CONTRACT NO: SD 15/2022
Outlying
Island Sewerage Stage 2 – South Lantau Sewage Works – Environmental Team Services (2023
– 2024) Under Environmental Permit no. EP-538/2017
Monthly Environmental Monitoring & Audit Report
october 2024
revision 4
|
|
CLIENTS: |
|
|
Drainage Services Department |
Lam Environmental Services Limited 19/F, Remex Centre, 42 Wong Chuk Hang Road, Hong Kong Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
|
|
|
Certified
by: |
|
|
_______________________________ Derek Lo Environmental
Team Leader |
|
|
DATE: |
|
|
14 November 2024 |
|
|
|
1.1.......... Scope
of the Report
1.2.......... Structure
of the Report
2.............. Basic project Information and Environmental Status
2.1.......... Basic
Project Information
2.2.......... Construction
Programme
2.3.......... Works
undertaken during the month
3............. Implementation
Status
3.2.......... Environmental
Mitigation Measures
3.3.......... Environmental
monitoring requirements and contractual requirements
3.4.......... Site
Inspection and Audit Reports
4............. Monitoring
Results
4.1.......... Noise
Monitoring
4.2.......... Water
Quality Monitoring
4.4.......... Waste
Management
5............. Complaints,
Notification of Summons and Prosecution
6............. Future
Key Issues
7.1.......... Noise Monitoring
7.2.......... Water Quality Monitoring
7.3.......... Ecological
Impact Monitoring
7.4.......... Review
of the Reasons for and the Implications of Non-compliance
7.5.......... Summary
of action taken in the event of and follow-up on non-compliance
lIST
OF TABLES
Table 3.1 Summary
of submission status under EP-538/2017
Table 3.3 Summary of Environmental
Inspections
Table 4.1 Noise Monitoring Equipment
Table 4.2 Noise Monitoring Station
Table 4.3 Water Quality Monitoring Equipment
Table 4.4 Marine Water Quality Stations for
Water Quality Monitoring
Table 4.5 Action and Limit Levels of Water
Quality
Table 4.6 Summary of Marine Water Quality
Exceedances
Table 4.7 Summary of Quantities of Waste
Material
Table 5.1 Cumulative Statistics on
Complaints
Table 5.2 Summary of Complaints
Table 5.3 Cumulative Statistics on
Successful Prosecutions
Table 6.1 Construction Activities and
Recommended Mitigation Measures in Coming Reporting 3 Months
lIST OF FIGUREs
Figure
2.2 Contract Layout Plan
Figure
2.3 Locations of Noise Monitoring
Station
Figure
2.4 Locations of Water Quality
Monitoring Stations
Figure
2.5 Mark up Figure 5.4i extracted from
approved EIA Report (AEIAR-210/2017)
Figure
2.6 Location Plan for Temporary Holding
Nursery
Figure
2.7 Typical Details of Proposed Silt
Curtain
lIST OF APPENDIces
Appendix 4.1 Copies of Calibration Certificates
Appendix
4.2 Impact Monitoring Schedule for
Reporting Month and Next Month
Appendix
4.3 Noise Monitoring Results and
Graphical Presentations
Appendix 4.4 Marine Water Quality Monitoring Results and
Graphical Presentations
Appendix
4.5 Monthly Summary Waste Flow Table
Appendix 6.1 3 Months Rolling Programme
EXECUTIVE SUMMARY
i.
This
is the Monthly Environmental Monitoring and Audit (EM&A) Report
– October
2024 for the Outlying Islands Sewerage Stage 2 – South Lantau
Sewerage Works under Environmental Permit No. EP-538/2017 (Hereafter as “the
Project”). The construction works of the
Project was commenced on 3 November 2021
and the tentative completion date is Q1 2026. This Monthly EM&A Report
presents the environmental monitoring findings and information recorded during
the period of 1 to 31 October 2024. The
cut-off date of reporting is at the end of each reporting month.
ii.
In
the reporting period, the principal work activities undertaken are as follows:
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen,
South Lantau Road, Chi Ma Wan Road
·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS)
·
Removal works of Excavation and Lateral Support (ELS)
·
ELS works
·
Superstructure Reinforced Concrete (RC) Works
·
Electrical and Mechanical (E&M) Installation at POSPS
Exceedances of Action/Limit Levels
Noise Monitoring
iii.
Noise monitoring was conducted at eight (8)
noise monitoring stations (N12a, N12b,
N13, N14, N15b, N16a, N16b and N17) once per week in the reporting period.
iv.
No school examination was taken place at N17 – Bui O Public School in
the reporting period.
v.
No Action/Limit
Level exceedances were recorded in this reporting period.
Water Quality Monitoring
vi.
Water quality monitoring (WQM) had been commenced on 12 April 2022 the
designated monitoring stations three days per week with respect to marine-based
construction works commenced on 19 April 2022. HDD casing works commenced on 30
May 2022.
vii.
According to the Contractor’s construction programme and confirmed with
Engineer Representative, there is no potential marine work until further
notice. As such, pursuant to Condition 3.1 of the Environmental Permit No.
EP-538/2017, proposal of temporary suspension of impact marine water quality monitoring
was submitted to EPD on 12 July 2024 for approval. This proposal was reviewed
and verified by the Independent Environmental Checker (IEC) on 12 July 2024. The
proposal was approved by EPD on 27 August 2024, thus, impact marine water
quality monitoring had been temporarily suspended starting from 28 August 2024
until further notice. Once Contractor and Engineer Representative confirm the
actual date to resume marine work, ET will notify EPD one month in advance, and
ET will resume impact marine water quality monitoring two weeks prior to the
start of marine works.
viii.
According to the Contractor’s
construction programme and confirmed with Engineer Representative (Binnies), the
marine works will be tentatively commenced on 21 October 2024, ET notified EPD
immediately on 17 September 2024 to resume the marine water quality monitoring
two weeks prior to commencement of marine works, WQM was resumed from 7 Oct
2024.
ix.
Further confirmed with the Contactor and ER, marine works has yet to
resume and no marine work were ongoing in October 2024.
x.
In accordance with the action level and limit level in Baseline
Monitoring Report Rev. 9.2 agreed by EPD on 2 September 2022, action level
exceedances of Depth-averaged on suspended solids (SS) was recorded at SR9,
SR10 and SR12 from 07:56 to 08:12 during ebb tide on 12 Oct 2024. Action level
exceedances of Depth-averaged on suspended solids (SS) was recorded at SR5 and
SR6 from 9:07 to 9:19 during flood tide as well as at SR10 and SR12 from 14:04
to 14:11 during ebb tide on 21 Oct 2024. Action level exceedances of
Depth-averaged on suspended solids (SS) was recorded at SR15 from 13:37 to
13:38 during flood tide on 23 Oct 2024. Limit level exceedances of
Depth-averaged on suspended solids (SS) was recorded at SR4 and SR15 from 09:20
to 09:30 during ebb tide on 28 Oct 2024. Action level exceedances of
Depth-averaged on suspended solids (SS) was recorded at SR5, SR6, SR9,SR10, and
SR12 from 09:38 to 10:24 during ebb tide as well as at SR4, SR5, SR6, SR9,SR10,
SR12and SR15 from 16:01 to 17:07 during flood tide on 28 Oct 2024. Action level
exceedances of Depth-averaged on suspended solids (SS) was recorded at SR10 and
SR12 during both ebb and flood tide from 11:25 to 11:32 and 16:32 to 16:38
respectively on 30 Oct 2024.
xi.
As the suspended solids (SS) result is determined by laboratory analysis
that require 7 working days, it is not possible to increase the monitoring
frequency to daily until no exceedance of Action Level after 30 Oct 2024. If
such exceedances continuous during marine works commencement, ET will check
with contractor the implementation of the mitigation measures and daily WQM
monitoring will be considered.
xii.
As no marine work were ongoing since Jan 2024, no sign of pollution was
observed during site inspection or marine water samples collection, it is
considered that the exceedance was not related to Project works.
xiii.
For the limit level exceedances of suspended solid recorded on 28 Oct
2024, confirmed with our field technician, the seawater was observed turbid
during sampling. As no marine work was conducted in Oct 2024 and no other
evidence indicate that the limit level exceedance was affected by the site
activities, it can be concluded that the limit level exceedances were possibly
induced by other factors such as natural variation or changes of water quality
in the vicinity of water quality monitoring station.
Ecological Impact Monitoring
xiv.
Transplanting of the trees of Aquilaris sinensis was completed on 26 April 2022. Maintenance works for trees in holding
nursery have commenced.
xv.
As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of
SSWSTW which are considered to be the plant species with conservative
importance for temporarily transplanted to the nursery at Kam Tin and
eventually be transplanted to Pui O Pumping Station.
xvi.
The weekly site audit was carried out by ET include checking whether
good site practices are being properly implemented by the Contractor.
xvii.
The extent of the work site boundaries was checked by the ET during the
weekly site audit.
Complaint log
xviii.
No environmental complaint regarding the construction
works was recorded in the reporting period.
Notifications
of Any Summons and Successful Prosecutions
xix.
No environmental notification of any summons and successful
prosecution regarding the construction works was recorded in the reporting
period.
Reporting
Changes
xx.
There are no particular reporting changes.
Future
Key Issues
xxi.
In coming reporting 3 months, the scheduled construction activities are
listed as follows:
·
Excavation,
sewer laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau Road,
Chi Ma Wan Road
·
Dredging
at marine *
·
Site
formation works at SSWSTW
·
Trenchless
drilling works (Chi Ma Wan Road)
·
Excavation works
(at site area)
·
ELS works at
SSWSTW
·
Superstructure
RC Works at SSWSTW
·
Removal works of
ELS at POSPS
·
E&M
Installation at POSPS
* Note: Further confirmed with the Contactor and ER, marine works has
yet to resume and no marine work were ongoing in October 2024. The impact
marine water quality monitoring was resumed from 7 October 2024.
xxii.
Key
construction activities for the next three months with the recommended
mitigation measures to be implemented are presented as follows:
|
Key Construction Works |
Recommended Mitigation Measures |
|
·
Excavation,
sewer laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau
Road, Chi Ma Wan Road ·
Dredging
at marine* ·
Site
formation works ·
Drilling
works ·
Excavation
works ·
ELS
works ·
Superstructure
RC Works ·
Removal
works of ELS ·
E&M
Installation at POSPS |
·
Implementation of noise pollution control in accordance with
Construction Noise Mitigation Plan; ·
Dust control during dust generating works; ·
Silt curtain should be maintained in good
condition prior to and during dredging and related marine works; ·
Adopt surface drainage and sediment control facilities for sewage
installation in village and public roads; ·
Adopt temporary drainage and sediment control facilities on Site; ·
Vehicle wheel-washing and body washing facilities should be provided
at the site entrance; ·
Regular water spraying on excavation works for dust control; and ·
Proper waste handling, recycling and storage. |
1.1.1.
Lam Environmental Services Limited (LES) has been appointed to work as
the Environmental Team (ET) under Environmental Permit (EP) No. EP-538/2017 to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for the Outlying Islands Sewerage Stage 2 – South
Lantau Sewerage Works (Register No.: AEIAR-210/2017).
1.1.2.
In accordance with Clause 3.4 stated in EP-538/2017, 4 hard copies and 1
electronic copy of Monthly EM&A Report shall be submitted to the Director
within 2 weeks after the end of each reporting month.
1.1.3.
According to Section 12.2 of the Project EM&A Manual, the Monthly
EM&A Report should be submitted within 10 working days of the end of each
reporting month, with the first report due in the month after construction
commences.
Section 1 Introduction – details the scope and structure of the report.
Section 2 Basic
project Information and Environmental Status – summarizes project organization and key personnel contact,
construction programme and works undertaken for the month. Construction programme,
works undertaken during the month with illustrations, drawing showing the
project area, environmental sensitive receivers and monitoring locations.
Section 3 Implementation
Status – advice on the implementation
status of environmental protection and pollution control/mitigation measures,
as recommended in the EIA Report and summarised in the updated implementation
schedule.
Section 4 Monitoring
Results – summarizes the monitoring
results obtained in the reporting period, including monitoring methodology,
name of laboratory and equipment used and calibration details, parameters
monitored, monitoring locations (and depth), monitoring date, frequency, and
duration.
Section 5 Report
on Complaints,
Notification of Summons and Successful Prosecutions – summarizes:
Record of all complaints received (written or
verbal) for each media, including locations and nature of complaints
investigation, liaison and consultation undertaken, actions and follow-up
procedures taken, results and summary;
Record of notifications of summons and
successful prosecutions for breaches of the current environmental
protection/pollution control legislations, including locations and nature of
the breaches, investigation, follow-up actions taken, results and summary;
Review of the reasons for and the implications
of non-compliance, complaints, summons and prosecutions including review of
pollution sources and working procedures; and
Description of the actions taken in the event
of non-compliance and deficiency reporting and any follow-up procedures related
to non-compliance.
Section 6 Future Key Issues – An account of the future key issues as reviewed from
the works programme and work method statements.
Section 7 Conclusion
2.1.1. Drainage Services Department is the
overall project controllers for the Project. For the construction phase of the Project,
Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage
and control environmental issues. Key personnel and contact particulars are
summarized in Table 2.1:
Table
2.1 Contact Details of Key Personnel
|
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
|
Drainage
Services Department (DSD) |
The Engineer for the
Contract |
Engineer |
Mr. KK Chan |
2594 7297 |
3104 6426 |
|
Binnies
Hong Kong Limited |
Engineer’s
Representative |
Resident
Engineer |
Mr. Kevin Chan |
3529 3003 |
- |
|
Kwan
Lee – Chun Wo Joint Venture |
Contractor
|
Sub
Agent |
Mr. Daniel Chu |
6737 6701 |
2744 6937 |
|
Environmental
Officer |
Ms. Hassan Ka Sin / Mr. Rico Chan |
6993 0990 / 6224 9332 |
|||
|
SMEC Hong Kong |
Independent Environmental
Checker (IEC) |
Independent Environmental Checker (IEC) |
Ms. Kitty Lee |
3995 8140 |
3422 3631 |
|
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Derek Lo |
2882 3939 |
2882 3331 |
2.2.1.
The proposed sewerage works will collect the sewage generated from
the unsewered areas of Shui Hau, Tong Fuk,
Cheung Sha, San Shek Wan, Pui O and Ham Tin in South
Lantau (i.e. within the Project Catchment Area) and convey it to a proposed
sewage treatment works at San Shek Wan for treatment and disposal
into outer bay of Pui O/ Chi Ma Wan via a submarine outfall.
2.2.2.
The entire Project are divided into three contracts. Contract No.
DC/2020/20 (the Contract) would have the following implementations as
demonstrated in Figure 2.1.
2.2.3.
The major components of the Contract under Environmental Permit (EP) (EP
No. EP-538/2017) comprises: (i) construction of secondary sewage treatment
works (STW) at San Shek Wan in South Lantau; (ii) construction of sewage
pumping station (SPS) at Pui O, San Shek Wan, Cheung Sha and Cheung Fu Street;
(iii) construction of about 1.4 kilometres (km) of submarine outfall with a
diameter of 350 millimetres (mm) for the disposal of treated effluent from the
STW at San Shek Wan; (iv) construction of about 10.1 km of gravity sewers with
diameters ranging from 150 mm to 375 mm along South Lantau Road and Chi Ma Wan
road and at Pui O; and (v) construction of about 3.1 km twin rising mains with
a diameter of 200 mm to 250 mm along South Lantau Road and Chi Ma Wan Road.
2.2.4.
The performance
of the environmental management system of the reporting period was generally
satisfied. Mitigation measures according to the environmental mitigation
implementation schedule and the EIA were generally implemented by the
Contractor. Hence, the EM&A programme was considered effective and shall be
maintained.
2.3.1.
In the reporting month, the principal work activities conducted are as
follow:
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen,
South Lantau Road, Chi Ma Wan Road
·
Excavation and site formation at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS)
·
Removal works of Excavation and Lateral Support (ELS)
·
ELS works
·
Superstructure Reinforced Concrete (RC) Works
·
Electrical and Mechanical (E&M) Installation at POSPS
The
locations of works are shown in Figure
2.2.
2.4.1.
Noise and water monitoring location plans with sensitive receivers are
shown in Figure 2.3 and Figure 2.4.
3.1.1. Mitigation measures according to
the environmental mitigation implementation schedule in Annex A of EM&A
Manual were generally implemented by the Contractor. Hence, the EM&A
programme was considered effective and shall be maintained.
3.2.1.
Environmental mitigation measures mentioned the EIA Report were weekly
reviewed and recorded in Weekly Environmental Site Audit Checklist. Also, a
summary of the current status on submissions and measures mentioned in
Environmental Permit (EP-538/2017) are shown in Table 3.1.
Table 3.1 Summary of submission status under EP-538/2017
|
EP Condition |
Submission |
Date of Latest Submission to EPD^ / EPD Approval# |
|
Condition 2.10 |
Waste Management Plan (Rev. 5) (electronic copy) |
4 April 2022# |
|
Condition 2.11 |
Submission of Preservation and/or Transplantation Plan for Plant
Species of Conservation Importance (Rev. 23) |
9 September 2022# |
|
Condition 2.12 |
Submission of Compensatory Woodland Planting Plan (Rev. 23) |
15 May 2023^ |
|
Condition 2.13 |
Silt Curtain Deployment Plan (Rev. 11) |
1 June 2022# |
|
Condition 2.14 |
Landscape Mitigation Plan |
To be confirmed |
|
Condition 2.15 |
Construction Noise Mitigation Plan (Rev. 20) |
4 August 2022# |
3.3.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.2.
Table 3.2 Summary of the current status on licences
and/or permits on environmental protection pertinent to the Project
|
Permits and/or Licences |
Permit. No. / Account No. |
Issued Date |
Valid Period & Expiry Date |
Status |
|
Notification
of Works Under APCO |
466408 |
14 Apr
2021 |
N/A |
Valid |
|
Wastewater Discharge Licence under Water Pollution Control Ordinance |
SSWSTW: WT00039636-2021 |
30 Dec
2021 |
30-12-2021
to 31-12-2026 |
Valid |
|
POPS: WT00039820-2021 |
31 Dec
2021 |
31-12-2021
to 31-12-2026 |
Valid |
|
|
SSWSTW:
Gravity Sewer & Raising Main: WT00042613-2022 |
09 Jan
2023 |
09-01-2023
to 31-01-2028 |
Valid |
|
|
Billing
account under Waste Disposal Ordinance |
Account
No.: 7040411 |
05 May
2021 |
N/A |
Valid |
|
Registration
as a Chemical Waste Producer |
0000-931-K3428-01 |
13 May
2021 |
N/A |
Valid |
|
Construction
Noise Permit under Noise Control Ordinance for SSWSTW |
GW-RS0658-24 |
17
July 2024 |
09-08-2024
to 08-02-2025 |
Valid |
|
Construction
Noise Permit under Noise Control Ordinance for POSPS |
GW-RS0856-24 |
17 Sep
2024 |
27-09-2024
to 26-03-2025 |
Valid |
|
Marine
Dumping Permit (Dredged Sediment Requiring Type 1 – Open Sea Disposal |
- |
- |
- |
Renewed Marine Dumping Permit under application |
Note: Only include those valid
or under application; fill in “N/A” for non-applicable item(s).
3.4.1.
Within this reporting month, weekly environmental site inspections were
conducted on 02, 08, 17, 21 and 29 October 2024. IEC attended the SSEMC meeting
held on 21 October 2024. Holding nursery visit for
transplanted trees on 23 October 2024.
3.4.2. No non-compliance was found during the site inspection while reminders on
environmental measures were recommended. Results and
findings of these inspections in this reporting month are listed below in Table
3.3.
Table 3.3 Summary
of Environmental Inspections
|
Inspection Date |
Reminder and Recommendations |
Close-out Date / Status |
|
2 October 2024 |
Pui O Sewage Pumping Station (POSPS) – Obs1: Water barriers and cover at site boundary were found
damaged by strong wind, contractor is requested to fix/replace the damaged
barriers and cover. San Shek Wan Sewage Treatment Works (SSWSTW) – R1. Tarpaulin sheets on slope found damaged by strong wind,
contractor is reminded to arrange replacement. |
Rectified by the Contractor on 8
October 2024 |
|
8 October 2024 |
Pui O Sewage Pumping Station (POSPS) – Obs.1: Sediment accumulated in the wheel washing facilities
should be removed regularly Obs.2: Construction waste outside the site boundary should be
removed regularly South Lantau Road (car park area) Rising Mains – Obs.3: Direct discharge observed, contractor is requested to
stop immediately and re-connected to silt removal facilities prior to
discharge San Shek Wan Sewage Treatment Works (SSWSTW) – R1. Contractor is reminded to provide regular watering on main
haul road during dry season. |
Rectified by the Contractor on 8
November 2024 |
|
17 October 2024 |
Pui O Sewage Pumping Station (POSPS) – Obs.1: Copies of Environmental Permit (EP) should be displayed
at site entrances San Shek Wan Sewage treatment Works(SSWSTW) –
Obs.2: drip tray should be provided to chemical container |
Rectified by the Contractor on 21 October 2024 |
|
21 October 2024 |
Pui O Sewage Pumping Station (POSPS) – Obs.1: Drip tray should be provided to chemical container |
Chemical container was removed
during site inspection on 29 Oct 2024 |
|
29 October 2024 |
Pui O Sewage Pumping Station (POSPS) – Obs.1: Drip tray should be provide to chemical container |
Rectified by the Contractor on 5
November 2024 |
4.1.1
Monitoring
Procedure
(a)
The impact noise monitoring should be
carried out at all the designated monitoring stations when there are
project-related construction activities undertaken within a radius of 300m from
the monitoring stations.
(b)
The monitoring station shall normally
be at a point 1m from the exterior of the sensitive receiver’s building façade
and be at a position 1.2m above the ground.
(c)
Façade measurements were made at the
monitoring locations. For free-field measurement, a correction factor of +3 dB (A)
would be applied.
(d)
The battery condition was checked to
ensure the correct functioning of the meter.
(e)
Parameters such as frequency weighting,
the time weighting and the measurement time were set as follows:
(f)
Frequency weighting: A, Time weighting:
Fast, Measurement time set: continuous 5 mins
(g)
Prior and after to the noise
measurement, the meter was checked using the acoustic calibrator for 94dB (A)
at 1000 Hz. If the difference in the calibration level before and after
measurement was more than ±1.0 dB (A), the measurement would be considered
invalid and repeat of noise measurement would be required after re-calibration
or repair of the equipment.
(h)
Noise measurements will be made in
accordance with standard acoustical principles and shall not be made in fog,
rain, wind with a steady speed exceeding 5m/s or wind with gusts exceeding
10m/s. The wind speed shall be checked with a portable wind speed meter capable
of measuring the wind speed in m/s.
name of laboratory and
equipment used and calibration details
4.1.2
Noise monitoring was performed
using sound level meter at the designated monitoring locations. The sound level
meters shall comply with the International Electrotechnical Commission
Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications. Acoustic
calibrator shall be deployed to check the sound level meters at a known sound
pressure level. Brand and model of the equipment is given in Table
4.1.
Table 4.1 Noise Monitoring Equipment
|
0004797 |
||
|
Larson Davis CAL200 |
13128 |
4.1.3 The calibration certificates of the noise monitoring equipment are attached in Appendix 4.1.
4.1.4
Calibration Details
(a)
The microphone head of the sound level
meter was cleaned with soft cloth at regular intervals.
(b)
The sound level meter and calibrator
were calibrated at yearly intervals.
Parameters monitored
4.1.5
The
construction noise level shall be measured in terms of the A-weighted
equivalent continuous sound pressure level (Leq). Leq(30min)
should be used as the monitoring parameter. Supplementary information for data auditing, statistical results
such as L10 and L90 shall also be obtained for reference.
4.1.6
For
impact monitoring for construction of village sewers / rising main,
noise monitoring should be undertaken on weekly basis. One set of Leq(30min)
noise level as six consecutive Leq(5min) between 07:00-19:00 hours
on normal weekdays.
Monitoring Stations
4.1.7
The
noise monitoring stations for the Project are listed and shown in Table 4.2,
impact noise monitoring was conducted at Eight (8) noise monitoring stations N12a, N12b, N13, N14, N15b,
N16a, N16b and N17 once per week in the reporting month.
Table 4.2 Noise
Monitoring Station
|
Monitoring
Station ID (1) |
Monitoring
Location |
Measurement
Type |
Level (in terms
of no.
of floor) |
|
N01a |
Shui Hau Village |
Free-Field |
G/F |
|
N01c |
Shui Hau Village |
Free-Field |
G/F |
|
N03a |
Tong Fuk Village |
Free-Field |
G/F |
|
N05a |
Residences at Cheung Fu Street |
Free-Field |
G/F |
|
N07 |
Government Holiday Bungalows |
Free-Field |
G/F |
|
N08 |
Cheung Sha Ha Tsuen |
Free-Field |
G/F |
|
N10 |
Cheung Sha Sheung Tsuen |
Façade |
G/F |
|
N11b |
San Shek Wan – Ming Garden |
Free-Field |
G/F |
|
N12a |
Lo Uk Tsuen |
Free-Field |
G/F |
|
N12b |
Lo Uk Tsuen |
Façade |
G/F |
|
N13 |
Pui O San Wai Tsuen |
Façade |
G/F |
|
N14 |
South Lantau Community Centre |
Free-Field |
G/F |
|
N15b |
Pui O Lo Wai Tsuen |
Façade |
G/F |
|
N16a |
Residences at Ham Tin |
Free-Field |
G/F |
|
N16b |
Residences at Ham Tin |
Free-Field |
G/F |
|
N17 |
Bui O Public School |
Façade |
R/F |
Remarks (1): Fine
adjustment of noise monitoring stations at all locations was proposed as per EP
Condition 3.1.
Monitoring date, time,
Frequency and Duration
4.1.8
For
daytime construction work on normal weekdays, monitoring of Leq(30min)
should be carried out at each station at 0700-1900 hours on normal weekdays at
a frequency of once a week. Impact
monitoring schedule can be referred to Appendix
4.2.
Noise Monitoring Results
4.1.9
Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring results and graphical presentation can
be referred in Appendix 4.3.
4.1.10 No school examination was taken place at N17 – Bui
O Public School in the reporting period.
4.1.11
No action or limit level exceedance was recorded in construction
noise level in this reporting period.
Monitoring Methodology
4.2.1
Monitoring
Procedure
(a)
The condition near the monitoring
stations shall be observed and recorded on the data log sheet.
(b)
Check of sensors and electrodes with
certified standard solutions before each use.
(c)
Wet bulb calibration for a DO meter
should be carried out before measurement.
(d)
Water depth should be recorded by
detector before sampling.
(e)
Sample would be taken using bucket
sampler at surface level.
(f)
Transfer the sampled water carefully
into cleaned water bottles (2x 1000ml) provided by the laboratory at the spot
after the collection of the water sample for the subsequent laboratory
Suspended Solid testing.
(g)
Transfer the sampled water from the
bucket sampler to the rinsed water container for in-situ measurement (In case
of the in-situ measurement cannot be carried at spot due to safety and adverse
weather condition, sampled water from the bucket sampler will be transfer to
cleaned water bottles provided by laboratory. Then, In-situ measurement will be
conducted at a safe location which sampled water inside cleaned water bottle
will be transfer to the rinsed water container for in-situ measurement) In-situ
measurement shall be measured in duplicate.
(h)
Parameters including Water Temperature
(°C), pH (units), Salinity (ppt), DO (mg/L), DO saturation (%) will be
measured by the Multifunctional Meter and Turbidity (NTU) will be measured by turbid
meter. (Water Temperature and Salinity will be measured as reference
parameters)
(i)
Record the result on the data log sheet
and record any special finding during / after in-situ measurement.
(j)
The water sample bottles will be stored
in a cool box (at cooled to 4°C without
being frozen), which shall be delivered to HOKLAS laboratory (ALS Technichem
(HK) Pty Ltd) for further testing to determine the level of SS.
Name of laboratory and
equipment used and calibration details
Laboratory Measurement /
Analysis
4.2.2
Analysis
of suspended solids will be carried out in a HOKLAS accredited laboratory,
which is ALS Technichem (HK) Pty Ltd.
equipment used
Dissolved Oxygen, pH And Temperature Measuring
Equipment
4.2.3
Multifunctional
Meter and Turbid Meter are used at each designated monitoring station. They are
capable of measuring:
(a)
a dissolved oxygen level in the range
of 0-20mg/L and 0-200% saturation (Detection Limit: 0.1mg/L)
(b)
a temperature of 0-45 degree Celsius (Detection Limit: 0.1 degree Celsius)
(c)
turbidity level between 0-1000NTU (Detection
Limit: 0.1NTU)
(d)
salinity in the range of 0-40ppt (Detection
Limit: 0.1ppt)
(e)
pH value in range of 0.0 – 14.0
(Detection Limit: 0.1units)
Other monitoring equipment namely water depth meter, water current
meter, dGPS positioning device, water sampler listed below were also deployed,
(a)
Water depth meter (Range: 0.6 -100m, Resolution: 0.1m)
(b)
Water current meter (Range: 0-360o, Detection
Limit: 1mm/s)
(c)
dGPS positioning device (Resolution: Horizontal: 0.25m; Vertical:
0.50 m )
(d)
Water sampler (Horizontal discrete type, Capacity: 2.2L)
Sampler Container and Storage
4.2.4
A
water sampler, Water samples for suspended solids measurement should be
collected in high-density polythene bottles, packed in ice (cooled to 4°C
without being frozen), and delivered to ALS Technichem (HK) Pty Ltd. as soon as
possible after collection for analysis.
Water Depth Detector
4.2.5
A
portable, battery-operated echo sounder shall be used for the determination of
water depth at each designated monitoring station. This unit can either be
handheld or affixed to the bottom of the workboat, if the same vessel is to be
used throughout the monitoring programme.
calibration details
4.2.6
Maintenance
and Calibration
(a)
The responses of sensors and electrodes
of the water quality monitoring equipment were cleaned and checked at regular
intervals.
(b)
DO meter (Multifunctional Meter) and
turbid meter was certified by a laboratory accredited under HOKLAS or any other
international accreditation scheme, and subsequently re-calibrated at three
monthly intervals.
4.2.7
Brand and model of the
equipment are given in Table 4.3.
Table
4.3 Water Quality Monitoring Equipment
|
Equipment |
Brand and
model |
Series
Number |
|
Multifunctional Meter |
YSI Professional Plus |
17G100383 |
|
Turbid meter |
WGZ-3B |
1807063 |
Calibration certificates of the water
quality monitoring equipment are attached in Appendix 4.1.
Parameters monitored
4.2.8
In
construction phase, the levels of dissolved oxygen (DO), temperature, turbidity
and salinity should be measured in situ while suspended solids (SS) is determined
by laboratory analysis.
MONITORING STATIONS
4.2.9
Water quality monitoring involves
9 monitoring stations. The locations of water quality monitoring station are
shown in Table 4.4.
Table 4.4 Marine
Water Quality Stations for Water Quality Monitoring
|
Station |
Description |
Easting |
Northing |
|
CE |
Upstream
control station at ebb tide |
810838 |
807538 |
|
CF |
Upstream
control station at flood tide |
815886 |
808081 |
|
SR4 (1) |
Ecological
Sensitive Receiver (Coral Communities) at Pui O Wan |
814938 |
810975 |
|
SR5 |
Ecological
Sensitive Receiver (Coral Communities) at Pui O Wan |
814326 |
810540 |
|
SR6 |
Gazetted Bathing Beach at Lower Cheung Sha |
810553 |
810475 |
|
SR9 (1) |
Ecological Important Stream
at Tong Fuk |
811325 |
809787 |
|
SR10 |
Secondary Contact
Recreational Zones at South Lantau |
810561 |
809494 |
|
SR12 (1) |
Proposed Special Site of
Scientific Interest (SSSI) at Shui Hau Wan |
810359 |
808989 |
|
SR15 |
Gazetted Bathing Beach at Pui O and Ecologically Important Stream at Pui O |
816037 |
810722 |
Remarks (1): Fine adjustment of water
quality monitoring stations at SR4, SR9 and SR12 was proposed as per EP
Condition 3.1, and baseline monitoring was conducted at corresponding fine
adjusted locations.
Monitoring date, time,
Frequency and Duration
4.2.10 Water quality monitoring had been
commenced on 12 April 2022 the designated monitoring stations three days per
week with respect to marine-based construction works commenced on 19 April
2022. HDD casing works commenced on 30 May 2022.
4.2.11 To support water quality monitoring, the
silt curtain deployment plan has minor updates to include an additional brand
of geosynthetic material as alternative for selection and adopt underwater
robot for inspecting condition of silt curtain.
4.2.12 For the upcoming marine works (stage 3
and stage 4), new silt curtain extension to be applied at diffuser and
emergency bypass constructions has been proposed and supplemented in the
revised silt curtain deployment plan. Typical details of proposed silt curtain
are shown in Figure
2.7.
4.2.13
The
levels of dissolved oxygen (DO), temperature, turbidity and salinity were
measured in situ while suspended solids (SS) is determined by laboratory
analysis at all the monitoring stations in Table 4.4 three times a week. Impact
monitoring schedule can be referred to Appendix
4.2.
4.2.14
In
association with the water quality parameters, other relevant data shall also
be recorded, such as monitoring location / position, time, water temperature,
DO saturation, weather conditions, and any special phenomena underway near the
monitoring station.
4.2.15
Impact
Monitoring shall be carried out three days per week, at mid-flood and mid-ebb
tides (within ± 1.75 hour of the predicted time). The interval between two sets
of monitoring shall not be less than 36 hours. The monitoring period should
avoid concurrent marine project in the vicinity.
4.2.16
The
sampling frequency of at least three days per week should be undertaken. Upon
completion of the construction works, the monitoring exercise at the designated
monitoring locations should be continued for four weeks in the same manner as
the impact monitoring. In case exceedance of Action/Limit Level is recorded,
the frequency shall be increased as per the Event and Action Plan.
4.2.17
To
ensure the robustness of in-situ measurement, parameters shall be measured in
duplicate. In case the difference between duplicates is larger than 25%, a
third set of measurement shall be carried out.
Monitoring Results
4.2.18 Marine water quality monitoring results measured in
this reporting period are reviewed and summarized. Details of marine water
quality monitoring results and graphical presentation can be referred in Appendix 4.4
4.2.19 Water quality monitoring is evaluated
against Action and Limit Levels. The derived Action and Limit Level proposed in
Baseline Monitoring Report Rev. 9.2 was agreed by EPD on 2 September 2022.
Action and Limit Levels of marine water quality monitoring have been set with
reference to the derived criteria as shown in Table 4.5 below for
reference.
Table 4.5 Action
and Limit Levels of Water Quality
|
Parameters |
Action Level |
Limit Level |
|
Construction
Phase Marine Water Monitoring - derived criteria |
||
|
DO in mg/L
B |
Surface and Middle: 5.8 mg/L Bottom: 5.9 mg/L |
Surface and Middle: 4 mg/L Bottom: 2 mg/L |
|
Turbidity
in NTU (Depth-averaged A) C |
14.4 NTU and 20% exceedance of value at any impact station compared with
corresponding data from control station D |
23.5 NTU and 30% exceedance of value at any impact station compared with corresponding
data from control station D |
|
SS in mg/L (Depth-averaged
A) C |
13.1 mg/L and 20% exceedance of value at any impact station compared with
corresponding data from control station D |
30.4 mg/L and 30% exceedance of value at any impact station compared with corresponding
data from control station D |
Notes (with proposed amendments in AL/LL in
underlined text):
A. “Depth-averaged” is calculated by taking
the arithmetic means of reading of all three depths.
B. For DO, non-compliance of the water
quality limits occurs when monitoring result is lower than the limits.
C. For SS and turbidity, non-compliance of
the water quality limits occurs when monitoring result is higher than the
limits.
D. Action Level and Limit Level with 95%-ile /
99%-ile derived from baseline data “and” 20% / 30% exceedance of control
station proposed in Baseline Monitoring Report.
4.2.20 Number of exceedances recorded during the reporting
month are summarized in Table 4.6.
Table 4.6 Summary
of Marine Water Quality Exceedances
|
|
Parameter |
DO (S&M) |
DO (Bottom) |
Turbidity |
SS |
Exceedance count |
|||||
|
Station |
Level exceeded |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
|
SR4 |
Action |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
|
Limit |
/ |
/ |
/ |
/ |
/ |
/ |
1 |
/ |
1 |
0 |
|
SR5 |
Action |
/ |
/ |
/ |
/ |
/ |
/ |
1 |
2 |
1 |
2 |
|
|
Limit |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
SR6 |
Action |
/ |
/ |
/ |
/ |
/ |
/ |
1 |
2 |
1 |
2 |
|
|
Limit |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
SR9 |
Action |
/ |
/ |
/ |
/ |
/ |
/ |
2 |
1 |
2 |
1 |
|
|
Limit |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
SR10 |
Action |
/ |
/ |
/ |
/ |
/ |
/ |
4 |
2 |
4 |
2 |
|
|
Limit |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
SR12 |
Action |
/ |
/ |
/ |
/ |
/ |
/ |
4 |
2 |
4 |
2 |
|
|
Limit |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
SR15 |
Action |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
2 |
0 |
2 |
|
|
Limit |
/ |
/ |
/ |
/ |
/ |
/ |
1 |
/ |
1 |
0 |
|
Total |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
12 |
11 |
23 |
|
|
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
0 |
2 |
|
4.2.21 According to the Contractor’s
construction programme and confirmed with Engineer Representative, there is no
potential marine work until further notice. As such, pursuant to Condition 3.1
of the Environmental Permit No. EP-538/2017, proposal of temporary suspension
of impact marine water quality monitoring was submitted to EPD for approval on
12 July 2024. This proposal was reviewed and verified by the Independent
Environmental Checker (IEC) on 12 July 2024. The proposal was approved by EPD
on 27 August 2024, thus, impact marine water quality monitoring had been temporarily
suspended starting from 28 August 2024 until further notice. Once Contractor
and Engineer Representative confirm the actual date to resume marine work, ET
will notify EPD one month in advance, and ET will resume impact marine water
quality monitoring two weeks prior to the start of marine works.
4.2.22 According to the Contractor’s
construction programme and confirmed with Engineer Representative (Binnies),
the marine works will be commenced on 21 October 2024, ET notified EPD
immediately on 17 September 2024 to resume the marine water quality monitoring
two weeks prior to commencement of marine works, WQM was resumed from 7 Oct
2024.
4.2.23 Further confirmed with the Contactor and ER, marine
works has yet to resume and no marine work were ongoing in October 2024.
4.2.24 In accordance with the action level and
limit level in Baseline Monitoring Report Rev. 9.2 agreed by EPD on 2 September
2022, action level exceedances of Depth-averaged on suspended solids (SS) was
recorded at SR9, SR10 and SR12 from 07:56 to 08:12 during ebb tide on 12 Oct
2024. Action level exceedances of Depth-averaged on suspended solids (SS) was
recorded at SR5 and SR6 from 9:07 to 9:19 during flood tide as well as at SR10
and SR12 from 14:04 to 14:11 during ebb tide on 21 Oct 2024. Action level
exceedances of Depth-averaged on suspended solids (SS) was recorded at SR15
from 13:37 to 13:38 during flood tide on 23 Oct 2024. Limit level exceedances
of Depth-averaged on suspended solids (SS) was recorded at SR4 and SR15 from
09:20 to 09:30 during ebb tide on 28 Oct 2024. Action level exceedances of
Depth-averaged on suspended solids (SS) was recorded at SR5, SR6, SR9,SR10, and
SR12 from 09:38 to 10:24 during ebb tide as well as at SR4, SR5, SR6, SR9,SR10,
SR12and SR15 from 16:01 to 17:07 during flood tide on 28 Oct 2024. Action level
exceedances of Depth-averaged on suspended solids (SS) was recorded at SR10 and
SR12 during both ebb and flood tide from 11:25 to 11:32 and 16:32 to 16:38
respectively on 30 Oct 2024.
4.2.25 As the
suspended solids (SS) result is determined by laboratory analysis that require
7 working days, it is not possible to increase the monitoring frequency to
daily until no exceedance of Action Level after 30 Oct 2024. If such
exceedances continuous during marine works commencement, ET will check with
contractor the implementation of the mitigation measures and daily WQM
monitoring will be considered.
4.2.26 As no marine
work were ongoing since Jan 2024, no sign of pollution was observed during site
inspection or marine water samples collection, it is considered that the
exceedance was not related to Project works.
4.2.27 For the limit
level exceedances of suspended solid recorded on 28 Oct 2024, confirmed with
our field technician, the seawater was observed turbid during sampling. As no
marine work was conducted in Oct 2024 and no other evidence indicate that the limit level exceedance was
affected by the site activities, it can be concluded that the limit level
exceedances were possibly induced by other factors such as natural variation or
changes of water quality in the vicinity of water quality monitoring station.
MONITORING METHODOLOGY
4.3.1
The
weekly site audit to be carried out by the ET should include checking whether
good site practices are being properly implemented by the Contractor.
4.3.2
Impact
monitoring of the transplanted Aquilaris sinensis at holding nursery and one retain tree of Aquilaris sinensis in SSWSTW Project
Site, establishment and after-establishment caring measures of the compensatory
mixed woodland to ensure the affected tree would not be affected by any
unacceptable construction works. The trees would be treated with establishment
works immediately after transplanting.
PARAMETERS MONITORED
4.3.3
The
extent of the work site boundaries should be checked by the ET during the
weekly site audit. Any disturbance by
the Contractor outside the works area especially any damage to the vegetation
and surrounding habitats outside the Project area shall be reported to ER and
IEC.
4.3.4
To
identify any unacceptable construction works for the trees of Aquilaris sinensis during transplanting,
establishment and after-establishment caring measures of the compensatory mixed
woodland.
MONITORING LOCATION
4.3.5
As
per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of SSWSTW (Figure
2.5) which are considered to be the plant species with
conservative importance for temporarily transplanted to the nursery (Figure
2.6) at Kam Tin and eventually be transplanted to Pui O
Pumping Station.
MONITORING DATE, TIME,
FREQUENCY AND DURATION
4.3.6
The
recommended good site practices to be audited once every week as part of the
site audit programme. The weekly site audit to be carried out by the ET
includes checking whether good site practices are being properly implemented by
the Contractor. Results are recorded in Weekly Environmental Site Audit
Checklist.
4.3.7
Monitoring
programme for post-transplantation was conducted on 23
October 2024 once per month.
MONITORING RESULTS
4.3.8
The
weekly site audit was carried out by ET include checking whether good site
practices are being properly implemented by the Contractor.
4.3.9
The
extent of the work site boundaries was checked by the ET during the weekly site
audit.
4.3.10
Results
and findings of site audit in this reporting month are listed in Table
3.3.
4.4.1 The quantities of waste for disposal in the
Reporting Period are summarized in Table 4.7. The Monthly Summary Waste
Flow Table is shown in Appendix
4.5.
Table
4.7 Summary of Quantities of Waste
Material
|
Waste Type |
Quantity this month |
Quantity (the end of last month) |
Cumulative Quantity-to-Date |
|
Hard Rock and Large Broken Concrete (Inert) (in ‘000m3) |
0 |
0 |
0 |
|
Reused in this Contract (Inert) (in ‘000m3) |
0 |
0 |
0 |
|
Reused in other Projects (Inert) (in ‘000m3) |
0 |
0 |
0 |
|
Disposal as Public Fill (Inert) (in ‘000m3) |
0.38 |
1.53802 |
25.09089 |
|
Metals (in ‘000kg) |
0 |
0.00300 |
15.69570 |
|
Paper / Cardboard Packing (in ‘000kg) |
0 |
0.01100 |
0.83538 |
|
Plastics (in ‘000kg) |
0 |
0.00190 |
0.07496 |
|
Chemical Wastes (in ‘000kg) |
0 |
0 |
0 |
|
General Refuses (in ‘000kg) |
12.49 |
15.89000 |
683.21 |
|
Marine Sediment (Type 1 – Open Sea Disposal)
, m3 |
0 |
0 |
60.2 |
5.1.1
No environmental complaint was recorded in the reporting month.
5.1.2
No notification of summons and successful prosecution regarding
construction works were recorded in the reporting month.
5.1.3
Cumulative statistic on complaints, summary of complaints and successful
prosecutions are summarized in Table 5.1, Table 5.2
and Table
5.3 respectively.
Table
5.1 Cumulative Statistics on
Complaints
|
Reporting
Period |
No.
of Complaints |
|
October
2024 |
0 |
|
Project
commencement to the end of last reporting month |
3 |
|
Total |
3 |
Table
5.2 Summary of Complaints
|
Date
of Notification from EPD |
Date
of Complaint |
Description
of Complaint |
Validity
of Complaint |
Close-Out
Date / Status |
|
26 May 2022 |
22 May 2022 |
A complaint is regarding to noise
nuisance from marine site of San Shek Wan, Lantau Island. |
Based on the investigation, the works
activities of marine works did not result in any noise nuisance to Noise
Sensitive Receivers (NSRs), noise nuisance from the Project is unlikely to be
valid. |
The interim report was submitted to
EPD in June 2022. EPD replied no further comments on the final investigation
report on 13 July 2022. |
|
23 Dec 2022 |
21 Dec 2022 |
A complaint is regarding to the water quality for Pui O Beach, Lantau
Island. |
Based on the investigation, the works activities at POPS did not
result in any water quality impacts to the Pui O Beach. |
The interim report was submitted to EPD on 4 Jan 2023. |
|
16 Aug 2024 2024 |
15 Aug 2024 |
A complaint is regarding to the damaged silt curtain and potential
water quality impact. |
Based on the investigation, no marine works since Dec 2023 till
present, the land based works activities at POPS did not result in any water
quality impacts to the Pui O Wan. |
The interim report was submitted to EPD on 31 Aug 2024. |
Table 5.3 Cumulative
Statistics on Successful Prosecutions
|
Environmental
Parameters |
Cumulative
No. Brought Forward |
No.
of Successful Prosecutions this month (Offence Date) |
Cumulative
No. Project-to-Date |
|
Air |
- |
0 |
0 |
|
Noise |
- |
0 |
0 |
|
Water |
- |
0 |
0 |
|
Waste |
- |
0 |
0 |
|
Other |
- |
0 |
0 |
|
Total |
- |
0 |
0 |
6.1.1
In coming reporting 3 months, the scheduled construction activities are
listed as follows:
·
Excavation,
sewer laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau Road,
Chi Ma Wan Road
·
Dredging
at marine *
·
Site
formation works at SSWSTW
·
Trenchless
drilling works (Chi Ma Wan Road)
·
Excavation
works (at site area)
·
ELS works
at SSWSTW
·
Superstructure
RC Works at SSWSTW
·
Removal
works of ELS at POSPS
·
E&M
Installation at POSPS
*
Note: Further confirmed with the Contactor and ER, marine works has yet to
resume and no marine work were ongoing in October 2024. The impact marine water
quality monitoring was resumed from 7 October 2024.
6.1.2
The scheduled construction activities and the recommended mitigation
measures for the coming 3 months are listed in Table 6.1. The
major construction activities for the next 3 months are summarized in Three
Months Rolling Programme – November 2024 to January 2025 in Appendix
6.1.
Table 6.1 Construction
Activities and Recommended Mitigation Measures in Coming Reporting 3 Months
|
Key Construction Works |
Recommended Mitigation Measures |
|
·
Excavation,
sewer laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau
Road, Chi Ma Wan Road ·
Dredging
at marine* ·
Site
formation works ·
Drilling
works ·
Excavation
works ·
ELS
works ·
Superstructure
RC Works ·
Removal
works of ELS ·
E&M
Installation at POSPS |
·
Implementation of noise pollution control in accordance with
Construction Noise Mitigation Plan; ·
Dust control during dust generating works; ·
Silt curtain should be maintained in good
condition prior to and during dredging and related marine works; ·
Adopt surface drainage and sediment control facilities for sewage
installation in village and public roads; ·
Adopt temporary drainage and sediment control facilities on Site; ·
Vehicle wheel-washing and body washing facilities should be provided
at the site entrance; ·
Regular water spraying on excavation works for dust control; and ·
Proper waste handling, recycling and storage. |
7.1.1
No school examination was taken place at N17 – Bui O Public School in the
reporting period.
7.1.2
No
action or limit level exceedance was recorded in construction noise level in
this reporting period.
7.2.1
Marine-based construction works commenced on
19 April 2022, HDD casing works commenced on 30 May 2022.
7.2.2
According to the Contractor’s construction
programme and confirmed with Engineer Representative, there is no potential
marine work until further notice. As such, pursuant to Condition 3.1 of the
Environmental Permit No. EP-538/2017, proposal of temporary suspension of
impact marine water quality monitoring was submitted to EPD for approval on 12
July 2024. This proposal was reviewed and verified by the Independent
Environmental Checker (IEC) on 12 July 2024. The proposal was approved by EPD
on 27 August 2024, thus, impact marine water quality monitoring had been temporarily suspended
starting from 28 August 2024 until further notice. Once Contractor and Engineer
Representative confirm the actual date to resume marine work, ET will notify
EPD one month in advance, and ET will resume impact marine water quality
monitoring two weeks prior to the start of marine works.
7.2.3
According to the Contractor’s construction
programme and confirmed with Engineer Representative (Binnies), the marine
works will be commenced on 21 October 2024, ET notified EPD immediately on 17
September 2024 to resume the marine water quality monitoring two weeks prior to
commencement of marine works, WQM was resumed from 7 Oct 2024.
7.2.4
Further confirmed with the Contactor and ER, marine
works has yet to resume and no marine work were ongoing in October 2024.
7.2.5
In accordance with the action level and limit
level in Baseline Monitoring Report Rev. 9.2 agreed by EPD on 2 September 2022,
action level exceedances of Depth-averaged on suspended solids (SS) was
recorded at SR9, SR10 and SR12 from 07:56 to 08:12 during ebb tide on 12 Oct
2024. Action level exceedances of Depth-averaged on suspended solids (SS) was
recorded at SR5 and SR6 from 9:07 to 9:19 during flood tide as well as at SR10
and SR12 from 14:04 to 14:11 during ebb tide on 21 Oct 2024. Action level
exceedances of Depth-averaged on suspended solids (SS) was recorded at SR15
from 13:37 to 13:38 during flood tide on 23 Oct 2024. Limit level exceedances
of Depth-averaged on suspended solids (SS) was recorded at SR4 and SR15 from
09:20 to 09:30 during ebb tide on 28 Oct 2024. Action level exceedances of
Depth-averaged on suspended solids (SS) was recorded at SR5, SR6, SR9,SR10, and
SR12 from 09:38 to 10:24 during ebb tide as well as at SR4, SR5, SR6, SR9,SR10,
SR12and SR15 from 16:01 to 17:07 during flood tide on 28 Oct 2024. Action level
exceedances of Depth-averaged on suspended solids (SS) was recorded at SR10 and
SR12 during both ebb and flood tide from 11:25 to 11:32 and 16:32 to 16:38
respectively on 30 Oct 2024.
7.2.6
As the suspended solids (SS) result is
determined by laboratory analysis that require 7 working days, it is not
possible to increase the monitoring frequency to daily until no exceedance of
Action Level after 30 Oct 2024. If such exceedances continuous during marine
works commencement, ET will check with contractor the implementation of the
mitigation measures and daily WQM monitoring will be considered.
7.2.7
As no marine work were ongoing since Jan 2024,
no sign of pollution was observed during site inspection or marine water
samples collection, it is considered that the exceedance was not related to
Project works.
7.2.8
For the limit level exceedances of suspended
solid recorded on 28 Oct 2024, confirmed with our field technician, the
seawater was observed turbid during sampling. As no marine work was conducted
in Oct 2024 and no other evidence indicate that
the limit level exceedance was affected by the site activities, it can be
concluded that the limit level exceedances were possibly induced by other
factors such as natural variation or changes of water quality in the vicinity
of water quality monitoring station.
7.3.1
Transplanting of the trees of Aquilaris sinensis was completed on 26
April 2022. Maintenance works for trees in holding nursery have commenced.
7.3.2
As per latest version of PTP, four tree found
(1 no. of Aquilaria sinensis and 3
nos. of Gmelina chinensis) within the
site of SSWSTW which are considered to be the plant species with conservative
importance for temporarily transplanted to the nursery at Kam Tin and eventually
be transplanted to Pui O Pumping Station.
7.3.3
The weekly site audit was carried out by ET
include checking whether good site practices are being properly implemented by
the Contractor.
7.3.4
The extent of the work site boundaries was
checked by the ET during the weekly site audit.
7.3.5
Within
this reporting period, holding nursery visit for transplanted trees on 23 October 2024.
7.3.6
No non-compliance
was found during the site inspection while reminders on environmental measures
were recommended. Results and findings of these inspections in this reporting period
are listed below in Table 7.1.
Table
7.1 Summary of Ecological Impact Monitoring
|
Inspection Date |
Reminder and Recommendations |
Close-out Date / Status |
|
23 October 2024 |
No particular findings |
N/A
|
7.4.1
No environmental
non-compliance was recorded in the reporting month.
7.5.1
There
was no particular action taken since no non-compliance was recorded in the reporting
period.