CONTRACT NO: SD 15/2022
Outlying
Island Sewerage Stage 2 – South Lantau Sewage Works – Environmental Team Services (2023
– 2024) Under Environmental Permit no. EP-538/2017
Monthly Environmental Monitoring & Audit Report
August 2023
revision 2
|
|
CLIENTS: |
|
|
Drainage Services Department |
Lam Environmental Services Limited 19/F, Remex Centre, 42 Wong Chuk Hang Road, Hong Kong Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
|
|
|
Certified
by: |
|
|
_______________________________ Derek Lo Environmental
Team Leader |
|
|
DATE: |
|
|
14 September 2023 |
|
|
|
1.1.......... Scope
of the Report
1.2.......... Structure
of the Report
2.............. Basic project Information and Environmental Status
2.1.......... Basic
Project Information
2.2.......... Construction
Programme
2.3.......... Works
undertaken during the month
3............. Implementation
Status
3.2.......... Environmental
Mitigation Measures
3.3.......... Environmental
monitoring requirements and contractual requirements
3.4.......... Site
Inspection and Audit Reports
4............. Monitoring
Results
4.1.......... Noise
Monitoring
4.2.......... Water
Quality Monitoring
4.4.......... Waste
Management
5............. Complaints,
Notification of Summons and Prosecution
6............. Future
Key Issues
7.1.......... Noise Monitoring
7.2.......... Water Quality Monitoring
7.3.......... Ecological
Impact Monitoring
7.4.......... Review
of the Reasons for and the Implications of Non-compliance
7.5.......... Summary
of action taken in the event of and follow-up on non-compliance
lIST
OF TABLES
Table 3.1 Summary
of submission status under EP-538/2017
Table 3.3 Summary of Environmental
Inspections
Table 4.1 Noise Monitoring Equipment
Table 4.2 Noise Monitoring Station
Table 4.3 Water Quality Monitoring Equipment
Table 4.4 Marine Water Quality Stations for
Water Quality Monitoring
Table 4.5 Action and Limit Levels of Water
Quality
Table 4.6 Summary of Marine Water Quality
Exceedances
Table 4.7 Summary of Quantities of Waste
Material
Table 5.1 Cumulative Statistics on
Complaints
Table 5.2 Summary of Complaints
Table 5.3 Cumulative Statistics on
Successful Prosecutions
Table 6.1 Construction Activities and
Recommended Mitigation Measures in Coming Reporting 3 Months
lIST OF FIGUREs
Figure 2.2 Contract Layout Plan
Figure
2.3 Locations of Noise Monitoring
Station
Figure
2.4 Locations of Water Quality
Monitoring Stations
Figure
2.5 Mark up Figure 5.4i extracted from
approved EIA Report (AEIAR-210/2017)
Figure 2.6 Location Plan for Temporary Holding Nursery
lIST OF APPENDIces
Appendix 4.1 Copies of Calibration Certificates
Appendix
4.2 Impact Monitoring Schedule for
Reporting Month and Next Month
Appendix
4.3 Noise Monitoring Results and
Graphical Presentations
Appendix 4.4 Marine Water Quality Monitoring Results and
Graphical Presentations
Appendix
4.5 Monthly Summary Waste Flow Table
Appendix 6.1 3 Months Rolling Programme
EXECUTIVE SUMMARY
i.
This
is the Monthly Environmental Monitoring and Audit (EM&A) Report
– August
2023 for the Outlying Islands Sewerage Stage 2 – South Lantau
Sewerage Works under Environmental Permit No. EP-538/2017 (Hereafter as “the
Project”). The construction works of the
Project was commenced on 3 November 2021
and the tentative completion date is Q1 2026. This Monthly EM&A Report
presents the environmental monitoring findings and information recorded during
the period of 1 to 31 August 2023. The cut-off date of reporting is at the end of
each reporting month.
ii.
In
the reporting period, the principal work activities undertaken are as follows:
· Excavation, sewer laying, construction
of manhole at Pui O Lo Uk Tsuen, South Lantau road, Pui O Beach
· Excavation and site formation at San
Shek Wan Sewage Treatment Works (SSWSTW) and Pui O Sewage Pumping Station (POSPS)
· Horizontal Directional Drilling (HDD)
works at marine and
SSWSTW
· Removal works of
Excavation and Lateral Support (ELS)
· Excavation and
Lateral Support (ELS) works
· Superstructure Reinforced Concrete (RC)
Works
Exceedances of Action/Limit Levels
Noise Monitoring
iii.
Noise monitoring was conducted at eight (8)
noise monitoring stations (N12a, N12b,
N13, N14, N15b, N16a, N16b and N17) once per week in the reporting period.
iv.
No school examination was taken place at N17 – Bui O Public School in
the reporting period.
v.
No Action/Limit
Level exceedances were recorded in this reporting period.
Water Quality Monitoring
vi.
Water quality monitoring (WQM) had been commenced on 12 April 2022 the
designated monitoring stations three days per week with respect to marine-based
construction works commenced on 19 April 2022. HDD casing works commenced on 30
May 2022.
vii.
In accordance with the action level and limit level in Baseline
Monitoring Report Rev. 9.2 agreed by EPD on 2 September 2022, 1 action level at
SR4 and 0 limit level exceedances on SS was recorded in the reporting month. It
can be concluded that the SS exceedances were possibly due to natural runoff
from streams to the sea in the reporting month.
viii.
Action Level exceedances at SR4 was recorded on 9 August 2023 on SS
(details shown in Table 4.6) during flood tide. No Limit Level exceedances
recorded in the reporting month. Co-related the monitoring dates with those
days with recorded marine works activities, no marine dredging works were
active during the reporting month. No marine works during 17 July 2023 to 11
Aug 2023 due to the silt curtain was found broken after Typhoon No. 8 on 17
July 2023 and repaired on 12 August 2023. No exceedance was recorded on same
day during ebb tide from 07:13 to 07:16 and in the subsequent monitoring on 11
August 2023 both ebb and flood tide. Reviewed the overall work situation and
the mitigation measures was implemented by the Contractor, it can be concluded
that the SS exceedances at SR4 was possibly due to natural runoff from streams
to the sea or sudden changed of water body.
Ecological Impact Monitoring
ix.
Transplanting of the trees of Aquilaris sinensis was completed on 26 April 2022. Maintenance works for trees in holding
nursery have commenced.
x.
As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of
SSWSTW which are considered to be the plant species with conservative
importance for temporarily transplanted to the nursery at Kam Tin and
eventually be transplanted to Pui O Pumping Station.
xi.
The weekly site audit was carried out by ET include checking whether
good site practices are being properly implemented by the Contractor.
xii.
The extent of the work site boundaries was checked by the ET during the
weekly site audit.
Complaint log
xiii.
No environmental complaint regarding the construction
works was recorded in the reporting period.
Notifications
of Any Summons and Successful Prosecutions
xiv.
No environmental notification of any summons and
successful prosecution regarding the construction works was recorded in the
reporting period.
Reporting
Changes
xv.
There are no particular reporting changes.
Future
Key Issues
xvi.
In coming reporting 3 months, the scheduled construction activities are
listed as follows:
·
Excavation,
sewer laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau Road, Pui O Beach
·
HDD works
at marine and SSWSTW
·
Site
formation works
·
Drilling
works
·
Excavation
works
·
ELS works
·
Superstructure
RC Works
·
Removal works of
ELS
xvii.
Key
construction activities for the next three months with the recommended
mitigation measures to be implemented are presented as follows:
|
Key Construction Works |
Recommended Mitigation Measures |
|
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen,
South Lantau
Road, Pui O Beach ·
HDD works at marine and SSWSTW ·
Site formation works ·
Drilling works ·
Excavation works ·
ELS works ·
Superstructure RC Works ·
Removal works of ELS |
·
Implementation of noise pollution control in accordance with
Construction Noise Mitigation Plan; ·
Dust control during dust generating works; ·
Silt curtain should be maintained in good condition; ·
Adopt surface drainage and sediment control facilities for sewage
installation in village and public roads; ·
Adopt temporary drainage and sediment control facilities on Site; ·
Vehicle wheel-washing and body washing facilities should be provided
at the site entrance; ·
Regular water spraying on excavation works for dust control; and ·
Proper waste handling, recycling and storage. |
1.1.1.
Lam Environmental Services Limited (LES) has been appointed to work as
the Environmental Team (ET) under Environmental Permit (EP) No. EP-538/2017 to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for the Outlying Islands Sewerage Stage 2 – South
Lantau Sewerage Works (Register No.: AEIAR-210/2017).
1.1.2.
In accordance with Clause 3.4 stated in EP-538/2017, 4 hard copies and 1
electronic copy of Monthly EM&A Report shall be submitted to the Director
within 2 weeks after the end of each reporting month.
1.1.3.
According to Section 12.2 of the Project EM&A Manual, the Monthly
EM&A Report should be submitted within 10 working days of the end of each
reporting month, with the first report due in the month after construction
commences.
Section 1 Introduction – details the scope and structure of the report.
Section 2 Basic
project Information and Environmental Status – summarizes project organization and key personnel contact,
construction programme and works undertaken for the month. Construction
programme, works undertaken during the month with illustrations, drawing
showing the project area, environmental sensitive receivers and monitoring
locations.
Section 3 Implementation
Status – advice on the implementation
status of environmental protection and pollution control/mitigation measures,
as recommended in the EIA Report and summarised in the updated implementation
schedule.
Section 4 Monitoring
Results – summarizes the monitoring
results obtained in the reporting period, including monitoring methodology, name
of laboratory and equipment used and calibration details, parameters monitored,
monitoring locations (and depth), monitoring date, frequency, and duration.
Section 5 Report
on Complaints,
Notification of Summons and Successful Prosecutions – summarizes:
Record of all complaints received (written or
verbal) for each media, including locations and nature of complaints
investigation, liaison and consultation undertaken, actions and follow-up
procedures taken, results and summary;
Record of notifications of summons and
successful prosecutions for breaches of the current environmental
protection/pollution control legislations, including locations and nature of
the breaches, investigation, follow-up actions taken, results and summary;
Review of the reasons for and the implications
of non-compliance, complaints, summons and prosecutions including review of
pollution sources and working procedures; and
Description of the actions taken in the event
of non-compliance and deficiency reporting and any follow-up procedures related
to non-compliance.
Section 6 Future Key Issues – An account of the future key issues as reviewed from
the works programme and work method statements.
Section 7 Conclusion
2.1.1. Drainage Services Department is the
overall project controllers for the Project. For the construction phase of the Project,
Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage
and control environmental issues. Key personnel and contact particulars are
summarized in Table 2.1:
Table
2.1 Contact Details of Key Personnel
|
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
|
Drainage
Services Department (DSD) |
The Engineer for the Contract |
Engineer |
Mr. Silas Chan |
2594 7272 |
3104 6426 |
|
Binnies
Hong Kong Limited |
Engineer’s
Representative |
Resident Engineer |
Mr. Kevin Chan |
3529 3013 |
- |
|
Kwan
Lee – Chun Wo Joint Venture |
Contractor
|
Site
Agent |
Mr. Charles Tse |
9270 3384 |
2744 6937 |
|
Environmental
Officer |
Ms. Shirley Kong |
5162 5933 |
|||
|
SMEC Hong Kong |
Independent Environmental
Checker (IEC) |
Independent Environmental Checker (IEC) |
Ms. Kitty Lee |
3995 8140 |
3995 8101 |
|
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Derek Lo |
2882 3939 |
2882 3331 |
2.2.1.
The proposed sewerage works will collect the sewage generated from
the unsewered areas of Shui Hau, Tong Fuk,
Cheung Sha, San Shek Wan, Pui O and Ham Tin in South
Lantau (i.e. within the Project Catchment Area) and convey it to a proposed
sewage treatment works at San Shek Wan for treatment and disposal
into outer bay of Pui O/ Chi Ma Wan via a submarine outfall.
2.2.2.
The entire Project are divided into three contracts. Contract No.
DC/2020/20 (the Contract) would have the following implementations as
demonstrated in Figure 2.1.
2.2.3.
The major components of the Contract under Environmental Permit (EP) (EP
No. EP-538/2017) comprises: (i) construction of secondary sewage treatment
works (STW) at San Shek Wan in South Lantau; (ii) construction of sewage
pumping station (SPS) at Pui O, San Shek Wan, Cheung Sha and Cheung Fu Street;
(iii) construction of about 1.4 kilometres (km) of submarine outfall with a
diameter of 350 millimetres (mm) for the disposal of treated effluent from the
STW at San Shek Wan; (iv) construction of about 10.1 km of gravity sewers with
diameters ranging from 150 mm to 375 mm along South Lantau Road and Chi Ma Wan
road and at Pui O; and (v) construction of about 3.1 km twin rising mains with
a diameter of 200 mm to 250 mm along South Lantau Road and Chi Ma Wan Road.
2.2.4.
The performance
of the environmental management system of the reporting period was generally
satisfied. Mitigation measures according to the environmental mitigation
implementation schedule and the EIA were generally implemented by the
Contractor. Hence, the EM&A programme was considered effective and shall be
maintained.
2.3.1.
In the reporting month, the principal work activities conducted are as
follow:
· Excavation, sewer laying, construction
of manhole at Pui O Lo Uk Tsuen, South Lantau road, Pui O Beach
· Excavation and site formation at San
Shek Wan Sewage Treatment Works (SSWSTW) and Pui O Sewage Pumping Station
(POSPS)
· Horizontal Directional Drilling (HDD)
works at marine and
SSWSTW
· Removal works of
Excavation and Lateral Support (ELS)
· Excavation and
Lateral Support (ELS) works
· Superstructure Reinforced Concrete (RC)
Works
The
locations of works are shown in Figure 2.2.
2.4.1.
Noise and water monitoring location plans with sensitive receivers are
shown in Figure 2.3 and Figure 2.4.
3.1.1. Mitigation measures according to
the environmental mitigation implementation schedule in Annex A of EM&A
Manual were generally implemented by the Contractor. Hence, the EM&A
programme was considered effective and shall be maintained.
3.2.1.
Environmental mitigation measures mentioned the EIA Report were weekly
reviewed and recorded in Weekly Environmental Site Audit Checklist. Also, a
summary of the current status on submissions and measures mentioned in
Environmental Permit (EP-538/2017) are shown in Table 3.1.
Table 3.1 Summary of submission status under EP-538/2017
|
EP Condition |
Submission |
Date of Latest Submission to EPD^ / EPD Approval# |
|
Condition 2.10 |
Waste Management Plan (Rev. 5) (electronic copy) |
4 April 2022# |
|
Condition 2.11 |
Submission of Preservation and/or Transplantation Plan for Plant
Species of Conservation Importance (Rev. 23) |
9 September 2022# |
|
Condition 2.12 |
Submission of Compensatory Woodland Planting Plan (Rev. 23) |
15 May 2023^ |
|
Condition 2.13 |
Silt Curtain Deployment Plan (Rev. 11) |
1 June 2022# |
|
Condition 2.14 |
Landscape Mitigation Plan |
To be confirmed |
|
Condition 2.15 |
Construction Noise Mitigation Plan (Rev. 20) |
4 August 2022# |
3.3.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.2.
Table 3.2 Summary of the current status on licences
and/or permits on environmental protection pertinent to the Project
|
Permits and/or Licences |
Permit. No. / Account No. |
Issued Date |
Valid Period & Expiry Date |
Status |
|
Notification
of Works Under APCO |
466408 |
14 Apr
2021 |
N/A |
Valid |
|
Wastewater Discharge Licence under Water Pollution Control Ordinance |
SSWSTW: WT00039636-2021 |
30 Dec
2021 |
30-12-2021
to 31-12-2026 |
Valid |
|
POPS: WT00039820-2021 |
31 Dec
2021 |
31-12-2021
to 31-12-2026 |
Valid |
|
|
SSWSTW:
Gravity Sewer & Raising Main: WT00042613-2022 |
09 Jan
2023 |
09-01-2023
to 31-01-2028 |
Valid |
|
|
Billing
account under Waste Disposal Ordinance |
Account
No.: 7040411 |
05 May
2021 |
N/A |
Valid |
|
Registration
as a Chemical Waste Producer |
0000-931-K3428-01 |
13 May
2021 |
N/A |
Valid |
|
Construction
Noise Permit under Noise Control Ordinance for SSWSTW |
GW-RS0039-23 |
20 Jan 2023 |
03-02-2023 to 02-08-2023 |
Invalid after 3 Aug 2023 |
|
GW-RS0657-23 |
9Aug 2023 |
11-08-2023 to 08-02-2024 |
Valid |
|
|
Construction
Noise Permit under Noise Control Ordinance for POSPS |
GW-RS0230-23 |
7 Mar 2023 |
27-03-2023 to 26-09-2023 |
Valid |
Note: Only include those valid
or under application; fill in “N/A” for non-applicable item(s).
3.4.1.
Within this reporting month, weekly environmental site inspections were
conducted on 01, 08, 15, 21 and 29 August 2023. IEC attended the SSEMC meeting
held on 21 August 2023. Holding nursery visit for
transplanted trees on 24 August 2023.
3.4.2. No non-compliance was found during the site inspection while reminders on
environmental measures were recommended. Results and
findings of these inspections in this reporting month are listed below in Table
3.3.
Table 3.3 Summary
of Environmental Inspections
|
Inspection Date |
Reminder and Recommendations |
Close-out Date / Status |
|
1 August
2023 |
No
particular findings |
NA |
|
8 August 2023 |
General reminder– 1.
Contractor is reminded to
segregating and sorting different types of waste into different recycle bins. |
Rectified on 8 Aug 2023 |
|
15 August
2023 |
No particular findings |
NA |
|
21 August
2023 |
Pui O Sewage Pumping Station- 1. Waste water tank was found overflow, contractor is required to
proper treat the waste water prior to discharge. 2. Drip tray should be provided to chemical container. |
Rectified on 25 Aug 2023 |
|
29 August
2023 |
Pui O Sewage Pumping Station- 1. Drip tray should be provided to chemical container. Village sewers works (Lo Uk Tsuen) – 2. Muddy trail on public area should be cleaned up regularly. |
Rectified on 30 Aug 2023 |
Note:
previous finding during site inspection on 25 July 2023 was rectified on 1 Aug
2023
4.1.1
Monitoring
Procedure
(a)
The impact noise monitoring should be
carried out at all the designated monitoring stations when there are
project-related construction activities undertaken within a radius of 300m from
the monitoring stations.
(b)
The monitoring station shall normally
be at a point 1m from the exterior of the sensitive receiver’s building façade
and be at a position 1.2m above the ground.
(c)
Façade measurements were made at the
monitoring locations. For free-field measurement, a correction factor of +3 dB (A)
would be applied.
(d)
The battery condition was checked to
ensure the correct functioning of the meter.
(e)
Parameters such as frequency weighting,
the time weighting and the measurement time were set as follows:
(f)
Frequency weighting: A, Time weighting:
Fast, Measurement time set: continuous 5 mins
(g)
Prior and after to the noise
measurement, the meter was checked using the acoustic calibrator for 94dB (A)
at 1000 Hz. If the difference in the calibration level before and after
measurement was more than ±1.0 dB (A), the measurement would be considered
invalid and repeat of noise measurement would be required after re-calibration
or repair of the equipment.
(h)
Noise measurements will be made in
accordance with standard acoustical principles and shall not be made in fog,
rain, wind with a steady speed exceeding 5m/s or wind with gusts exceeding
10m/s. The wind speed shall be checked with a portable wind speed meter capable
of measuring the wind speed in m/s.
name of laboratory and
equipment used and calibration details
4.1.2
Noise monitoring was performed
using sound level meter at the designated monitoring locations. The sound level
meters shall comply with the International Electrotechnical Commission
Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications. Acoustic
calibrator shall be deployed to check the sound level meters at a known sound
pressure level. Brand and model of the equipment is given in Table
4.1.
Table 4.1 Noise Monitoring Equipment
|
0005062 |
||
|
Larson Davis CAL200 |
13437 |
4.1.3 The calibration certificates of the noise monitoring equipment are attached in Appendix 4.1.
4.1.4
Calibration Details
(a)
The microphone head of the sound level
meter was cleaned with soft cloth at regular intervals.
(b)
The sound level meter and calibrator
were calibrated at yearly intervals.
Parameters monitored
4.1.5
The
construction noise level shall be measured in terms of the A-weighted
equivalent continuous sound pressure level (Leq). Leq(30min)
should be used as the monitoring parameter. Supplementary information for data auditing, statistical results
such as L10 and L90 shall also be obtained for reference.
4.1.6
For
impact monitoring for construction of village sewers / rising main,
noise monitoring should be undertaken on weekly basis. One set of Leq(30min)
noise level as six consecutive Leq(5min) between 07:00-19:00 hours
on normal weekdays.
Monitoring Stations
4.1.7
The
noise monitoring stations for the Project are listed and shown in Table 4.2,
impact noise monitoring was conducted at Eight (8) noise monitoring stations N12a, N12b, N13, N14, N15b,
N16a, N16b and N17 once per week in the reporting month.
Table 4.2 Noise
Monitoring Station
|
Monitoring
Station ID (1) |
Monitoring
Location |
Measurement
Type |
Level (in terms
of no.
of floor) |
|
N01a |
Shui Hau Village |
Free-Field |
G/F |
|
N01c |
Shui Hau Village |
Free-Field |
G/F |
|
N03a |
Tong Fuk Village |
Free-Field |
G/F |
|
N05a |
Residences at Cheung Fu Street |
Free-Field |
G/F |
|
N07 |
Government Holiday Bungalows |
Free-Field |
G/F |
|
N08 |
Cheung Sha Ha Tsuen |
Free-Field |
G/F |
|
N10 |
Cheung Sha Sheung Tsuen |
Façade |
G/F |
|
N11b |
San Shek Wan – Ming Garden |
Free-Field |
G/F |
|
N12a |
Lo Uk Tsuen |
Free-Field |
G/F |
|
N12b |
Lo Uk Tsuen |
Façade |
G/F |
|
N13 |
Pui O San Wai Tsuen |
Façade |
G/F |
|
N14 |
South Lantau Community Centre |
Free-Field |
G/F |
|
N15b |
Pui O Lo Wai Tsuen |
Façade |
G/F |
|
N16a |
Residences at Ham Tin |
Free-Field |
G/F |
|
N16b |
Residences at Ham Tin |
Free-Field |
G/F |
|
N17 |
Bui O Public School |
Façade |
R/F |
Remarks (1): Fine
adjustment of noise monitoring stations at all locations was proposed as per EP
Condition 3.1.
Monitoring date, time,
Frequency and Duration
4.1.8
For
daytime construction work on normal weekdays, monitoring of Leq(30min)
should be carried out at each station at 0700-1900 hours on normal weekdays at
a frequency of once a week. Impact
monitoring schedule can be referred to Appendix
4.2.
Noise Monitoring Results
4.1.9
Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring results and graphical presentation can
be referred in Appendix 4.3.
4.1.10 No school examination was taken place at
N17 – Bui O Public School in the reporting period.
4.1.11
No action or limit level exceedance was recorded in construction
noise level in this reporting period.
Monitoring Methodology
4.2.1
Monitoring
Procedure
(a)
The condition near the monitoring
stations shall be observed and recorded on the data log sheet.
(b)
Check of sensors and electrodes with
certified standard solutions before each use.
(c)
Wet bulb calibration for a DO meter
should be carried out before measurement.
(d)
Water depth should be recorded by
detector before sampling.
(e)
Sample would be taken using bucket
sampler at surface level.
(f)
Transfer the sampled water carefully
into cleaned water bottles (2x 1000ml) provided by the laboratory at the spot
after the collection of the water sample for the subsequent laboratory
Suspended Solid testing.
(g)
Transfer the sampled water from the
bucket sampler to the rinsed water container for in-situ measurement (In case
of the in-situ measurement cannot be carried at spot due to safety and adverse
weather condition, sampled water from the bucket sampler will be transfer to
cleaned water bottles provided by laboratory. Then, In-situ measurement will be
conducted at a safe location which sampled water inside cleaned water bottle
will be transfer to the rinsed water container for in-situ measurement) In-situ
measurement shall be measured in duplicate.
(h)
Parameters including Water Temperature
(°C), pH (units), Salinity (ppt), DO (mg/L), DO saturation (%) will be
measured by the Multifunctional Meter and Turbidity (NTU) will be measured by turbid
meter. (Water Temperature and Salinity will be measured as reference
parameters)
(i)
Record the result on the data log sheet
and record any special finding during / after in-situ measurement.
(j)
The water sample bottles will be stored
in a cool box (at cooled to 4°C without
being frozen), which shall be delivered to HOKLAS laboratory (ALS Technichem
(HK) Pty Ltd) for further testing to determine the level of SS.
Name of laboratory and
equipment used and calibration details
Laboratory Measurement /
Analysis
4.2.2
Analysis
of suspended solids will be carried out in a HOKLAS accredited laboratory,
which is ALS Technichem (HK) Pty Ltd.
equipment used
Dissolved Oxygen, pH And Temperature Measuring
Equipment
4.2.3
Multifunctional
Meter and Turbid Meter are used at each designated monitoring station. They are
capable of measuring:
(a)
a dissolved oxygen level in the range
of 0-20mg/L and 0-200% saturation (Detection Limit: 0.1mg/L)
(b)
a temperature of 0-45 degree Celsius (Detection Limit: 0.1 degree Celsius)
(c)
turbidity level between 0-1000NTU (Detection
Limit: 0.1NTU)
(d)
salinity in the range of 0-40ppt (Detection
Limit: 0.1ppt)
(e)
pH value in range of 0.0 – 14.0
(Detection Limit: 0.1units)
Other monitoring equipment namely water depth meter, water current
meter, dGPS positioning device, water sampler listed below were also deployed,
(a)
Water depth meter (Range: 0.6 -100m, Resolution: 0.1m)
(b)
Water current meter (Range: 0-360o, Detection
Limit: 1mm/s)
(c)
dGPS positioning device (Resolution: Horizontal: 0.25m; Vertical:
0.50 m )
(d)
Water sampler (Horizontal discrete type, Capacity: 2.2L)
Sampler Container and Storage
4.2.4
A
water sampler, Water samples for suspended solids measurement should be
collected in high-density polythene bottles, packed in ice (cooled to 4°C
without being frozen), and delivered to ALS Technichem (HK) Pty Ltd. as soon as
possible after collection for analysis.
Water Depth Detector
4.2.5
A
portable, battery-operated echo sounder shall be used for the determination of
water depth at each designated monitoring station. This unit can either be
handheld or affixed to the bottom of the workboat, if the same vessel is to be
used throughout the monitoring programme.
calibration details
4.2.6
Maintenance
and Calibration
(a)
The responses of sensors and electrodes
of the water quality monitoring equipment were cleaned and checked at regular
intervals.
(b)
DO meter (Multifunctional Meter) and
turbid meter was certified by a laboratory accredited under HOKLAS or any other
international accreditation scheme, and subsequently re-calibrated at three
monthly intervals.
4.2.7
Brand and model of the
equipment are given in Table 4.3.
Table
4.3 Water Quality Monitoring Equipment
|
Equipment |
Brand and
model |
Series
Number |
|
Multifunctional Meter |
Sonde YSI Professional Plus |
14E100105/17G100383 |
|
Turbid meter |
Xin Rui WGZ-3B |
1807073 |
Calibration certificates of the water
quality monitoring equipment are attached in Appendix 4.1.
Parameters monitored
4.2.8
In
construction phase, the levels of dissolved oxygen (DO), temperature, turbidity
and salinity should be measured in situ while suspended solids (SS) is
determined by laboratory analysis.
MONITORING STATIONS
4.2.9
Water quality monitoring involves
9 monitoring stations. The locations of water quality monitoring station are
shown in Table 4.4.
Table 4.4 Marine
Water Quality Stations for Water Quality Monitoring
|
Station |
Description |
Easting |
Northing |
|
CE |
Upstream
control station at ebb tide |
810838 |
807538 |
|
CF |
Upstream
control station at flood tide |
815886 |
808081 |
|
SR4 (1) |
Ecological
Sensitive Receiver (Coral Communities) at Pui O Wan |
814938 |
810975 |
|
SR5 |
Ecological
Sensitive Receiver (Coral Communities) at Pui O Wan |
814326 |
810540 |
|
SR6 |
Gazetted Bathing Beach at Lower Cheung Sha |
810553 |
810475 |
|
SR9 (1) |
Ecological Important Stream
at Tong Fuk |
811325 |
809787 |
|
SR10 |
Secondary Contact
Recreational Zones at South Lantau |
810561 |
809494 |
|
SR12 (1) |
Proposed Special Site of
Scientific Interest (SSSI) at Shui Hau Wan |
810359 |
808989 |
|
SR15 |
Gazetted Bathing Beach at Pui O and Ecologically Important Stream at Pui O |
816037 |
810722 |
Remarks (1): Fine adjustment of water
quality monitoring stations at SR4, SR9 and SR12 was proposed as per EP
Condition 3.1, and baseline monitoring was conducted at corresponding fine
adjusted locations.
Monitoring date, time,
Frequency and Duration
4.2.10 Water quality monitoring had been
commenced on 12 April 2022 the designated monitoring stations three days per
week with respect to marine-based construction works commenced on 19 April
2022. HDD casing works commenced on 30 May 2022.
4.2.11 To support water quality monitoring, the
silt curtain deployment plan has minor updates to include an additional brand
of geosynthetic material as alternative for selection and adopt underwater
robot for inspecting condition of silt curtain.
4.2.12
The
levels of dissolved oxygen (DO), temperature, turbidity and salinity were
measured in situ while suspended solids (SS) is determined by laboratory
analysis at all the monitoring stations in Table 4.4 three times a week. Impact
monitoring schedule can be referred to Appendix
4.2.
4.2.13
In
association with the water quality parameters, other relevant data shall also
be recorded, such as monitoring location / position, time, water temperature,
DO saturation, weather conditions, and any special phenomena underway near the
monitoring station.
4.2.14
Impact
Monitoring shall be carried out three days per week, at mid-flood and mid-ebb
tides (within ± 1.75 hour of the predicted time). The interval between two sets
of monitoring shall not be less than 36 hours. The monitoring period should
avoid concurrent marine project in the vicinity.
4.2.15
The
sampling frequency of at least three days per week should be undertaken. Upon
completion of the construction works, the monitoring exercise at the designated
monitoring locations should be continued for four weeks in the same manner as
the impact monitoring. In case exceedance of Action/Limit Level is recorded,
the frequency shall be increased as per the Event and Action Plan.
4.2.16
To
ensure the robustness of in-situ measurement, parameters shall be measured in
duplicate. In case the difference between duplicates is larger than 25%, a
third set of measurement shall be carried out.
Monitoring Results
4.2.17
Marine
water quality monitoring results measured in this reporting period are reviewed
and summarized. Details of marine water quality monitoring results and
graphical presentation can be referred in Appendix 4.4
4.2.18
Water quality monitoring is evaluated against Action and Limit Levels. The
derived Action and Limit Level proposed in Baseline Monitoring Report Rev. 9.2
was agreed by EPD on 2 September 2022. Action and Limit Levels of marine water
quality monitoring have been set with reference to the derived criteria as
shown in Table 4.5 below for reference.
Table
4.5 Action and Limit Levels of Water
Quality
|
Parameters |
Action Level |
Limit Level |
|
Construction
Phase Marine Water Monitoring - derived criteria |
||
|
DO in mg/L
B |
Surface and Middle: 5.8 mg/L Bottom: 5.9 mg/L |
Surface and Middle: 4 mg/L Bottom: 2 mg/L |
|
Turbidity
in NTU (Depth-averaged A) C |
14.4 NTU and 20% exceedance of value at any impact station compared with
corresponding data from control station D |
23.5 NTU and 30% exceedance of value at any impact station compared with
corresponding data from control station D |
|
SS in mg/L (Depth-averaged
A) C |
13.1 mg/L and 20% exceedance of value at any impact station compared with
corresponding data from control station D |
30.4 mg/L and 30% exceedance of value at any impact station compared with corresponding
data from control station D |
Notes (with proposed amendments in AL/LL in underlined
text):
A. “Depth-averaged” is calculated by taking
the arithmetic means of reading of all three depths.
B. For DO, non-compliance of the water
quality limits occurs when monitoring result is lower than the limits.
C. For SS and turbidity, non-compliance of
the water quality limits occurs when monitoring result is higher than the
limits.
D. Action Level and Limit Level with 95%-ile /
99%-ile derived from baseline data “and” 20% / 30% exceedance of control
station proposed in Baseline Monitoring Report.
4.2.19
Number
of exceedances recorded during the reporting month are summarized in Table
4.6.
Table
4.6 Summary of Marine Water Quality
Exceedances
|
|
Parameter |
DO (S&M) |
DO (Bottom) |
Turbidity |
SS |
Exceedance count |
|||||
|
Station |
Level exceeded |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
|
SR4 |
Action |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
9/8/2023 |
0 |
1 |
|
|
Limit |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
SR5 |
Action |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
|
Limit |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
SR6 |
Action |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
|
Limit |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
SR9 |
Action |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
|
Limit |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
SR10 |
Action |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
|
Limit |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
SR12 |
Action |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
|
Limit |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
SR15 |
Action |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
|
Limit |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
0 |
0 |
|
Total |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
|
|
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
4.2.20 In accordance with the action level and
limit level in Baseline Monitoring Report Rev. 9.2 agreed by EPD on 2 September
2022, 1 action level at SR4 and 0 limit level exceedances on SS was recorded in
the reporting month. It can be concluded that the SS exceedances were possibly
due to natural runoff from streams to the sea in the reporting month.
4.2.21 Checked with contractor and RSS on the
marine works activities in the reporting month, the following activities were
recorded:
·
2, 4, 7, 9, 11 and 14 Aug 2023: No activity
·
16, 18 and 21 Aug 2023: Pilot hole reaming works
·
23 and 25 Aug 2023: Tripping out works for marine HDD2 works
·
28 and 30 Aug 2023: Smoothing for marine HDD2 works
4.2.22 Action Level exceedances at SR4 was
recorded on 9 August 2023 on SS (details shown in Table 4.6) during flood
tide. No Limit Level exceedances recorded in the reporting month. Co-related
the monitoring dates with those days with recorded marine works activities, no
marine dredging works were active during the reporting month. No marine works during
17 July 2023 to 11 Aug 2023 due to the silt curtain was found broken after
Typhoon No. 8 on 17 July 2023 and repaired on 12 August 2023. No exceedance was
recorded on same day during ebb tide from 07:13 to 07:16 and in the subsequent
monitoring on 11 August 2023 both ebb and flood tide. Reviewed the overall work
situation and the mitigation measures was implemented by the Contractor, it can
be concluded that the SS exceedances at SR4 was possibly due to natural runoff
from streams to the sea or sudden changed of water body.
MONITORING METHODOLOGY
4.3.1
The
weekly site audit to be carried out by the ET should include checking whether
good site practices are being properly implemented by the Contractor.
4.3.2
Impact
monitoring of the transplanted Aquilaris sinensis at holding nursery and one retain tree of Aquilaris sinensis in SSWSTW Project
Site, establishment and after-establishment caring measures of the compensatory
mixed woodland to ensure the affected tree would not be affected by any
unacceptable construction works. The trees would be treated with establishment
works immediately after transplanting.
PARAMETERS MONITORED
4.3.3
The
extent of the work site boundaries should be checked by the ET during the
weekly site audit. Any disturbance by
the Contractor outside the works area especially any damage to the vegetation
and surrounding habitats outside the Project area shall be reported to ER and
IEC.
4.3.4
To
identify any unacceptable construction works for the trees of Aquilaris sinensis during transplanting,
establishment and after-establishment caring measures of the compensatory mixed
woodland.
MONITORING LOCATION
4.3.5
As
per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of SSWSTW (Figure
2.5) which are considered to be the plant species with
conservative importance for temporarily transplanted to the nursery (Figure
2.6) at Kam Tin and eventually be transplanted to Pui O
Pumping Station.
MONITORING DATE, TIME,
FREQUENCY AND DURATION
4.3.6
The
recommended good site practices to be audited once every week as part of the
site audit programme. The weekly site audit to be carried out by the ET
includes checking whether good site practices are being properly implemented by
the Contractor. Results are recorded in Weekly Environmental Site Audit
Checklist.
4.3.7
Monitoring
programme for post-transplantation will be conducted once per month (21 July 2023).
MONITORING RESULTS
4.3.8
The
weekly site audit was carried out by ET include checking whether good site
practices are being properly implemented by the Contractor.
4.3.9
The
extent of the work site boundaries was checked by the ET during the weekly site
audit.
4.3.10
Results
and findings of site audit in this reporting month are listed in Table
3.3.
4.4.1 The quantities of waste for disposal in the
Reporting Period are summarized in Table 4.7. The Monthly Summary Waste
Flow Table is shown in Appendix
4.5.
Table
4.7 Summary of Quantities of Waste
Material
|
Waste Type |
Quantity this month |
Quantity (the end of last month) |
Cumulative Quantity-to-Date |
|
Hard Rock and Large Broken Concrete (Inert) (in ‘000m3) |
0 |
0 |
0 |
|
Reused in this Contract (Inert) (in ‘000m3) |
0 |
0 |
0 |
|
Reused in other Projects (Inert) (in ‘000m3) |
0 |
0 |
0 |
|
Disposal as Public Fill (Inert) (in ‘000m3) |
1.30758 |
1.66675 |
13.10725 |
|
Metals (in ‘000kg) |
0.0043 |
0.0040 |
7.51480 |
|
Paper / Cardboard Packing (in ‘000kg) |
0.0227 |
0.0390 |
0.41948 |
|
Plastics (in ‘000kg) |
0.0092 |
0.0037 |
0.04786 |
|
Chemical Wastes (in ‘000kg) |
0 |
0 |
0 |
|
General Refuses (in ‘000kg) |
5.85 |
9.35 |
512.41 |
5.1.1
No environmental complaint was recorded in the reporting month.
5.1.2
No notification of summons and successful prosecution regarding
construction works were recorded in the reporting month.
5.1.3
Cumulative statistic on complaints, summary of complaints and successful
prosecutions are summarized in Table 5.1, Table 5.2
and Table
5.3 respectively.
Table
5.1 Cumulative Statistics on
Complaints
|
Reporting
Period |
No.
of Complaints |
|
August
2023 |
0 |
|
Project
commencement to the end of last reporting month |
2 |
|
Total |
2 |
Table
5.2 Summary of Complaints
|
Date
of Notification from EPD |
Date
of Complaint |
Description
of Complaint |
Validity
of Complaint |
Close-Out
Date / Status |
|
26 May 2022 |
22 May 2022 |
A complaint is regarding noise
nuisance from marine site of San Shek Wan, Lantau Island. |
Based on the investigation, the works
activities of marine works did not result in any noise nuisance to Noise
Sensitive Receivers (NSRs), noise nuisance from the Project is unlikely to be
valid. |
The interim report was submitted to
EPD in June 2022. EPD replied no further comments on the final investigation
report on 13 July 2022. |
|
23 Dec 2022 |
21 Dec 2022 |
A complaint is regarding to the water quality for Pui O Beach, Lantau
Island. |
Based on the investigation, the works activities at POPS did not
result in any water quality impacts to the Pui O Beach. |
The interim report was submitted to EPD on 4 Jan 2023. |
Table 5.3 Cumulative
Statistics on Successful Prosecutions
|
Environmental
Parameters |
Cumulative
No. Brought Forward |
No.
of Successful Prosecutions this month (Offence Date) |
Cumulative
No. Project-to-Date |
|
Air |
- |
0 |
0 |
|
Noise |
- |
0 |
0 |
|
Water |
- |
0 |
0 |
|
Waste |
- |
0 |
0 |
|
Other |
- |
0 |
0 |
|
Total |
- |
0 |
0 |
6.1.1
In coming reporting 3 months, the scheduled construction activities are
listed as follows:
·
Excavation,
sewer laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau Road, Pui O Beach
·
HDD works
at marine and SSWSTW
·
Site
formation works
·
Drilling
works
·
Excavation
works
·
ELS works
·
Superstructure
RC Works
·
Removal works of
ELS
6.1.2
The scheduled construction activities and the recommended mitigation
measures for the coming 3 months are listed in Table 6.1. The
major construction activities for the next 3 months are summarized in Three
Months Rolling Programme - September 2023 to November 2023 in Appendix
6.1.
Table 6.1 Construction
Activities and Recommended Mitigation Measures in Coming Reporting 3 Months
|
Key Construction Works |
Recommended Mitigation Measures |
|
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen,
South Lantau
Road, Pui O Beach ·
HDD works at marine and SSWSTW ·
Site formation works ·
Drilling works ·
Excavation works ·
ELS works ·
Superstructure RC Works ·
Removal works of ELS |
·
Implementation of noise pollution control in accordance with
Construction Noise Mitigation Plan; ·
Dust control during dust generating works; ·
Silt curtain should be maintained in good condition; ·
Adopt surface drainage and sediment control facilities for sewage
installation in village and public roads; ·
Adopt temporary drainage and sediment control facilities on Site; ·
Vehicle wheel-washing and body washing facilities should be provided
at the site entrance; ·
Regular water spraying on excavation works for dust control; and ·
Proper waste handling, recycling and storage. |
7.1.1
No school examination was taken place at N17 –
Bui O Public School in the reporting period.
7.1.2
No
action or limit level exceedance was recorded in construction noise level in
this reporting period.
7.2.1
Marine-based construction works commenced on
19 April 2022, HDD casing works commenced on 30 May 2022.
7.2.2
In accordance with the action level and limit
level in Baseline Monitoring Report Rev. 9.2 agreed by EPD on 2 September 2022,
1 action level at SR4 and 0 limit level exceedances on SS was recorded in the
reporting month. It can be concluded that the SS exceedances were possibly due
to natural runoff from streams to the sea in the reporting month.
7.2.3
Action Level exceedances at SR4 was recorded
on 9 August 2023 on SS (details shown in Table
4.6) during flood tide. No Limit Level exceedances recorded in the
reporting month. Co-related the monitoring dates with those days with recorded
marine works activities, no marine dredging works were active during the
reporting month. No marine works during 17 July 2023 to 11 Aug 2023 due to the
silt curtain was found broken after Typhoon No. 8 on 17 July 2023 and repaired
on 12 August 2023. No exceedance was recorded on same day during ebb tide from
07:13 to 07:16 and in the subsequent monitoring on 11 August 2023 both ebb and
flood tide. Reviewed the overall work situation and the mitigation measures was
implemented by the Contractor, it can be concluded that the SS exceedances at
SR4 was possibly due to natural runoff from streams to the sea or sudden
changed of water body.
7.3.1
Transplanting of the trees of Aquilaris sinensis was completed on 26
April 2022. Maintenance works for trees in holding nursery have commenced.
7.3.2
As per latest version of PTP, four tree found
(1 no. of Aquilaria sinensis and 3
nos. of Gmelina chinensis) within the
site of SSWSTW which are considered to be the plant species with conservative
importance for temporarily transplanted to the nursery at Kam Tin and
eventually be transplanted to Pui O Pumping Station.
7.3.3
The weekly site audit was carried out by ET
include checking whether good site practices are being properly implemented by
the Contractor.
7.3.4
The extent of the work site boundaries was
checked by the ET during the weekly site audit.
7.3.5
Within
this reporting period, holding nursery visit for transplanted trees on 24 August 2023.
7.3.6
No non-compliance
was found during the site inspection while reminders on environmental measures
were recommended. Results and findings of these inspections in this reporting period
are listed below in Table 7.1.
Table 7.1 Summary
of Ecological
Impact Monitoring
|
Inspection Date |
Reminder and Recommendations |
Close-out Date / Status |
|
24
August 2023 |
Transplanted
trees in holding nursery at Kam Tin 1. The Contractor was reminded to avoid damage to the remaining trunk
when conducting pruning work (for T751). The Contractor was reminded to check with their arborist/ ecologist to review if the two batches of lichen in dark colour formed on the surface along the trunk of plant species of conservation importance, Aquilaria sinensis (T392), are insignificant to the plant species in terms of health. |
31
August 2023 |
7.4.1
No environmental
non-compliance was recorded in the reporting month.
7.5.1
There
was no particular action taken since no non-compliance was recorded in the reporting
period.