints received (written or verbal) for each media, liaison and
consultation undertaken, actions and follow-up procedures taken;
A summary record of
notifications of summons and successful prosecutions for breaches of the
current environmental protection/pollution control legislations, including
locations and nature of the breaches, investigation, follow-up actions taken
and results.
Section 7 Comments and Recommendations – such as effectiveness and efficiency of the mitigation
measures, improvement in the EM&A programme, if any.
Section 8 Conclusion
and Project Proponent’s contacts and hotline telephone number for the public to
make enquiries
2.1.1
Drainage Services Department is the overall project controllers for the
Project. For the construction phase of the Project, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues. Key personnel and contact particulars are
summarised in Figure 2.1 and Table 2.1:
Table 2.1 Contact Details of Key Personnel
|
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
|
Drainage
Services Department (DSD) |
The Engineer for the
Contract |
Engineer |
Mr. Silas Chan |
2594 7272 |
3104 6426 |
|
Binnies
Hong Kong Limited |
Engineer’s
Representative |
Resident
Engineer |
Mr. Clarence Chak / Mr. Clayton Lei* |
3529 3013 |
- |
|
Kwan
Lee – Chun Wo Joint Venture |
Contractor
|
Site
Agent |
Mr. Charles Tse |
9270 3384 |
2744 6937 |
|
Environmental
Officer |
Ms. Shirley Kong |
5162 5933 |
|||
|
SMEC Hong Kong |
Independent Environmental
Checker (IEC) |
Independent Environmental Checker (IEC) |
Ms. Kitty Lee |
3995 8140 |
3995 8101 |
|
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Derek Lo |
2882 3939 |
2882 3331 |
Notes: Engineer’s Representative change from
Mr. Clarence Chak to Mr. Clayton Lei start from September 2022
2.2.1
The proposed sewerage works will collect the sewage generated from
the unsewered areas of Shui Hau, Tong Fuk,
Cheung Sha, San Shek Wan, Pui O and Ham Tin in South
Lantau (i.e. within the Project Catchment Area) and convey it to a proposed
sewage treatment works at San Shek Wan for treatment and disposal
into outer bay of Pui O/ Chi Ma Wan via a submarine outfall.
2.2.2
The entire Project are divided into three contracts. Contract No.
DC/2020/20 (the Contract) would have the following implementations as
demonstrated in Figure 2.2.
2.2.3
The major components of the Project under Environmental Permit (EP) (EP
No. EP-538/2017) comprises: (i) construction of sewage treatment works at San
Shek Wan (SSWSTW) and associated submarine outfall; (ii) construction of sewage
pumping station at Pui O (POSPS); (iii) village sewage works at Pui O; and (iv)
trunk sewers and rising mains on carriageways.
Noise
Monitoring
3.1.1 The construction noise level shall
be measured in terms of the A-weighted equivalent continuous sound pressure
level (Leq). Leq (30min) should be used as the monitoring
parameter. Supplementary information for data auditing, statistical results
such as L10 and L90 shall also be obtained for reference.
3.1.2 For impact monitoring for
construction of village sewers / rising main, noise monitoring should be
undertaken on weekly basis. One set of Leq
(30min) noise level as six consecutive Leq (5min) between
07:00-19:00 hours on normal weekdays.
Water Quality Monitoring
3.1.3 In construction phase, the levels
of dissolved oxygen (DO), temperature, turbidity and salinity should be measured
in-situ while suspended solids (SS)
is determined by laboratory analysis.
Ecological Impact Monitoring
3.1.4 Monitoring in the form of regular
site inspections should be carried out to ensure ecological measures in the
form of tree transplantation and establishment are being implemented and
effective for plant species of conservation importance (e.g. Aquilaria sinensis).
Noise
Monitoring
3.2.1 No action and limit level exceedances were
recorded in construction noise level in the reporting period.
Water
Quality Monitoring
3.2.2 Marine-based construction works had been
commenced since 19 April 2022, marine water quality monitoring was initialised
since 12 April 2022.
3.2.3
In accordance with the EM&A Manual, 19 action level and 0 limit
level exceedances on DO, 27 action level and 16 limit level exceedances on
turbidity, 13 action level and 30 limit level exceedances on SS were recorded
in the reporting period of 1 August 2022 to 1 September 2022.
3.2.4
Action Level exceedances were recorded on 11 August 2022 on DO, reviewed
the overall work situation with no marine works and sea condition, it can be
concluded that the DO exceedances were possibly due to Tropical Storm MULAN
during 9 – 10 August 2022.
3.2.5
Overall exceedances on turbidity and SS during 1 August 2022 to 1
September 2022 (i.e. SR4, SR15 downstream to the construction site during
mid-ebb, SR5, SR6, SR9, SR10 and SR12 exceedances downstream to the
construction site during mid-flood,) in the reporting period were referred to
the 20% / 30% of control station criteria only whereas there were no exceedance
as referred to 95%-ile / 99%-ile criteria, indicating that the exceedance is
due to the localized water quality better than baseline range were captured at
the control station whereas the impact station are still within the baseline
ranges.
3.2.6 Checked with contractor and RSS on the marine works
activities during water Quality
monitoring in the reporting period, the following activities were recorded:
• 2 - 6, 15 - 19/8/2022 -
Appliance maintenance on working barge and casing installation for marine HDD works
• 9, 12, 14, 16, 19 and 21/9/2022
- Appliance maintenance on working barge and casing installation for marine HDD
works
• 7, 10, 12, 14, and 28 October
2022 - Appliance maintenance on working barge and casing installation for
marine HDD works
3.2.7
Co-related the monitoring dates with those days with recorded marine
works activities, no marine dredging works were active during the reporting period
of 1 August to 1 September 2022.
Majority of recorded marine works activities were maintenance on working
barge not in contact with water, except casing installation for marine HDD
works on 2 - 6 and 15 -19 August 2022 within the replaced fully enclosed silt
curtain. Reviewed the overall work
situation with limited marine works, it can be concluded that all the turbidity
and SS exceedances were possibly due to natural runoff from streams to the sea
as a result of frequent rainfall as recorded in the reporting period. (tropical
cyclone warning signals recorded on 3 - 4, 9 - 10 and 23 – 25 August 2022.
There was also typhoon no. 8 on 24 – 25 August 2022).
3.2.8
Reviewing the “and“ approach, no exceedance in turbidity and SS during 1
August 2022 to 1 September 2022 would be recorded on adopting the ‘and’
criteria in the Action and Limit Level as proposed in submitted Baseline
Monitoring Report Rev. 9.2.
3.2.9
In accordance with the action level and limit level in Baseline
Monitoring Report Rev. 9.2 agreed by EPD on 2 September 2022, 3 action level
and 0 limit level exceedances on turbidity and 6 action level and 0 limit level
exceedances on SS were recorded in the reporting period of 2 September 2022 to
31 October 2022. It can be concluded that all the exceedances were possibly due
to natural runoff from streams to the sea as a result of frequent rainfall as
recorded in the reporting period of 2 September to 31 October 2022.
3.2.10
Action Level exceedances were recorded on 30 September 2022 on turbidity
and Action Level exceedances were recorded on 7 and 26 October 2022 on SS. Strong
current with brownish yellow in colour on surface of sea was observed on 7 and
26 October 2022. Co-related the monitoring dates with those days with recorded
marine works activities, no marine dredging works were active during the
reporting month. Majority of recorded
marine works activities were maintenance on working barge not in contact with
water, except casing installation for marine HDD works between 9-21 September
2022 and 7-14 October 2022 within the replaced fully enclosed silt
curtain. Reviewed the overall work
situation with limited marine works, it can be concluded that all the turbidity
and SS exceedances were possibly due to natural runoff from streams to the sea
as a result of frequent rainfall as recorded in the reporting period of 2
September 2022 to 31 October 2022 (Strong Monsoon Signal during 27 – 29
September 2022 and Amber Rainstorm Warning Signal on 30 September 2022; Tropical
Cyclone Warning Signals recorded on 16-17 Oct 2022. There was also Strong
Monsoon Signal on 9, 16, 18, 19, 23, 25 and 26 Oct 2022).
3.2.11 All action and limit level exceedances
under “or” criteria as stated in the EM&A Manual and the derived criteria
proposed in Baseline Monitoring Report Rev. 9.2 agreed by EPD on 2 September
2022 were concluded as non-project related upon investigation.
3.2.12 Water quality monitoring is evaluated
against Action and Limit Levels. The derived Action and Limit Level proposed in
Baseline Monitoring Report Rev. 9.2 was agreed by EPD on 2 September 2022. Both
the EM&A Manual criteria for the reporting period of 1 August 2022 to 1
September 2022 and derived criteria for the reporting period of 2 September
2022 to 31 October 2022 are shown in Table 3.1 below.
Table 3.1 Action and Limit Levels of Water Quality
|
Parameters |
Action
Level |
Limit
Level |
|
Construction Phase Marine Water
Monitoring - EM&A Manual criteria |
||
|
DO in mg/L |
Surface and Middle:
5.8 mg/L Bottom: 5.9 mg/L |
Surface and Middle:
4 mg/L Bottom: 2 mg/L |
|
Turbidity in NTU (Depth-averaged A) c |
14.4 NTU, or 20% exceedance of
value at any impact station compared with corresponding data from control
station |
23.5 NTU, or 30% exceedance of
value at any impact station compared with corresponding data
from control station |
|
SS in mg/L (Depth-averaged A) c |
13.1 mg/L, or 20% exceedance of
value at any impact station compared with corresponding data from control
station |
30.4 mg/L, or 30% exceedance of
value at any impact station compared with corresponding data
from control station |
|
Construction Phase Marine Water
Monitoring - derived criteria |
||
|
DO in mg/L B |
Surface and Middle:
5.8 mg/L Bottom: 5.9 mg/L |
Surface and Middle:
4 mg/L Bottom: 2 mg/L |
|
Turbidity in NTU (Depth-averaged A) C |
14.4 NTU and 20% exceedance of
value at any impact station compared with corresponding data from control
station D |
23.5 NTU and 30% exceedance of
value at any impact station compared with corresponding data from control
station D |
|
SS in mg/L (Depth-averaged A) C |
13.1 mg/L and 20% exceedance of
value at any impact station compared with corresponding data from control
station D |
30.4 mg/L and 30% exceedance of
value at any impact station compared with corresponding data from control
station D |
Notes
(with proposed amendments in AL/LL in underlined text):
A. “Depth-averaged”
is calculated by taking the arithmetic means of reading of all three depths.
B. For
DO, non-compliance of the water quality limits occurs when monitoring result is
lower than the limits.
C.
For SS and turbidity, non-compliance of the water quality limits occurs when
monitoring result is higher than the limits.
D.
Action Level and Limit Level with 95%-ile / 99%-ile derived from baseline data
“and” 20% / 30% exceedance of control station proposed in Baseline
Monitoring Report.
Ecological monitoring
3.2.13 Transplanting works for plant species, Aquilaris sinensis, was completed on 26
April 2022. Maintenance works for trees in holding nursery have commenced.
3.2.14 Monitoring of maintenance works for the
transplanted plant species was conducted at the holding nursery while in the
reporting period.
3.2.15
As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of
SSWSTW which are considered to be the plant species with conservative
importance for temporarily transplanted to the nursery at Kam Tin and
eventually be transplanted to Pui O Pumping Station.
4.1.1
Mitigation measures according to the environmental mitigation
implementation schedule in Annex A of EM&A Manual were generally
implemented by the Contractor. Hence,
the EM&A programme was considered effective and shall be maintained.
4.2.1
Environmental mitigation measures mentioned the EIA Report were weekly
reviewed and recorded in Weekly Environmental Site Audit Checklist. Also, a summary of the submission status of
the reporting quarter on submissions and measures mentioned in Environmental
Permit (EP-538/2017) are shown in Table 4.1.
Table 4.1 Summary of
submission status under EP-538/2017
|
EP Condition |
Submission |
Date of Latest Submission to EPD ^ / EPD Approval # |
|
Condition 2.10 |
Waste Management Plan (Rev. 5) (electronic copy) |
4 April 2022# |
|
Condition 2.11 |
Submission of Preservation and/or Transplantation Plan for Plant
Species of Conservation Importance (Rev. 23) |
31 August 2022^ |
|
Condition 2.12 |
Submission of Compensatory Woodland Planting Plan (Rev. 16) |
23 September 2022^ |
|
Condition 2.13 |
Silt Curtain Deployment Plan (Rev. 14) |
5 August 2022^ |
|
Condition 2.14 |
Landscape Mitigation Plan |
To be confirmed |
|
Condition 2.15 |
Construction Noise Mitigation Plan (Rev. 20) |
4 August 2022# |
4.3.1
A summary of the submission status for the reporting period on licences
and/or permits on environmental protection pertinent to the Project is shown in
Table 4.2.
Table 4.2 Summary of the
current status on licences and/or permits on environmental protection pertinent
to the Project
|
Permits and/or Licences |
Permit.
No. / Account No. |
Issued Date |
Valid Period & Expiry Date (dd-mm-yyyy to dd-mm-yyyy) |
Status |
|
Notification
Pursuant to Section 3(1) of Air
Pollution Control (Construction Dust) Regulation |
466408 |
14 Apr 2021 |
N/A |
Valid |
|
Wastewater
Discharge Licence under Water Pollution
Control Ordinance |
SSWSTW: WT00039636-2021 |
30 Dec 2021 |
30-12-2021 to 31-12-2026 |
Valid |
|
POPS: WT00039820-2021 |
31 Dec 2021 |
31-12-2021 to 31-12-2026 |
Valid |
|
|
Billing
Account under Waste Disposal (Charges
for Disposal of Construction Waste) Regulation |
Account No.: 7040411 |
05 May 2021 |
N/A |
Valid |
|
Registration
as Chemical Waste Producer under Waste
Disposal (Chemical Waste) (General) Regulation |
WPN 0000-931-K3428-01 |
13 May 2021 |
N/A |
Valid |
|
Construction
Noise Permit under Noise Control
Ordinance |
GW-RS0642-22 |
3 Aug 2022 |
05-08-2022 to 02-02-2023 |
Valid |
|
GW-RS0840-22 |
3 Oct 2022 |
05-10-2022 to 26-03-2023 |
Valid |
Note:
Only include those valid or under application; fill in “N/A” for non-applicable
item(s).
5.1.1
With respect to the commencement of construction works at South Lantau
Road near WSD Pui O No.2 Raw Water Pumping Station, the weekly noise monitoring
at N15b – Pui O Lo Wai Tsuen was started from 11 October 2022 onwards.
5.1.2
Weekly Noise monitoring was conducted at Seven (7) noise monitoring
stations (N12a, N12b, N13, N14, N16a, N16b and N17) from 1 August to 10 October
2022 and Eight (8) noise monitoring stations (N12a, N12b, N13, N14, N15b, N16a,
N16b and N17) started from 11 October 2022 once per week in the reporting
period.
5.1.4
Noise monitoring results measured in the reporting period were reviewed
and summarised. Noise monitoring
graphical presentation can be referred to
Appendix 5.1.
5.1.5
No action and limit level exceedances were recorded
in construction noise level in the reporting period.
5.2.1
Marine Water quality monitoring involves nine (9)
monitoring stations (seven impact & two control stations) three days per
week in the reporting period starting from 12 April 2022.
5.3.1
Transplanting of the trees of Aquilaris sinensis was completed on 26 April 2022. Maintenance
works for trees in holding nursery have commenced.
5.4.1
The quantities of waste for disposal in present
quarter are summarized in Table 5.1. The Quarterly Summary
Waste Flow Table is shown in Appendix
5.3.
Table 5.1 Summary of
Quantities of Waste Material (August 2022 to October 2022)
|
Waste Type |
Quantity for reporting quarter |
Cumulative Quantity-to-Date |
|
Hard Rock and Large Broken Concrete (Inert) (in ‘000m3) |
0 |
0 |
|
Reused in this Contract (Inert) (in ‘000m3) |
0 |
0 |
|
Reused in other Projects (Inert) (in ‘000m3) |
0 |
0 |
|
Disposal as Public Fill (Inert) (in ‘000m3) |
1.94268 |
8.55411 |
|
Metals (in ‘000kg) |
0.00490 |
1.56990 |
|
Paper / Cardboard Packing (in ‘000kg) |
0.0919 |
0.22938 |
|
Plastics (in ‘000kg) |
0.00930 |
0.02336 |
|
Chemical Wastes (in ‘000kg) |
0 |
0 |
|
General Refuses (in ‘000kg) |
44.3646 |
389.13460 |
|
*: Further breakdown into sub-group if considered applicable; |
||
6.1.1
No environmental
complaint, notification of summons and successful prosecution regarding
construction works was recorded in present quarter.
6.1.2
Cumulative statistic on complaints and successful prosecutions are
summarized in Table 6.1 and Table 6.2 respectively.
Table 6.1 Cumulative
Statistics on Complaints
|
Reporting
Period |
No.
of Complaints |
|
August
2022 - October 2022 |
0 |
|
Project
commencement to the end of last reporting quarter |
1 |
|
Total |
1 |
Table 6.2 Cumulative
Statistics on Successful Prosecutions
|
Environmental
Parameters |
Cumulative
No. Brought Forward |
No.
of Successful Prosecutions this month (Offence Date) |
Cumulative
No. Project-to-Date |
|
Air |
- |
0 |
0 |
|
Noise |
- |
0 |
0 |
|
Water |
- |
0 |
0 |
|
Waste |
- |
0 |
0 |
|
Other |
- |
0 |
0 |
|
Total |
- |
0 |
0 |
7.1.1
In the reporting period, the principal work activities conducted are as
follow.
Table 7.1 Construction
Activities in Past 3 Months
|
August 2022 |
September 2022 |
October 2022 |
|
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Excavation at South Lantau Road ·
SSWSTW and HDD works ·
Site formation works at POSPS ·
ELS works at POSPS |
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Excavation at South Lantau Road ·
SSWSTW and HDD works ·
ELS works at POSPS |
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen,
South Lantau road, Pui O Beach ·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
HDD works at marine and SSWSTW ·
ELS works at POSPS |
7.1.2
The recommended mitigation measures for the past 3 months are listed
below:
·
Provide caring measures for the health, form and structural conditions for
transplant trees including Aquilaris sinensis in holding nursery;
·
Fully implement tree preservation works on site and holding nursery to
ensure compliance of relevant legislation and guidelines stated in EM&A
Manual.
·
Implementation of noise pollution control in accordance with
Construction Noise Mitigation Plan;
·
Dust control during dust generating works;
·
Adopt surface
drainage and sediment control facilities for sewage installation in village and
public roads;
·
Adopt temporary
drainage and sediment control facilities on Site;
·
Vehicle wheel-washing and body washing facilities should be provided at
the site entrance;
·
Regular water spraying on drilling and excavation works for dust
control; and
·
Proper waste handling, recycling and storage.
·
To inspect the
condition of silt curtains on regular basis, and after adverse weather
including any rainstorms and typhoons in wet season.
·
Implementation of noise pollution control in accordance with
Construction Noise Mitigation Plan;
·
Dust control during dust generating works;
·
Adopt surface drainage and sediment control facilities for sewage installation
in village and public roads;
·
Adopt temporary drainage and sediment control facilities on Site;
·
Vehicle wheel-washing and body washing facilities should be provided at
the site entrance;
·
Regular water spraying on drilling and excavation works for dust
control; and
·
Proper waste handling, recycling and storage.
The implemented mitigation
measures are considered effective.
8.1.1
With respect to the commencement of construction works at South Lantau
Road near WSD Pui O No.2 Raw Water Pumping Station, the weekly noise monitoring
at N15b – Pui O Lo Wai Tsuen was started from 11 October 2022 onwards.
8.1.2
No action or limit level exceedance was recorded in construction noise
level in this present quarter.
8.2.1
Marine-based construction works commenced on 19 April 2022, water
quality monitoring was commenced on 12 April 2022.
8.2.2
In accordance with the EM&A Manual, 19 action level and 0 limit
level exceedances on DO, 27 action level and 16 limit level exceedances on
turbidity, 13 action level and 30 limit level exceedances on SS were recorded
in the reporting period of 1 August 2022 to 1 September 2022.
8.2.3
Action Level exceedances were recorded on 11 August 2022 on DO, reviewed
the overall work situation with no marine works and sea condition, it can be
concluded that the DO exceedances were possibly due to Tropical Storm MULAN
during 9 – 10 August 2022.
8.2.4
Overall exceedances on turbidity and SS during 1 August 2022 to 1
September 2022 (i.e. SR4, SR15 downstream to the construction site during
mid-ebb, SR5, SR6, SR9, SR10 and SR12 exceedances downstream to the
construction site during mid-flood,) in the reporting period were referred to
the 20% / 30% of control station criteria only whereas there were no exceedance
as referred to 95%-ile / 99%-ile criteria, indicating that the exceedance is
due to the localized water quality better than baseline range were captured at
the control station whereas the impact station are still within the baseline ranges.
8.2.5
Co-related the monitoring dates with those days with recorded marine
works activities, no marine dredging works were active during the reporting
period of 1 August to 1 September 2022.
Majority of recorded marine works activities were maintenance on working
barge not in contact with water, except casing installation for marine HDD
works on 2 - 6 and 15 -19 August 2022 within the replaced fully enclosed silt
curtain. Reviewed the overall work
situation with limited marine works, it can be concluded that all the turbidity
and SS exceedances were possibly due to natural runoff from streams to the sea
as a result of frequent rainfall as recorded in the reporting period. (tropical
cyclone warning signals recorded on 3 - 4, 9 - 10 and 23 – 25 August 2022.
There was also typhoon no. 8 on 24 – 25 August 2022).
8.2.6
Reviewing the “and“ approach, no exceedance in turbidity and SS during 1
August 2022 to 1 September 2022 would be recorded on adopting the ‘and’
criteria in the Action and Limit Level as proposed in submitted Baseline
Monitoring Report Rev. 9.2.
8.2.7
In accordance with the action level and limit level in Baseline
Monitoring Report Rev. 9.2 agreed by EPD on 2 September 2022, 3 action level
and 0 limit level exceedances on turbidity and 6 action level and 0 limit level
exceedances on SS were recorded in the reporting period of 2 September 2022 to
31 October 2022. In accordance with the action level and limit level in
Baseline Monitoring Report Rev. 9.2 agreed by EPD on 2 September 2022, 3 action
level and 0 limit level exceedances on turbidity and 6 action level and 0 limit
level exceedances on SS were recorded in the reporting period of 2 September
2022 to 31 October 2022. It can be concluded that all the exceedances were
possibly due to natural runoff from streams to the sea as a result of frequent
rainfall as recorded in the reporting period of 2 September to 31 October 2022.
8.2.8
Action Level exceedances were recorded on 30 September 2022 on turbidity
and Action Level exceedances were recorded on 7 and 26 October 2022 on SS.
Strong current with brownish yellow in colour on surface of sea was observed on
7 and 26 October 2022. Co-related the monitoring dates with those days with
recorded marine works activities, no marine dredging works were active during
the reporting month. Majority of
recorded marine works activities were maintenance on working barge not in
contact with water, except casing installation for marine HDD works between
9-21 September 2022 and 7-14 October 2022 within the replaced fully enclosed
silt curtain. Reviewed the overall work
situation with limited marine works, it can be concluded that all the turbidity
and SS exceedances were possibly due to natural runoff from streams to the sea
as a result of frequent rainfall as recorded in the reporting period of 2
September 2022 to 31 October 2022 (Strong Monsoon Signal during 27 – 29
September 2022 and Amber Rainstorm Warning Signal on 30 September 2022;
Tropical Cyclone Warning Signals recorded on 16-17 Oct 2022. There was also
Strong Monsoon Signal on 9, 16, 18, 19, 23, 25 and 26 Oct 2022).
8.2.9
All action and limit level exceedances under “or” criteria as stated in
the EM&A Manual and the derived criteria proposed in Baseline Monitoring
Report Rev. 9.2 agreed by EPD on 2 September 2022 were concluded as non-project
related upon investigation.
8.3.1
Transplanting works for plant species, Aquilaris sinensis, was completed on 26 April 2022. Maintenance
works for trees in holding nursery have commenced.
8.3.2
Monitoring of maintenance works for the transplanted plant species was
conducted at the holding nursery while in the reporting period.
8.3.3
As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of
SSWSTW which are considered to be the plant species with conservative
importance for temporarily transplanted to the nursery at Kam Tin and
eventually be transplanted to Pui O Pumping Station.
8.4.1
No environmental non-compliance was recorded in present quarter.
8.5.1
There was no particular action taken since no non-compliance was
recorded in present quarter.
Figure 2.1
Project Organisation Chart
Figure 2.2
Master Layout Plan
Figure 5.1
Locations of Noise Monitoring Station
Figure 5.2
Locations of Water Quality Monitoring Stations
Appendix 5.1
Noise Monitoring Graphical Presentations
Appendix 5.2
Marine Water Quality Monitoring Graphical and
Summary of Exceedance Presentations
Appendix 5.3
Quarterly Summary Waste Flow Table