CONTRACT NO: SD 6/2020
Construction of San Shek Wan Sewage Treatment Works
Associated Submarine Outfall and Pui O Sewerage Works Under Environmental Permit no. EP-538/2017
Monthly Environmental Monitoring & Audit Report
August 2022
revision 3
|
|
CLIENTS: |
|
|
Drainage Services Department |
Lam Environmental Services Limited 19/F, Remex Centre, 42 Wong Chuk Hang Road, Hong Kong Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
|
|
|
Certified
by: |
|
|
_______________________________ Derek Lo Environmental
Team Leader |
|
|
DATE: |
|
|
14 September 2022 |
|
|
|
1.1.......... Scope
of the Report
1.2.......... Structure
of the Report
2.............. Basic project Information and Environmental Status
2.1.......... Basic
Project Information
2.2.......... Construction
Programme
2.3.......... Works
undertaken during the month
3............. Implementation
Status
3.2.......... Environmental
Mitigation Measures
3.3.......... Environmental
monitoring requirements and contractual requirements
3.4.......... Site
Inspection and Audit Reports
4............. Monitoring
Results
4.1.......... Noise
Monitoring
4.2.......... Water
Quality Monitoring
4.4.......... Waste
Management
5............. Complaints,
Notification of Summons and Prosecution
6............. Future
Key Issues
7.1.......... Noise Monitoring
7.2.......... Water Quality Monitoring
7.3.......... Ecological
Impact Monitoring
7.4.......... Review
of the Reasons for and the Implications of Non-compliance
7.5.......... Summary
of action taken in the event of and follow-up on non-compliance
lIST
OF TABLES
Table 3.1 Summary of submission status under
EP-538/2017
Table 3.3
Summary of Environmental Inspections
Table 4.1 Noise
Monitoring Equipment
Table 4.2 Noise
Monitoring Station
Table 4.3 Water
Quality Monitoring Equipment
Table 4.4 Marine
Water Quality Stations for Water Quality Monitoring
Table 4.5 Action
and Limit Levels of Water Quality
Table 4.6 Summary
of Marine Water Quality Exceedances (EM&A manual)
Table 4.7 Review
of Exceedances in Turbidity and SS (proposed “and” approach)
Table 4.8 Summary
of Quantities of Waste Material
Table 5.1 Cumulative
Statistics on Complaints
Table 5.2 Cumulative
Statistics on Successful Prosecutions
Table 6.1 Construction
Activities and Recommended Mitigation Measures in Coming Reporting 3 Months
lIST OF FIGUREs
Figure 2.2 Contract Layout Plan
Figure
2.3 Locations of Noise Monitoring
Station
Figure
2.4 Locations of Water Quality
Monitoring Stations
Figure
2.5 Mark up Figure 5.4i extracted from
approved EIA Report (AEIAR-210/2017)
Figure
2.6 Location Plan for Temporary Holding
Nursery
lIST OF APPENDIces
Appendix 4.1 Copies of Calibration Certificates
Appendix
4.2 Impact Monitoring Schedule for
Reporting Month and Next Month
Appendix
4.3 Noise Monitoring Results and
Graphical Presentations
Appendix 4.4 Marine Water Quality Monitoring Results and
Graphical Presentations
Appendix
4.5 Monthly Summary Waste Flow Table
Appendix 6.1 3 Months Rolling Programme – September 2022 to November 2022
EXECUTIVE SUMMARY
i.
This
is the Monthly Environmental Monitoring and Audit (EM&A) Report
– August
2022 for the Outlying Islands Sewerage Stage 2 – South Lantau
Sewerage Works under Environmental Permit No. EP-538/2017 (Hereafter as “the
Project”). The construction works of the
Project was commenced on 3 November 2021
and the tentative completion date is Q1 2026. This Monthly EM&A Report
presents the environmental monitoring findings and information recorded during
the period of 1 to 31 August 2022. The cut-off date of reporting is at the end of
each reporting month.
ii.
In
the reporting period, the principal work activities undertaken are as follows:
· Excavation, sewer laying, construction
of manhole at Pui O Lo Uk Tsuen
· Excavation and site formation at San
Shek Wan Sewage Treatment Works (SSWSTW) and Pui O Sewage Pumping Station (POSPS)
· Excavation at South Lantau Road
· SSWSTW and HDD works
· Site formation works at POSPS
· ELS works at POSPS
Exceedances of Action/Limit Levels
Noise Monitoring
iii.
Noise monitoring was conducted at seven (7)
noise monitoring stations (N12a, N12b,
N13, N14, N16a, N16b and N17) once per week in the reporting period.
iv.
No examination was taken place at N17 – Bui O Public School in the
reporting period.
v.
No Action/Limit
Level exceedances were recorded in this reporting period.
Water Quality Monitoring
vi.
Water quality monitoring had been commenced on 12 April 2022 the
designated monitoring stations three days per week with respect to marine-based
construction works commenced on 19 April 2022. HDD casing works commenced on 30
May 2022.
vii.
Water quality monitoring on 9 August 2022 and flood tide on 24 August
2022 was cancelled due to adverse weather.
viii.
Refer to the Section 3.4 of Environmental Permit, the monthly EM&A
report will be submitted within 2 weeks after end of the reporting month, since
liaison with HOKLAS Laboratory (ALS), the WQM result for Suspended Solids (SS)
on 31 August 2022 could not be issued before the report due date, as such, the
cut-off day for WQM for this report would be 30 August 2022. The WQM result for
31 August 2022 would be presented in next monthly EM&A report i.e.
September 2022.
ix.
In accordance with the EM&A Manual, 19 action level and 0 limit
level exceedances on DO, 27 action level and 16 limit level exceedances on
turbidity, 13 action level and 30 limit level exceedances on SS were recorded
in the reporting month.
x.
Action Level exceedances were recorded on 11 August 2022 on DO, reviewed
the overall work situation with no marine works and sea condition, it can be
concluded that the DO exceedances were possibly due to Tropical Storm MULAN
during 9 – 10 August 2022.
xi.
Overall exceedances on turbidity and SS (i.e. SR4, SR15 downstream to
the construction site during mid-ebb, SR5, SR6, SR9, SR10 and SR12 exceedances
downstream to the construction site during mid-flood,) in the reporting month
were referred to the 20% / 30% of control station criteria only whereas there
were no exceedance as referred to 95%-ile / 99%-ile criteria, indicating that
the exceedance is due to the localized water quality better than baseline range
were captured at the control station whereas the impact station are still
within the baseline ranges.
xii.
Co-related the monitoring dates with those days
with recorded marine works activities, no marine dredging works were active during
the reporting month. Majority of
recorded marine works activities were maintenance on working barge not in
contact with water, except casing installation for marine HDD works between 2 -
6 and 15 -19 August 2022 within the replaced fully enclosed silt curtain. Reviewed the overall work situation with
limited marine works, it can be concluded that all the turbidity and SS
exceedances were possibly due to natural runoff from streams to the sea as a
result of frequent rainfall as recorded in the reporting month (tropical
cyclone warning signals recorded on 3 - 4, 9 - 10 and 23 – 25 August 2022.
There was also typhoon no. 8 on 24 – 25 August 2022).
xiii.
Reviewing the “and approach”, no exceedance in turbidity and SS would be
recorded on adopting the ‘and’ criteria in the Action and Limit Level as
proposed in submitted Baseline Monitoring Report.
Ecological Impact Monitoring
xiv.
Transplanting of the trees of Aquilaris sinensis was completed on 26 April 2022. Maintenance works for trees in holding
nursery have commenced.
xv.
As per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of
SSWSTW which are considered to be the plant species with conservative
importance for temporarily transplanted to the nursery at Kam Tin and
eventually be transplanted to Pui O Pumping Station.
xvi.
The weekly site audit was carried out by ET include checking whether
good site practices are being properly implemented by the Contractor.
xvii.
The extent of the work site boundaries was checked by the ET during the
weekly site audit.
Complaint log
xviii.
No environmental complaint regarding the construction
works was recorded in the reporting period.
Notifications
of Any Summons and Successful Prosecutions
xix.
No environmental notification of any summons and
successful prosecution regarding the construction works was recorded in the
reporting period.
Reporting
Changes
xx.
There are no particular reporting changes.
Future
Key Issues
xxi.
In coming reporting 3 months, the scheduled construction activities are
listed as follows:
·
Excavation,
sewer laying, construction of manhole at Pui O Lo Uk Tsuen
·
Construction
of trunk sewers and rising mains
·
SSWSTW
and HDD works
·
Site
formation works for POSPS
·
Drilling
works
·
Excavation
works
·
ELS works
·
Piling
Works
·
Superstructure
RC Words
xxii.
Key
construction activities for the next three months with the recommended
mitigation measures to be implemented are presented as follows:
|
Key Construction Works |
Recommended Mitigation Measures |
|
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen ·
Construction of trunk sewers and rising mains ·
SSWSTW and HDD works ·
Site formation works for POSPS ·
Drilling works ·
Excavation works ·
ELS works ·
Piling Works ·
Superstructure RC Words |
·
Implementation of noise pollution control in accordance with
Construction Noise Mitigation Plan; ·
Dust control during dust generating works; ·
Adopt surface drainage and sediment control facilities for sewage
installation in village and public roads; ·
Adopt temporary drainage and sediment control facilities on Site; ·
Vehicle wheel-washing and body washing facilities should be provided
at the site entrance; ·
Regular water spraying on drilling and excavation works for dust
control; and ·
Proper waste handling, recycling and storage. |
1.1.1.
Lam Environmental Services Limited (LES) has been appointed to work as
the Environmental Team (ET) under Environmental Permit (EP) No. EP-538/2017 to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for the Outlying Islands Sewerage Stage 2 – South
Lantau Sewerage Works (Register No.: AEIAR-210/2017).
1.1.2.
In accordance with Clause 3.4 stated in EP-538/2017, 4 hard copies and 1
electronic copy of Monthly EM&A Report shall be submitted to the Director
within 2 weeks after the end of each reporting month.
1.1.3.
According to Section 12.2 of the Project EM&A Manual, the Monthly
EM&A Report should be submitted within 10 working days of the end of each
reporting month, with the first report due in the month after construction
commences.
Section 1 Introduction – details the scope and structure of the report.
Section 2 Basic
project Information and Environmental Status – summarizes project organization and key personnel contact,
construction programme and works undertaken for the month. Construction
programme, works undertaken during the month with illustrations, drawing
showing the project area, environmental sensitive receivers and monitoring
locations.
Section 3 Implementation
Status – advice on the implementation
status of environmental protection and pollution control/mitigation measures,
as recommended in the EIA Report and summarised in the updated implementation
schedule.
Section 4 Monitoring
Results – summarizes the monitoring
results obtained in the reporting period, including monitoring methodology,
name of laboratory and equipment used and calibration details, parameters
monitored, monitoring locations (and depth), monitoring date, frequency, and
duration.
Section 5 Report
on Complaints,
Notification of Summons and Successful Prosecutions – summarizes:
Record of all complaints received (written or
verbal) for each media, including locations and nature of complaints
investigation, liaison and consultation undertaken, actions and follow-up
procedures taken, results and summary;
Record of notifications of summons and
successful prosecutions for breaches of the current environmental
protection/pollution control legislations, including locations and nature of
the breaches, investigation, follow-up actions taken, results and summary;
Review of the reasons for and the implications
of non-compliance, complaints, summons and prosecutions including review of
pollution sources and working procedures; and
Description of the actions taken in the event
of non-compliance and deficiency reporting and any follow-up procedures related
to non-compliance.
Section 6 Future Key Issues – An account of the future key issues as reviewed from
the works programmed and work method statements.
Section 7 Conclusion
2.1.1. Drainage Services Department is the
overall project controllers for the Project. For the construction phase of the Project,
Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage
and control environmental issues. Key personnel and contact particulars are
summarized in Table 2.1:
Table
2.1 Contact Details of Key Personnel
|
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
|
Drainage
Services Department (DSD) |
The Engineer for the
Contract |
Engineer |
Mr. Silas Chan |
2594 7272 |
3104 6426 |
|
Binnies
Hong Kong Limited |
Engineer’s
Representative |
Resident
Engineer |
Mr. Clarence Chak |
6428 5532 |
- |
|
Kwan
Lee – Chun Wo Joint Venture |
Contractor
|
Site
Agent |
Mr. Charles Tse |
9270 3384 |
2744 6937 |
|
Environmental
Officer |
Ms. Shirley Kong |
5162 5933 |
|||
|
SMEC Hong Kong |
Independent Environmental
Checker (IEC) |
Independent Environmental Checker (IEC) |
Ms. Kitty Lee |
3995 8140 |
3995 8101 |
|
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Derek Lo |
2882 3939 |
2882 3331 |
2.2.1.
The proposed sewerage works will collect the sewage generated from the unsewered areas
of Shui Hau, Tong Fuk, Cheung Sha,
San Shek Wan, Pui O and Ham Tin in South Lantau (i.e.
within the Project Catchment Area) and convey it to a proposed sewage treatment
works at San Shek Wan for treatment and disposal into outer bay
of Pui O/ Chi Ma Wan via a submarine outfall.
2.2.2.
The entire Project are divided into three contracts. Contract No.
DC/2020/20 (the Contract) would have the following implementations as
demonstrated in Figure 2.1.
2.2.3.
The major components of the Contract under Environmental Permit (EP) (EP
No. EP-538/2017) comprises: (i) construction of sewage treatment works at San
Shek Wan (SSWSTW) and associated submarine outfall; (ii) construction of sewage
pumping station at Pui O (POSPS); (iii) village sewage works at Pui O; and (iv)
trunk sewers and rising mains on carriageways.
2.2.4.
The performance
of the environmental management system of the reporting period was generally
satisfied. Mitigation measures according to the environmental mitigation
implementation schedule and the EIA were generally implemented by the
Contractor. Hence, the EM&A programme was considered effective and shall be
maintained.
2.3.1.
In the reporting month, the principal work activities conducted are as
follow:
· Excavation, sewer laying, construction
of manhole at Pui O Lo Uk Tsuen
· Excavation and site formation at SSWSTW
and POSPS
· Excavation at South Lantau Road
· SSWSTW and HDD works
· Site formation works at POSPS
· ELS works at POSPS
The
locations of works are shown in Figure 2.2.
2.4.1.
Noise and water monitoring location plans with sensitive receivers are
shown in Figure 2.3 and Figure 2.4.
3.1.1. Mitigation measures according to
the environmental mitigation implementation schedule in Annex A of EM&A
Manual were generally implemented by the Contractor. Hence, the EM&A
programme was considered effective and shall be maintained.
3.2.1. Environmental mitigation measures
mentioned the EIA Report were weekly reviewed and recorded in Weekly
Environmental Site Audit Checklist. Also, a summary of the current status on
submissions and measures mentioned in Environmental Permit (EP-538/2017) are
shown in Table 3.1.
Table 3.1 Summary of submission status under EP-538/2017
|
EP Condition |
Submission |
Date of Latest Submission to EPD^ / EPD Approval# |
|
Condition 2.10 |
Waste Management Plan (Rev. 5) (electronic copy) |
4 April 2022# |
|
Condition 2.11 |
Submission of Preservation and/or Transplantation Plan for Plant
Species of Conservation Importance (Rev. 23) |
31 August 2022^ |
|
Condition 2.12 |
Submission of Compensatory Woodland Planting Plan (Rev. 12) |
8 August 2022^ |
|
Condition 2.13 |
Silt Curtain Deployment Plan (Rev. 14) |
5 August 2022^ |
|
Condition 2.14 |
Landscape Mitigation Plan |
To be confirmed |
|
Condition 2.15 |
Construction Noise Mitigation Plan (Rev. 20) |
4 August 2022# |
3.3.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.2.
Table 3.2 Summary of the current status on licences
and/or permits on environmental protection pertinent to the Project
|
Permits and/or Licences |
Permit. No. / Account No. |
Issued Date |
Valid Period & Expiry Date |
Status |
|
Notification
of Works Under APCO |
466408 |
14 Apr
2021 |
N/A |
Valid |
|
Discharge
Licence |
POPS:
WT00039820-2021 SSWSTW:
WT00039636-2021 |
31 Dec
2021 30 Dec
2021 |
31-12-2021
to 31-12-2026 30-12-2021
to 31-12-2026 |
Valid |
|
Billing
account under Waste Disposal Ordinance |
Account
No.: 7040411 |
05 May
2021 |
N/A |
Valid |
|
Registration
as a Chemical Waste Producer |
0000-931-K3428-01 |
13 May
2021 |
N/A |
Valid |
|
Construction
Noise Permit |
GW-RS0428-22 |
26 May
2022 |
29-05-2022
to 28-11-2022 |
Cancelled |
|
|
GW-RS0642-22 |
3 Aug
2022 |
05-08-2022
to 02-02-2023 |
Valid |
Note: Only include those valid
or under application; fill in “N/A” for non-applicable item(s).
3.4.1.
Within this reporting month, weekly environmental site inspections were
conducted on 02, 09, 15, 23 and 30 August 2022. IEC attended the SSEMC meeting
held on 15 August 2022. Holding nursery visit for
transplanted trees on 15 August 2022.
3.4.2. No non-compliance was found during the site inspection while reminders on
environmental measures were recommended. Results and
findings of these inspections in this reporting month are listed below in Table
3.3.
Table 3.3 Summary
of Environmental Inspections
|
Inspection Date |
Reminder and Recommendations |
Close-out Date / Status |
|
2 August 2022 |
1.
No particular finding |
N/A |
|
9 August 2022 |
1.
No particular finding |
N/A |
|
15 August
2022 |
Pui O Sewage Pumping Station 1. Damaged cover should be replaced to prevent the soil and sand
dispersion 2. Contractor is reminded to segregating and sorting different
types of waste into different recycle bins 3. Contractor is requested to clear the stagnant water in the drip
tray regularly 4. Electric cable should be removed from the tree. Transplant trees in holding nursery 5. The Contractor was reminded to remove other herbaceous plant
species from the plant species of conservation importance, Gmelina chinensis (T742) |
22 August 2022 |
|
23 August
2022 |
San Shek Wan Sewage Treatment Works 1. Open pipe ends shall be placed inside collection pit to avoid
accidental spill of untreated water on slope |
27 August 2022 |
|
30 August 2022 |
Pui O
Sewage Pumping Station 1.
The exposed roots of retained
tree within the construction site should be protected properly Village
sewers works (Lo Uk Tsuen) 2.
The generator shall be sited as
far away from Noise Sensitive Receivers(NSRs) as possible or provided
moveable noise barrier to reduce noise nuisance to NSRs San Shek
Wan Sewage Treatment Works 3.
Oil stain was observed,
contractor was requested to remove the contaminated soil as chemical waste properly |
1
September 2022 |
4.1.1
Monitoring
Procedure
(a)
The impact noise monitoring should be
carried out at all the designated monitoring stations when there are
project-related construction activities undertaken within a radius of 300m from
the monitoring stations.
(b)
The monitoring station shall normally
be at a point 1m from the exterior of the sensitive receiver’s building façade
and be at a position 1.2m above the ground.
(c)
Façade measurements were made at the
monitoring locations. For free-field measurement, a correction factor of +3 dB (A)
would be applied.
(d)
The battery condition was checked to
ensure the correct functioning of the meter.
(e)
Parameters such as frequency weighting,
the time weighting and the measurement time were set as follows:
(f)
Frequency weighting: A, Time weighting:
Fast, Measurement time set: continuous 5 mins
(g)
Prior and after to the noise
measurement, the meter was checked using the acoustic calibrator for 94dB (A)
at 1000 Hz. If the difference in the calibration level before and after
measurement was more than ±1.0 dB (A), the measurement would be considered
invalid and repeat of noise measurement would be required after re-calibration
or repair of the equipment.
(h)
Noise measurements will be made in
accordance with standard acoustical principles and shall not be made in fog,
rain, wind with a steady speed exceeding 5m/s or wind with gusts exceeding
10m/s. The wind speed shall be checked with a portable wind speed meter capable
of measuring the wind speed in m/s.
name of laboratory and
equipment used and calibration details
4.1.2
Noise monitoring was performed
using sound level meter at the designated monitoring locations. The sound level
meters shall comply with the International Electro-technical Commission
Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications. Acoustic
calibrator shall be deployed to check the sound level meters at a known sound
pressure level. Brand and model of the equipment is given in Table
4.1.
Table 4.1 Noise Monitoring Equipment
|
0006346 |
||
|
Honglim HLES-02 |
2016611465 |
4.1.3 The calibration certificates of the noise monitoring equipment are attached in Appendix 4.1.
4.1.4
Calibration Details
(a)
The microphone head of the sound level
meter was cleaned with soft cloth at regular intervals.
(b)
The sound level meter and calibrator
were calibrated at yearly intervals.
Parameters monitored
4.1.5
The
construction noise level shall be measured in terms of the A-weighted
equivalent continuous sound pressure level (Leq). Leq(30min)
should be used as the monitoring parameter. Supplementary information for data auditing, statistical results
such as L10 and L90 shall also be obtained for reference.
4.1.6
For
impact monitoring for construction of village sewers / rising main,
noise monitoring should be undertaken on weekly basis. One set of Leq(30min)
noise level as six consecutive Leq(5min) between 07:00-19:00 hours
on normal weekdays.
Monitoring Stations
4.1.7
The
noise monitoring stations for the Project are listed and shown in Table 4.2,
impact noise monitoring was conducted at Seven (7) noise monitoring stations N12a, N12b, N13, N14,
N16a, N16b and N17 once per week in the reporting month.
Table 4.2 Noise
Monitoring Station
|
Monitoring
Station ID (1) |
Monitoring
Location |
Measurement
Type |
Level (in terms
of no.
of floor) |
|
N01a |
Shui Hau Village |
Free-Field |
G/F |
|
N01c |
Shui Hau Village |
Free-Field |
G/F |
|
N03a |
Tong Fuk Village |
Free-Field |
G/F |
|
N05a |
Residences at Cheung Fu Street |
Free-Field |
G/F |
|
N07 |
Government Holiday Bungalows |
Free-Field |
G/F |
|
N08 |
Cheung Sha Ha Tsuen |
Free-Field |
G/F |
|
N10 |
Cheung Sha Sheung Tsuen |
Façade |
G/F |
|
N11b |
San Shek Wan – Ming Garden |
Free-Field |
G/F |
|
N12a |
Lo Uk Tsuen |
Free-Field |
G/F |
|
N12b |
Lo Uk Tsuen |
Façade |
G/F |
|
N13 |
Pui O San Wai Tsuen |
Façade |
G/F |
|
N14 |
South Lantau Community Centre |
Free-Field |
G/F |
|
N15b |
Pui O Lo Wai Tsuen |
Façade |
G/F |
|
N16a |
Residences at Ham Tin |
Free-Field |
G/F |
|
N16b |
Residences at Ham Tin |
Free-Field |
G/F |
|
N17 |
Bui O Public School |
Façade |
R/F |
Remarks (1): Fine
adjustment of noise monitoring stations at all locations was proposed as per EP
Condition 3.1.
Monitoring date, time,
Frequency and Duration
4.1.8
For
daytime construction work on normal weekdays, monitoring of Leq(30min)
should be carried out at each station at 0700-1900 hours on normal weekdays at
a frequency of once a week. Impact
monitoring schedule can be referred to Appendix
4.2.
Noise Monitoring Results
4.1.9
Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring results and graphical presentation can
be referred in Appendix 4.3.
4.1.10
No examination was
taken place at N17 – Bui O Public School in the reporting period.
4.1.11
No action or limit level exceedance was recorded in construction
noise level in this reporting period.
Monitoring Methodology
4.2.1
Monitoring
Procedure
(a)
The condition near the monitoring
stations shall be observed and recorded on the data log sheet.
(b)
Check of sensors and electrodes with
certified standard solutions before each use.
(c)
Wet bulb calibration for a DO meter
should be carried out before measurement.
(d)
Water depth should be recorded by
detector before sampling.
(e)
Sample would be taken using bucket
sampler at surface level.
(f)
Transfer the sampled water carefully
into cleaned water bottles (2x 1000ml) provided by the laboratory at the spot
after the collection of the water sample for the subsequent laboratory
Suspended Solid testing.
(g)
Transfer the sampled water from the
bucket sampler to the rinsed water container for in-situ measurement (In case
of the in-situ measurement cannot be carried at spot due to safety and adverse
weather condition, sampled water from the bucket sampler will be transfer to
cleaned water bottles provided by laboratory. Then, In-situ measurement will be
conducted at a safe location which sampled water inside cleaned water bottle
will be transfer to the rinsed water container for in-situ measurement) In-situ
measurement shall be measured in duplicate.
(h)
Parameters including Water Temperature
(°C), pH (units), Salinity (ppt), DO (mg/L), DO saturation (%) will be
measured by the Multifunctional Meter and Turbidity (NTU) will be measured by turbid
meter. (Water Temperature and Salinity will be measured as reference
parameters)
(i)
Record the result on the data log sheet
and record any special finding during / after in-situ measurement.
(j)
The water sample bottles will be stored
in a cool box (at cooled to 4°C without
being frozen), which shall be delivered to HOKLAS laboratory (ALS Technichem
(HK) Pty Ltd) for further testing to determine the level of SS.
Name of laboratory and
equipment used and calibration details
Laboratory Measurement /
Analysis
4.2.2
Analysis
of suspended solids will be carried out in a HOKLAS accredited laboratory,
which is ALS Technichem (HK) Pty Ltd.
equipment used
Dissolved Oxygen, pH And Temperature Measuring
Equipment
4.2.3
Multifunctional
Meter and Turbid Meter are used at each designated monitoring station. They are
capable of measuring:
(a)
a dissolved oxygen level in the range
of 0-20mg/L and 0-200% saturation (Detection Limit: 0.1mg/L)
(b)
a temperature of 0-45 degree Celsius (Detection Limit: 0.1 degree Celsius)
(c)
turbidity level between 0-1000NTU (Detection
Limit: 0.1NTU)
(d)
salinity in the range of 0-40ppt (Detection
Limit: 0.1ppt)
(e)
pH value in range of 0.0 – 14.0
(Detection Limit: 0.1units)
Other monitoring equipment namely water depth meter, water current
meter, dGPS positioning device, water sampler listed below were also deployed,
(a)
Water depth meter (Range: 0.6 -100m, Resolution: 0.1m)
(b)
Water current meter (Range: 0-360o, Detection
Limit: 1mm/s)
(c)
dGPS positioning device (Resolution: Horizontal: 0.25m; Vertical:
0.50 m )
(d)
Water sampler (Horizontal discrete type, Capacity: 2.2L)
Sampler Container and Storage
4.2.4
A
water sampler, Water samples for suspended solids measurement should be
collected in high-density polythene bottles, packed in ice (cooled to 4°C
without being frozen), and delivered to ALS Technichem (HK) Pty Ltd. as soon as
possible after collection for analysis.
Water Depth Detector
4.2.5
A
portable, battery-operated echo sounder shall be used for the determination of
water depth at each designated monitoring station. This unit can either be
handheld or affixed to the bottom of the workboat, if the same vessel is to be
used throughout the monitoring programme.
calibration details
4.2.6
Maintenance
and Calibration
(a)
The responses of sensors and electrodes
of the water quality monitoring equipment were cleaned and checked at regular
intervals.
(b)
DO meter (Multifunctional Meter) and
turbid meter was certified by a laboratory accredited under HOKLAS or any other
international accreditation scheme, and subsequently re-calibrated at three
monthly intervals.
4.2.7
Brand and model of the
equipment are given in Table 4.3.
Table
4.3 Water Quality Monitoring Equipment
|
Equipment |
Brand and
model |
Series
Number |
|
Multifunctional Meter |
Sonde YSI Professional Plus |
19H100656/14E101065 |
|
Turbid meter |
Xin Rui WGZ-3B |
1807073 |
Calibration certificates of the water
quality monitoring equipment are attached in Appendix 4.1.
Parameters monitored
4.2.8
In
construction phase, the levels of dissolved oxygen (DO), temperature, turbidity
and salinity should be measured in situ while suspended solids (SS) is
determined by laboratory analysis.
MONITORING STATIONS
4.2.9
Water quality monitoring involves
9 monitoring stations. The locations of water quality monitoring station are
shown in Table 4.4.
Table 4.4 Marine
Water Quality Stations for Water Quality Monitoring
|
Station |
Description |
Easting |
Northing |
|
CE |
Upstream
control station at ebb tide |
810838 |
807538 |
|
CF |
Upstream control
station at flood tide |
815886 |
808081 |
|
SR4 (1) |
Ecological
Sensitive Receiver (Coral Communities) at Pui O Wan |
814938 |
810975 |
|
SR5 |
Ecological
Sensitive Receiver (Coral Communities) at Pui O Wan |
814326 |
810540 |
|
SR6 |
Gazetted Bathing Beach at Lower Cheung Sha |
810553 |
810475 |
|
SR9 (1) |
Ecological Important Stream
at Tong Fuk |
811325 |
809787 |
|
SR10 |
Secondary Contact
Recreational Zones at South Lantau |
810561 |
809494 |
|
SR12 (1) |
Proposed Special Site of
Scientific Interest (SSSI) at Shui Hau Wan |
810359 |
808989 |
|
SR15 |
Gazetted Bathing Beach at Pui O and Ecologically Important Stream at Pui O |
816037 |
810722 |
Remarks (1): Fine adjustment of water
quality monitoring stations at SR4, SR9 and SR12 was proposed as per EP
Condition 3.1, and baseline monitoring was conducted at corresponding fine
adjusted locations.
Monitoring date, time,
Frequency and Duration
4.2.10 Water quality monitoring had been
commenced on 12 April 2022 the designated monitoring stations three days per
week with respect to marine-based construction works commenced on 19 April
2022. HDD casing works commenced on 30
May 2022.
4.2.11 Water quality monitoring on 9 August
2022 and flood tide on 24 August 2022 was cancelled due to adverse weather. No
substitution would be arranged for such cancellation since it is impossible to
maintain the monitoring frequency as three times a week for the event of marine
water quality monitoring cancellation in between time with respect to the fact
that not less than 36 hours interval shall be followed for two monitoring days
as required by the EM&A Manual Clause 5.1.6 (b) for the project.
4.2.12 Refer to the Section 3.4 of
Environmental Permit, the monthly EM&A report will be submitted within 2
weeks after end of the reporting month, since liaison with HOKLAS Laboratory
(ALS), the WQM result for Suspended Solids (SS) on 31 August 2022 could not be
issued before the report due date, as such, the cut-off day for WQM for this
report would be 30 August 2022. The WQM result for 31 August 2022 would be
presented in next monthly EM&A report i.e. September 2022.
4.2.13
The
levels of dissolved oxygen (DO), temperature, turbidity and salinity were
measured in situ while suspended solids (SS) is determined by laboratory
analysis at all the monitoring stations in Table 4.4 three times a week. Impact
monitoring schedule can be referred to Appendix
4.2.
4.2.14
In
association with the water quality parameters, other relevant data shall also
be recorded, such as monitoring location / position, time, water temperature,
DO saturation, weather conditions, and any special phenomena underway near the
monitoring station.
4.2.15
Impact
Monitoring shall be carried out three days per week, at mid-flood and mid-ebb
tides (within ± 1.75 hour of the predicted time). The interval between two sets
of monitoring shall not be less than 36 hours. The monitoring period should
avoid concurrent marine project in the vicinity.
4.2.16
The
sampling frequency of at least three days per week should be undertaken. Upon
completion of the construction works, the monitoring exercise at the designated
monitoring locations should be continued for four weeks in the same manner as
the impact monitoring. In case exceedance of Action/Limit Level is recorded,
the frequency shall be increased as per the Event and Action Plan.
4.2.17
To
ensure the robustness of in-situ measurement, parameters shall be measured in
duplicate. In case the difference between duplicates is larger than 25%, a
third set of measurement shall be carried out.
Monitoring Results
4.2.18
Marine
water quality monitoring results measured in this reporting period are reviewed
and summarized. Details of marine water quality monitoring results and
graphical presentation can be referred in Appendix 4.4
4.2.19
Water
quality monitoring is evaluated against Action and Limit Levels. Note that derived
Action and Limit Level was proposed in Baseline Monitoring Report for approval.
Action and Limit Levels of marine water quality monitoring have been set with reference to the EM&A Manual criteria and
derived criteria as shown in Table 4.5 below.
Table
4.5 Action and Limit Levels of Water
Quality
|
Parameters |
Action Level |
Limit Level |
|
Construction
Phase Marine Water Monitoring - EM&A Manual criteria |
||
|
DO in mg/L |
Surface and Middle: 5.8 mg/L Bottom: 5.9 mg/L |
Surface and Middle: 4 mg/L Bottom: 2 mg/L |
|
Turbidity
in NTU (Depth-averaged A) c |
14.4 NTU, or 20% exceedance of value at any impact station compared with
corresponding data from control station |
23.5 NTU, or 30% exceedance of value at any impact station compared with
corresponding data from control station |
|
SS in mg/L (Depth-averaged
A) c |
13.1 mg/L, or 20% exceedance of value at any impact station compared with
corresponding data from control station |
30.4 mg/L, or 30% exceedance of value at any impact station compared with
corresponding data from control station |
|
Construction
Phase Marine Water Monitoring - derived criteria |
||
|
DO in mg/L
B |
Surface and Middle: 5.8 mg/L Bottom: 5.9 mg/L |
Surface and Middle: 4 mg/L Bottom: 2 mg/L |
|
Turbidity
in NTU (Depth-averaged A) C |
14.4 NTU and 20% exceedance of value at any impact station compared with
corresponding data from control station D |
23.5 NTU and 30% exceedance of value at any impact station compared with
corresponding data from control station D |
|
SS in mg/L (Depth-averaged
A) C |
13.1 mg/L and 20% exceedance of value at any impact station compared with
corresponding data from control station D |
30.4 mg/L and 30% exceedance of value at any impact station compared with corresponding
data from control station D |
Notes (with proposed amendments in AL/LL in underlined
text):
A. “Depth-averaged” is calculated by taking
the arithmetic means of reading of all three depths.
B. For DO, non-compliance of the water
quality limits occurs when monitoring result is lower than the limits.
C. For SS and turbidity, non-compliance of
the water quality limits occurs when monitoring result is higher than the
limits.
D. Action Level and Limit Level with 95%-ile /
99%-ile derived from baseline data “and” 20% / 30% exceedance of control
station proposed in Baseline Monitoring Report.
4.2.20
Number
of exceedances recorded during the reporting month are summarized in Table
4.6.
Table
4.6 Summary of Marine Water Quality
Exceedances (EM&A manual)
|
|
Parameter |
DO (S&M) |
DO (Bottom) |
Turbidity |
SS |
Exceedance count |
|||||
|
Station |
Level exceeded |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
|
SR4 |
Action |
11/8/2022 |
11/8/2022 |
11/8/2022 |
/ |
4/8/2022 11/8/2022 26/8/2022 |
2/8/2022 |
13/8/2022 26/8/2022 |
/ |
7 |
2 |
|
|
Limit |
/ |
/ |
/ |
/ |
24/8/2022 |
13/8/2022 19/8/2022 |
2/8/2022 4/8/2022 17/8/2022 19/8/2022 24/8/2022 |
22/8/2022 |
6 |
3 |
|
SR5 |
Action |
11/8/2022 |
11/8/2022 |
11/8/2022 |
11/8/2022 |
11/8/2022 26/8/2022 29/8/2022 |
11/8/2022 |
4/8/2022 26/8/2022 |
/ |
7 |
3 |
|
|
Limit |
/ |
/ |
/ |
/ |
13/8/2022 22/8/2022 |
13/8/2022 17/8/2022 |
13/8/2022 17/8/2022 19/8/2022 22/8/2022 |
/ |
6 |
2 |
|
SR6 |
Action |
11/8/2022 |
11/8/2022 |
/ |
/ |
11/8/2022 13/8/2022 26/8/2022 |
11/8/2022 |
26/8/2022 |
/ |
5 |
2 |
|
|
Limit |
/ |
/ |
/ |
/ |
22/8/2022 |
/ |
2/8/2022 22/8/2022 29/8/2022 |
26/8/2022 |
4 |
1 |
|
SR9 |
Action |
11/8/2022 |
11/8/2022 |
11/8/2022 |
11/8/2022 |
11/8/2022 22/8/2022 26/8/2022 |
17/8/2022 26/8/2022 |
22/8/2022 26/8/2022 |
2/8/2022 |
7 |
5 |
|
|
Limit |
/ |
/ |
/ |
/ |
/ |
/ |
2/8/2022 24/8/2022 |
26/8/2022 |
2 |
1 |
|
SR10 |
Action |
11/8/2022 |
11/8/2022 |
/ |
/ |
2/8/2022 11/8/2022 17/8/2022 26/8/2022 |
/ |
2/8/2022 |
/ |
6 |
1 |
|
|
Limit |
/ |
/ |
/ |
/ |
24/8/2022 |
6/8/2022 17/8/2022 |
4/8/2022 24/8/2022 |
2/8/2022 26/8/2022 |
3 |
4 |
|
SR12 |
Action |
11/8/2022 |
11/8/2022 |
/ |
/ |
11/8/2022 26/8/2022 |
11/8/2022 |
2/8/2022 |
4/8/2022 15/8/2022 |
4 |
4 |
|
|
Limit |
/ |
/ |
/ |
/ |
13/8/2022 |
17/8/2022 |
4/8/2022 |
22/8/2022 26/8/2022 |
2 |
3 |
|
SR15 |
Action |
11/8/2022 |
11/8/2022 |
/ |
/ |
11/8/2022 26/8/2022 |
17/8/2022 |
/ |
26/8/2022 |
3 |
3 |
|
|
Limit |
/ |
/ |
/ |
/ |
4/8/2022 13/8/2022 |
13/8/2022 |
2/8/2022 4/8/2022 24/8/2022 |
15/8/2022 22/8/2022 29/8/2022 |
5 |
4 |
|
Total |
Action |
7 |
7 |
3 |
2 |
20 |
7 |
9 |
4 |
59 |
|
|
|
Limit |
0 |
0 |
0 |
0 |
8 |
8 |
20 |
10 |
46 |
|
4.2.21
In
accordance with the EM&A Manual, 19 action level
and 0 limit level exceedances on DO, 27 action level and 16 limit
level exceedances on turbidity, 13 action level
and 30 limit level exceedances on SS were
recorded in the reporting month.
4.2.22
SR4
and SR15 located at upstream of construction site during mid-flood such that
the Action and Limit Level exceedances on turbidity and SS along these stations
in general were contributed by upstream sources before entering the submarine
outfall construction location.
Similarly, SR5, SR6, SR9, SR10 and SR12 located at upstream of
construction site during mid-ebb, such that the Action and Limit Level
exceedances on turbidity and SS along these stations in general were
contributed by upstream sources before entering the submarine outfall
construction location.
4.2.23
Checked
with contractor and RSS on the marine works activities in the reporting month on the scheduled WQM dates, the following activities were
recorded:
·
11, 13,
22 - 31/8/2022 - No activity
·
2 - 6, 15
- 19/8/2022 - Appliance maintenance on working barge and casing installation
for marine HDD works
4.2.24 Action Level exceedances were recorded
on 11 August 2022 on DO, reviewed the overall work situation with no marine
works and sea condition, it can be concluded that the DO exceedances were
possibly due to Tropical Storm MULAN during 9 – 10 August 2022.
4.2.25 Overall exceedances on turbidity and SS
(i.e. SR4, SR15 downstream to the construction site during mid-ebb, SR5, SR6,
SR9, SR10 and SR12 exceedances downstream to the construction site during
mid-flood,) in the reporting month were referred to the 20% / 30% of control
station criteria only whereas there were no exceedance as referred to 95%-ile /
99%-ile criteria, indicating that the exceedance is due to the localized water
quality better than baseline range were captured at the control station whereas
the impact station are still within the baseline ranges.
4.2.26 Co-related the monitoring dates with those
days with recorded marine works activities, no marine dredging works were
active during the reporting month. Majority
of recorded marine works activities were maintenance on working barge not in
contact with water, except casing installation for marine HDD works between 2 –
6 and 15-19 August 2022 within the replaced fully enclosed silt curtain. Reviewed the overall work situation with
limited marine works, it can be concluded that all the turbidity and SS
exceedances were possibly due to natural runoff from streams to the sea as a
result of frequent rainfall as recorded in the reporting month (tropical
cyclone warning signals recorded on 3 - 4, 9 - 10 and 23 – 25 August 2022.
There was also typhoon no. 8 on 24 – 25 August 2022).
4.2.27 Reviewing the “and“ approach, no exceedance in turbidity and SS would be
recorded on adopting the ‘and’ criteria in
the Action and Limit Level as proposed in submitted Baseline Monitoring
Report as presented in Table
4.7. Majority of the
exceedance were considered to be false alarm with review of the “and“ approach
for counteracting the over-sensitivity of control station criteria as proposed
in the baseline report.
Table
4.7 Review of Exceedances in Turbidity
and SS (proposed “and” approach)
|
|
Parameter |
Turbidity |
SS |
Exceedance count |
|||
|
Station |
Level exceeded |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
|
SR4 |
Action |
- |
- |
- |
- |
0 |
0 |
|
|
Limit |
- |
- |
- |
- |
0 |
0 |
|
SR5 |
Action |
- |
- |
- |
- |
0 |
0 |
|
|
Limit |
- |
- |
- |
- |
0 |
0 |
|
SR6 |
Action |
- |
- |
- |
- |
0 |
0 |
|
|
Limit |
- |
- |
- |
- |
0 |
0 |
|
SR9 |
Action |
- |
- |
- |
- |
0 |
0 |
|
|
Limit |
- |
- |
- |
- |
0 |
0 |
|
SR10 |
Action |
- |
- |
- |
- |
0 |
0 |
|
|
Limit |
- |
- |
- |
- |
0 |
0 |
|
SR12 |
Action |
- |
- |
- |
- |
0 |
0 |
|
|
Limit |
- |
- |
- |
- |
0 |
0 |
|
SR15 |
Action |
- |
- |
- |
- |
0 |
0 |
|
|
Limit |
- |
- |
- |
- |
0 |
0 |
|
Total |
Action |
0 |
0 |
0 |
0 |
0 |
|
|
|
Limit |
0 |
0 |
0 |
0 |
0 |
|
MONITORING METHODOLOGY
4.3.1
The
weekly site audit to be carried out by the ET should include checking whether good
site practices are being properly implemented by the Contractor.
4.3.2
Impact
monitoring of the transplanted Aquilaris sinensis at holding nursery and one retain tree of Aquilaris sinensis in SSWSTW Project
Site, establishment and after-establishment caring measures of the compensatory
mixed woodland to ensure the affected tree would not be affected by any
unacceptable construction works. The trees would be treated with establishment
works immediately after transplanting.
PARAMETERS MONITORED
4.3.3
The
extent of the work site boundaries should be checked by the ET during the
weekly site audit. Any disturbance by
the Contractor outside the works area especially any damage to the vegetation
and surrounding habitats outside the Project area shall be reported to ER and
IEC.
4.3.4
To
identify any unacceptable construction works for the trees of Aquilaris sinensis during transplanting,
establishment and after-establishment caring measures of the compensatory mixed
woodland.
MONITORING LOCATION
4.3.5
As
per latest version of PTP, four tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of SSWSTW (Figure
2.5) which are considered to be the plant species with
conservative importance for temporarily transplanted to the nursery (Figure
2.6) at Kam Tin and eventually be transplanted to Pui O
Pumping Station.
MONITORING DATE, TIME,
FREQUENCY AND DURATION
4.3.6
The
recommended good site practices to be audited once every week as part of the
site audit programme. The weekly site audit to be carried out by the ET
includes checking whether good site practices are being properly implemented by
the Contractor. Results are recorded in Weekly Environmental Site Audit
Checklist.
4.3.7
Monitoring
programme for post-transplantation will be conducted once per month (15 August 2022).
MONITORING RESULTS
4.3.8
The
weekly site audit was carried out by ET include checking whether good site
practices are being properly implemented by the Contractor.
4.3.9
The
extent of the work site boundaries was checked by the ET during the weekly site
audit.
4.3.10
Results
and findings of site audit in this reporting month are listed in Table 3.3.
4.4.1 The quantities of waste for disposal in the
Reporting Period are summarized in Table 4.8. The Monthly Summary Waste
Flow Table is shown in Appendix
4.5.
Table
4.8 Summary of Quantities of Waste
Material
|
Waste Type |
Quantity this month |
Quantity (the end of last month) |
Cumulative Quantity-to-Date |
|
Hard Rock and Large Broken Concrete (Inert) (in ‘000m3) |
0 |
0 |
0 |
|
Reused in this Contract (Inert) (in ‘000m3) |
0 |
0 |
0 |
|
Reused in other Projects (Inert) (in ‘000m3) |
0 |
0 |
0 |
|
Disposal as Public Fill (Inert) (in ‘000m3) |
0.09705 |
0.01537 |
6.70848 |
|
Metals (in ‘000kg) |
0.00300 |
0 |
1.56800 |
|
Paper / Cardboard Packing (in ‘000kg) |
0.04410 |
0 |
0.18158 |
|
Plastics (in ‘000kg) |
0.00710 |
0 |
0.02116 |
|
Chemical Wastes (in ‘000kg) |
0 |
0 |
0 |
|
General Refuses (in ‘000kg) |
18.25460# |
17.34 |
363.0246 |
*: Further breakdown
into sub-group if considered applicable;
#: 4.6 kg
of glass were recycled, and courted in general refuse.
5.1.1
No environmental complaint, notification of summons and successful
prosecution regarding construction works was recorded in the reporting period.
5.1.2
No notification of summons and successful prosecution regarding construction
works were recorded in the reporting period.
5.1.3
Cumulative statistic on complaints and successful prosecutions are
summarized in Table 5.1 and Table 5.2 respectively.
Table
5.1 Cumulative Statistics on
Complaints
|
Reporting
Period |
No.
of Complaints |
|
August
2022 |
0 |
|
Project
commencement to the end of last reporting month |
1 |
|
Total |
1 |
Table
5.2 Cumulative Statistics on
Successful Prosecutions
|
Environmental
Parameters |
Cumulative
No. Brought Forward |
No.
of Successful Prosecutions this month (Offence Date) |
Cumulative
No. Project-to-Date |
|
Air |
- |
0 |
0 |
|
Noise |
- |
0 |
0 |
|
Water |
- |
0 |
0 |
|
Waste |
- |
0 |
0 |
|
Other |
- |
0 |
0 |
|
Total |
- |
0 |
0 |
6.1.1
In coming reporting 3 months, the scheduled construction activities are
listed as follows:
·
Excavation,
sewer laying, construction of manhole at Pui O Lo Uk Tsuen
·
Construction
of trunk sewers and rising mains
·
SSWSTW
and HDD works
·
Site
formation works for POSPS
·
Drilling
works
·
Excavation
works
·
ELS works
·
Piling
Works
·
Superstructure
RC Works
6.1.2
The scheduled construction activities and the recommended mitigation
measures for the coming 3 months are listed in Table 6.1. The
major construction activities for the next 3 months are summarized in Three
Months Rolling Programme - September 2022 to November 2022 in Appendix
6.1.
Table 6.1 Construction
Activities and Recommended Mitigation Measures in Coming Reporting 3 Months
|
Key Construction Works |
Recommended Mitigation Measures |
|
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen ·
Construction of trunk sewers and rising mains ·
SSWSTW and HDD works ·
Site formation works for POSPS ·
Drilling works ·
Excavation works ·
ELS works ·
Piling Works ·
Superstructure RC Words |
·
Implementation of noise pollution control in accordance with
Construction Noise Mitigation Plan; ·
Dust control during dust generating works; ·
Adopt surface drainage and sediment control facilities for sewage
installation in village and public roads; ·
Adopt temporary drainage and sediment control facilities on Site; ·
Vehicle wheel-washing and body washing facilities should be provided
at the site entrance; ·
Regular water spraying on drilling and excavation works for dust
control; and ·
Proper waste handling, recycling and storage. |
7.1.1
No examination was taken place at N17 – Bui O
Public School in the reporting period.
7.1.2
No
action or limit level exceedance was recorded in construction noise level in
this reporting period.
7.2.1
Marine-based construction works commenced on
19 April 2022, HDD casing works commenced on 30 May 2022.
7.2.2
Water quality monitoring on 9 August 2022 and
flood tide on 24 August 2022 was cancelled due to adverse weather.
7.2.3
Refer to the Section 3.4 of Environmental Permit, the monthly EM&A
report will be submitted within 2 weeks after end of the reporting month, since
liaison with HOKLAS Laboratory (ALS), the WQM result for Suspended Solids (SS)
on 31 August 2022 could not be issued before the report due date, as such, the
cut-off day for WQM for this report would be 30 August 2022. The WQM result for
31 August 2022 would be presented in next monthly EM&A report i.e.
September 2022.
7.2.4
In accordance with the EM&A Manual, 19 action level and 0 limit
level exceedances on DO, 27 action level and 16 limit level exceedances on
turbidity, 13 action level and 30 limit level exceedances on SS were recorded
in the reporting month. No exceedance in turbidity and SS would be
recorded on adopting the “and” criteria in the Action and Limit Level as proposed
in the Baseline Monitoring Report.
7.3.1
Transplanting of the trees of Aquilaris sinensis was completed on 26
April 2022. Maintenance works for trees in holding nursery have commenced.
7.3.2
As per latest version of PTP, four tree found
(1 no. of Aquilaria sinensis and 3
nos. of Gmelina chinensis) within the
site of SSWSTW which are considered to be the plant species with conservative
importance for temporarily transplanted to the nursery at Kam Tin and
eventually be transplanted to Pui O Pumping Station.
7.3.3
The weekly site audit was carried out by ET
include checking whether good site practices are being properly implemented by
the Contractor.
7.3.4
The extent of the work site boundaries was
checked by the ET during the weekly site audit.
7.3.5
Within
this reporting period, holding nursery visit for transplanted trees on 15 August 2022.
7.3.6
No non-compliance
was found during the site inspection while reminders on environmental measures
were recommended. Results and findings of these inspections in this reporting period
are listed below in Table 7.1.
Table 7.1 Summary
of Ecological
Impact Monitoring
|
Inspection Date |
Reminder and Recommendations |
Close-out Date / Status |
|
15
August 2022 |
1.
The Contractor was reminded to
remove other herbaceous plant species from the plant species of conservation
importance, Gmelina chinensis
(T742) |
22 August 2022 |
7.4.1
No environmental
non-compliance was recorded in the reporting month.
7.5.1
There
was no particular action taken since no non-compliance was recorded in the reporting
period.
Figure 2.1
Master Layout Plan
Figure 2.2
Contract Layout Plan
Figure 2.3
Locations of Noise Monitoring Station
Figure 2.4
Locations of Water Quality Monitoring Stations
Figure 2.5
Mark up Figure 5.4i extracted from approved EIA
Report (AEIAR-210/2017)
Figure 2.6
Location Plan for Temporary Holding Nursery
Appendix 4.1
Copies of Calibration Certificates
Appendix 4.2
Impact Monitoring Schedule for Reporting Month and
Next Month
Appendix 4.3
Noise Monitoring Results and Graphical
Presentations
Appendix 4.4
Marine Water Quality Monitoring Results and
Graphical Presentations
Appendix 4.5
Monthly Summary Waste Flow Table
Appendix 6.1
Three Months Rolling Programme – September 2022 to
November 2022