CONTRACT NO: SD 6/2020
Construction of San Shek Wan Sewage Treatment Works
Associated Submarine Outfall and Pui O Sewerage Works Under Environmental Permit no. EP-538/2017
quarterly Environmental Monitoring & Audit
Report
November 2021 - January 2022
revision 2
|
|
CLIENTS: |
|
|
Drainage Services Department |
Lam Environmental Services Limited 19/F Remex Centre, 42 Wong Chuk Hang Road, Hong Kong Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
|
|
|
Certified
by: |
|
|
Melody Cheng Environmental
Team Leader |
|
|
DATE: |
|
|
11 May 2022 |
|
|
|
1.1.......... Scope of the Report
1.2.......... Structure of the Report
2.1.......... Project Organization
and Key Contact Personnel
2.2.......... Construction Programme
3. A Brief Summary of EM&A
Requirements
3.1.......... Monitoring Parameters
3.2.......... Environmental Quality
Performance Limits
4.2.......... Environmental
Mitigation Measures
4.3.......... Environmental
monitoring requirements and contractual requirements
5. Monitoring Results Analysis
5.1.......... Noise Monitoring
5.2.......... Water Quality
Monitoring
5.3.......... Waste Management
6. Complaints, Notification of Summons
and Prosecution
7. Comments and Recommendations
lIST OF TABLES
Table 2.1 Contact
Details of Key Personnel
Table 4.1 Summary of submission status under
EP-538/2017
Table 5.1 Summary of Quantities of Waste
Material (November 2021 to January 2022)
Table 6.1 Cumulative Statistics on
Complaints
Table 6.2 Cumulative Statistics on
Successful Prosecutions
Table 7.1 Construction Activities and
Recommended Mitigation Measures in Past 3 Months
lIST OF FIGUREs
Figure 2.1 Project Organization Chart
Figure
5.1 Locations of Noise
Monitoring Station
Figure
5.2 Locations of Water Quality Monitoring
Stations
lIST OF APPENDIces
Appendix 5.1 Noise Monitoring Results and Graphical
Presentations
Appendix
5.2 Monthly Summary Waste Flow Table
& Yearly
Summary Waste Flow Table
EXECUTIVE SUMMARY
i.
This
is the Environmental Monitoring and Audit (EM&A) Quarterly Report
– November
2021 to January 2022 of
Outlying Islands Sewerage Stage
2 – South Lantau Sewerage Works under Environmental Permit no. EP-538/2017
(Hereafter as “the Project”). The construction works of the Project was
commenced on 3 November 2021 and the tentative completion date is Q1 2026. The EM&A report
presenting the environmental monitoring findings and information recorded
during the period of 01 November 2021 to 31 January 2022.
The cut-off date of reporting is at the end of each reporting month.
ii.
In
the reporting months, the principal work activities conducted are as follow:
|
November 2021 |
December 2021 |
January 2022 |
|
·
Ground investigation works and preliminary drilling works at San Shek
Wan Sewage Treatment Works (SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Village
sewers (excavation, sewer laying, construction of manhole) at Pui O Lo Uk
Tsuen |
·
Ground investigation works and preliminary drilling works at San Shek
Wan Sewage Treatment Works (SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Village sewers (excavation, sewer laying, construction of manhole) at
Pui O Lo Uk Tsuen |
·
Tree pruning, removal, digging Recipient site preparation and transplanting
works at San Shek Wan Sewage Treatment Works (SSWSTW) and Pui O Sewage
Pumping Station (POSPS) ·
Site formation at SSWSTW ·
Village sewers (excavation, sewer laying, construction of manhole) at
Pui O Lo Uk Tsuen |
Exceedances of Action/Limit Levels
Noise Monitoring
iii.
Noise monitoring was conducted at five (5)
noise monitoring stations N12a, N12b, N13, N14 and N17 once per week in the
reporting month.
iv.
No action or limit level exceedance was recorded in construction noise
level in this reporting period.
Water Quality Monitoring
v.
No water quality monitoring
was conducted at nine (9) monitoring stations three
days per week in the reporting month due to no
marine-based construction works.
Complaint log
vi.
No environmental complaint regarding the construction works
was recorded in present quarter.
Notifications
of Any Summons and Successful Prosecutions
vii.
No environmental notification of any summons and
successful prosecution regarding the construction works was recorded in present quarter.
1.1.1.
Lam Environmental Services Limited (LES) has been appointed to work as
the Environmental Team (ET) under Environmental Permit (EP) no. EP-538/2017 to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Outlying Islands Sewerage Stage 2 - South Lantau
Sewerage Works (Register No.: AEIAR-210/2017).
1.1.2.
The quarterly EM&A Report is prepared according to Section 12.3 of
the Project EM&A Manual.
Section 1 Introduction – details the scope and structure of the report
Section 2 Basic
Project Information – a synopsis of project
organization, programme contacts of key management, and a synopsis of work undertaken
during the quarter.
Section 3 A
Brief Summary of EM&A requirements – including monitoring parameters, environmental quality
performance limits (Action and Limit levels); and environmental mitigation
measure, as recommended in the EIA Report.
Section 4 Implementation
Status – Advice on the implementation
status of environmental protection and pollution control/mitigation measures,
as recommended in the EIA Report and summarised in the updated implementation schedule.
Section 5 Monitoring
Results Analysis – the trends of the
monitoring parameters in present quarter; advice on the solid and liquid waste
management status.
Section 6 Summary
of Non-Compliance (exceedances) of the environmental quality performance
limits, Complaints,
Notification of Summons and Successful Prosecutions
A brief review of the reasons
for and the implications of non-compliance and a summary description of the
actions taken and any follow-up procedures related to earlier non-compliance.
A summary record of all
complaints received (written or verbal) for each media, liaison and
consultation undertaken, actions and follow-up procedures taken;
A summary record of
notifications of summons and successful prosecutions for breaches of the
current environmental protection/pollution control legislations, including
locations and nature of the breaches, investigation, follow-up actions taken
and results;
Section 7 Comments and Recommendations – such as effectiveness and efficiency of the mitigation
measures, improvement in the EM&A programme, if any.
Section 8 Conclusion
and Project Proponent’s contacts and hotline telephone number for the public to
make enquiries
2.1.1
Drainage Services Department is the overall project controllers for the
Project. For the construction phase of the Project, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues. Key personnel and contact particulars
are summarized in Figure
2.1 and Table 2.1:
Table 2.1 Contact Details of Key Personnel
|
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
|
Drainage
Services Department (DSD) |
The Engineer for the
Contract |
Engineer |
Mr. Silas Chan |
2594 7272 |
3104 6426 |
|
Binnies
Hong Kong Limited |
Engineer’s
Representative |
Resident
Engineer |
Mr. Clarence Chak |
6428 5532 |
- |
|
Kwan
Lee – Chun Wo Joint Venture |
Contractor
|
Site
Agent |
Mr. Charles Tse |
9270 3384 |
2744 6937 |
|
Environmental
Officer |
Ms. Shirley Kong |
5162 5933 |
|||
|
SMEC Hong Kong |
Independent Environmental
Checker (IEC) |
Independent Environmental Checker (IEC) |
Ms. Kitty Lee |
3995 8140 |
3995 8101 |
|
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Ms. Melody Cheng |
2882 3939 |
2882 3331 |
2.2.1
The proposed sewerage works will collect the sewage generated from
the unsewered areas of Shui Hau, Tong Fuk,
Cheung Sha, San Shek Wan, Pui O and Ham Tin in South
Lantau (i.e. within the Project Catchment Area) and convey it to a proposed
sewage treatment works at San Shek Wan for treatment and disposal
into outer bay of Pui O/ Chi Ma Wan via a submarine outfall.
2.2.2
The entire Project are divided into three contracts. Contract No.
DC/2020/20 (the Contract) would have the following implementations as
demonstrated in Figure 2.2.
2.2.3
The major components of the Project under Environmental Permit (EP) (EP
No. EP-538/2017) comprises: (i) construction of sewage treatment works at San
Shek Wan (SSWSTW) and associated submarine outfall; (ii) construction of sewage
pumping station at Pui O (POSPS); (iii) village sewage works at Pui O; and (iv)
trunk sewers and rising mains on carriageways.
Noise
Monitoring
3.1.1 The construction noise level shall
be measured in terms of the A-weighted equivalent continuous sound pressure
level (Leq). Leq (30min) should be used as the monitoring parameter. Supplementary
information for data auditing, statistical results such as L10 and L90 shall
also be obtained for reference.
3.1.2 For impact monitoring for
construction of village sewers / rising main, noise monitoring should be
undertaken on weekly basis. One set of Leq (30min) noise level as six
consecutive Leq (5min) between 07:00-19:00 hours on normal weekdays.
Water Quality Monitoring
3.1.3 In construction phase, the levels
of dissolved oxygen (DO), temperature, turbidity and salinity should be measured
in situ while suspended solids (SS) is determined by laboratory analysis.
Noise
Monitoring
3.2.1 No action or limit level exceedance was
recorded in construction noise level in this reporting period.
Water
Quality Monitoring
3.2.2 Due to no marine-based construction
works in reporting period, water quality monitoring was not conducted.
4.1.1
Mitigation measures according to the environmental mitigation
implementation schedule in Annex A of EM&A Manual were generally
implemented by the Contractor. Hence, the EM&A programme was considered
effective and shall be maintained.
4.2.1
Environmental mitigation measures mentioned the EIA Report were weekly reviewed
and recorded in Weekly Environmental Site Audit Checklist. Also, a summary of
the submission status of the reporting quarter on submissions and measures
mentioned in Environmental Permit (EP-538/2017) are shown in Table
4.1.
Table 4.1 Summary of submission
status under EP-538/2017
|
EP Condition |
Submission |
Date of Latest Submission to EPD^ / EPD Approval# |
|
Condition 2.10 |
Waste Management Plan (Rev. 5) |
19 Nov 2021^ |
|
Condition 2.11 |
Submission of Preservation and/or Transplantation Plan for Plant
Species of Conservation Importance (Rev. 4) |
25 June 2021^ |
|
Condition 2.12 |
Submission of Compensatory Woodland Planting Plan (Rev. 5) |
2 July 2021^ |
|
Condition 2.13 |
Silt Curtain Deployment Plan (Stage 1) |
31 Jan 2022^ |
|
Condition 2.14 |
Landscape Mitigation Plan |
To be confirmed |
|
Condition 2.15 |
Construction Noise Mitigation Plan |
29 Dec 2021^ |
4.3.1
A summary of the submission status of the reporting quarter on licences
and/or permits on environmental protection pertinent to the Project is shown in
Table 4.2.
Table 4.2 Summary of the
current status on licences and/or permits on environmental protection pertinent
to the Project
|
Permits and/or Licences |
Permit.
No. / Account No. |
Issued Date |
Valid Period & Expiry Date (dd-mm-yyyy to dd-mm-yyyy) |
Status |
|
Notification
of Works Under APCO |
466408 |
14 Apr
2021 |
N/A |
Valid |
|
Discharge
Licence |
POPS:
WT00039820-2021 SSWSTW:
WT00039636-2021 |
31 Dec
2021 30 Dec
2021 |
31-12-2021
to 31-12-2026 30-12-2021
to 31-12-2026 |
Valid |
|
Billing
account under Waste Disposal Ordinance |
Account
No.: 7040411 |
05 May
2021 |
N/A |
Valid |
|
Registration
as a Chemical Waste Producer |
0000-931-K3428-01 |
13 May
2021 |
N/A |
Valid |
|
Construction
Noise Permit |
GW-RS0921-21 |
26 Nov
2021 |
29-11-2021
to 28-05-2022 |
Valid |
Note: Only include
those valid or under application; fill in “N/A” for non-applicable item(s).
5.1.1
Noise monitoring was conducted at five (5) noise monitoring stations N12a,
N12b, N13, N14 and N17 once per week in present quarter.
5.1.3
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise monitoring results and graphical presentation
can be referred in Appendix 5.1.
5.1.4
One set of Leq(30min) was recorded 77.3 dB(A) at N12b (Lo Uk
Tsuen) on 23 December 2021. Construction noise sources and other noise sources
are recorded during the noise measurement. Construction noise sources include
grinder, handheld breaker and excavator in Lo Uk Tsuen sewer works; non-project
related traffic noise at South Lantau Road was also recorded. The construction
noise level was 67.4 dB(A) when factor out baseline level of 76.8 dB(A), which
is below limit level.
5.1.5
No action or limit level exceedance was recorded in
construction noise level in this present quarter.
5.2.1
Water quality monitoring involves nine (9)
monitoring stations and to be conducted three days per week upon commencement
of marine works.
5.2.3
Due to no marine-based construction works in present quarter, no water quality
monitoring was conducted. Water quality monitoring results to be measured in the upcoming
reporting period will be reviewed and summarized.
5.3.1
The quantities of waste for disposal in present
quarter are summarized in Table 5.1. The Quarterly Summary
Waste Flow Table and Yearly Summary Waste Flow Table are
shown in Appendix
5.2.
Table 5.1 Summary of Quantities of Waste Material (November 2021 to January
2022)
|
Waste Type |
Quantity for reporting quarter |
Cumulative Quantity-to-Date |
|
Hard Rock and Large Broken Concrete (Inert) (in ‘000m3) |
0 |
0 |
|
Reused in this Contract (Inert) (in ‘000m3) |
0 |
0 |
|
Reused in other Projects (Inert) (in ‘000m3) |
0 |
0 |
|
Disposal as Public Fill (Inert) (in ‘000m3) |
0.86687 |
0.86687 |
|
Metals (in ‘000kg) |
0.00720 |
0.00720 |
|
Paper / Cardboard Packing (in ‘000kg) |
0.02448 |
0.02448 |
|
Plastics (in ‘000kg) |
0.00696 |
0.00696 |
|
Chemical Wastes (in ‘000kg) |
0 |
0 |
|
General Refuses (in ‘000kg) |
178.95 |
178.95 |
*:
Further
breakdown into sub-group if considered applicable;
*: Please also
provide daily dumping report for our records.
*: Delete as
appropriate
6.1.1
No environmental
complaint, notification of summons and successful prosecution regarding
construction works was recorded in present quarter.
6.1.2
Cumulative statistic on complaints and successful prosecutions are
summarized in Table 6.1 and Table 6.2 respectively.
Table 6.1 Cumulative
Statistics on Complaints
|
Reporting
Period |
No.
of Complaints |
|
November
2021 - January 2022 |
0 |
|
Project
commencement to the end of last reporting month |
- |
|
Total |
0 |
Table 6.2 Cumulative
Statistics on Successful Prosecutions
|
Environmental
Parameters |
Cumulative
No. Brought Forward |
No.
of Successful Prosecutions this month (Offence Date) |
Cumulative
No. Project-to-Date |
|
Air |
- |
0 |
0 |
|
Noise |
- |
0 |
0 |
|
Water |
- |
0 |
0 |
|
Waste |
- |
0 |
0 |
|
Other |
- |
0 |
0 |
|
Total |
- |
0 |
0 |
7.1.1
In the reporting months, the principal work activities conducted are as
follow.
Table 7.1 Construction Activities in Past 3 Months
|
November 2021 |
December 2021 |
January 2022 |
|
·
Ground investigation works and preliminary drilling works at San Shek
Wan Sewage Treatment Works (SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Village
sewers (excavation, sewer laying, construction of manhole) at Pui O Lo Uk
Tsuen |
·
Ground investigation works and preliminary drilling works at San Shek
Wan Sewage Treatment Works (SSWSTW) and Pui O Sewage Pumping Station (POSPS) ·
Village sewers (excavation, sewer laying, construction of manhole) at
Pui O Lo Uk Tsuen |
·
Tree pruning, removal, digging Recipient site preparation and
transplanting works at San Shek Wan Sewage Treatment Works (SSWSTW) and Pui O
Sewage Pumping Station (POSPS) ·
Site formation at SSWSTW ·
Village sewers (excavation, sewer laying, construction of manhole) at
Pui O Lo Uk Tsuen |
7.1.2
The recommended mitigation measures for the past 3 months are listed
below:
• Proper
water pollution control measures to be taken to prevent untreated effluent
discharge from site work
• Dust
control during dust generating works;
• Implementation
of proper noise pollution control;
• Tree
protection works within the Project Site; and
• Proper
waste handling, recycling and storage.
The implemented mitigation
measures are considered effective.
8.1.1
No action or limit level exceedance was recorded in construction noise
level in this present quarter.
8.2.1
Due to no marine-based construction works in present quarter, no water
quality monitoring was conducted.
8.3.1
No environmental non-compliance was recorded in present quarter.
8.4.1
There was no particular action taken since no non-compliance was
recorded in present quarter.
Figure 2.1
Project Organisation Chart
Figure 2.2
Master Layout Plan
Figure 5.1
Locations of Noise Monitoring Station
Figure 5.2
Locations of Water Quality Monitoring Stations
Appendix 5.1
Noise Monitoring Results and Graphical
Presentations
Appendix 5.2
Monthly Summary Waste Flow Table
&
Yearly Summary Waste Flow Table