CONTRACT NO: SD 6/2020
Construction of San Shek Wan Sewage Treatment Works
Associated Submarine Outfall and Pui O Sewerage Works Under Environmental Permit no. EP-538/2017
Monthly Environmental Monitoring & Audit Report
april 2022
revision 2.4
|
|
CLIENTS: |
|
|
Drainage Services Department |
Lam Environmental Services Limited 19/F Remex Centre, 42 Wong Chuk Hang Road, Hong Kong Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
|
|
|
Certified
by: |
|
|
Melody Cheng Environmental
Team Leader |
|
|
DATE: |
|
|
20 May 2022 |
|
|
|
1.1.......... Scope of the Report
1.2.......... Structure of the Report
2.1.......... Construction Programme
2.2.......... Works undertaken during the month
3.2.......... Environmental Mitigation Measures
3.3.......... Environmental monitoring requirements and
contractual requirements
3.4.......... Site Inspection and Audit Reports
4.1.......... Noise Monitoring
4.2.......... Water Quality Monitoring
4.4.......... Waste Management
5. Complaints, Notification
of Summons and Prosecution
lIST OF TABLES
Table 3.1 Summary
of submission status under EP-538/2017
Table 3.3 Summary of Environmental
Inspections
Table 4.1 Noise Monitoring Equipment
Table 4.2 Noise Monitoring Station
Table 4.3 Water Quality Monitoring Equipment
Table 4.4 Marine Water Quality Stations for
Water Quality Monitoring
Table 4.5 Action and Limit Levels of Water
Quality
Table 4.6 Summary of Marine Water Quality
Exceedances (EM&A manual)
Table 4.7 Review of Exceedances in Turbidity
and SS (proposed “and” approach)
Table 4.8 Summary of Quantities of Waste
Material (as of April 2022)
Table 5.1 Cumulative Statistics on Complaints
Table 5.2 Cumulative Statistics on
Successful Prosecutions
Table 6.1 Construction Activities and
Recommended Mitigation Measures in Coming Reporting 3 Months
lIST OF FIGUREs
Figure 2.2 Contract Layout Plan
Figure 2.3
Locations of Noise Monitoring Station
Figure
2.4 Locations of Water Quality
Monitoring Stations
Figure 2.5 Mark up Figure 5.4i extracted from approved
EIA Report (AEIAR-210/2017)
Figure
2.6 Location Plan for Temporary Holding
Nursery
lIST OF APPENDIces
Appendix 4.1 Copies of Calibration Certificates
Appendix
4.2 Impact Monitoring Schedule
Appendix
4.3 Noise Monitoring Results and
Graphical Presentations
Appendix 4.4 Marine Water Quality Monitoring Results and
Graphical Presentations
Appendix
4.5 Monthly Summary Waste Flow Table
Appendix 6.1 3 Months Rolling Programme – May 2022 to July 2022
EXECUTIVE SUMMARY
i.
This
is the Environmental Monitoring and Audit (EM&A) Monthly Report
– April
2022 of Outlying
Islands Sewerage Stage 2 – South Lantau Sewerage Works under Environmental
Permit no. EP-538/2017 (Hereafter as “the Project”). The construction works of the
Project was commenced on 3 November 2021
and the tentative completion date is Q1 2026. The
EM&A report presenting the environmental monitoring findings and
information recorded during the period of 01 April 2022 to 30 April 2022. The cut-off date of reporting is at the end of each
reporting month.
ii.
In
the reporting month, the principal work activities conducted are as follow:
·
Maintenance works for tree in holding nursery and Site
·
Excavation and site formation works at San Shek Wan Sewage Treatment Works
(SSWSTW) and Pui O Sewage Pumping Station (POSPS).
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen
·
Excavation of Trial Pit at Chi Ma Wan Road and South Lantau Road
·
Pre-drilling works at Pui O beach road
·
Preparation of HDD works
·
Installation of silt curtain and construction of temporary marine
platform
Exceedances of Action/Limit Levels
Noise Monitoring
iii.
Noise monitoring was conducted at five (5)
noise monitoring stations N12a, N12b, N13, N14 and N17 once per week in the
reporting month.
iv.
No action or limit level exceedance was recorded in construction noise
level in this reporting period.
Water Quality Monitoring
v.
Marine-based construction works commenced on 19 April 2022. Water quality monitoring had been
commenced on 12 April 2022 at seven (7)
monitoring stations three days per week. Results to be provided.
vi.
Marine-based construction works commenced on 19 April 2022, water
quality monitoring was commenced on 12 April 2022. 66 action level exceedances on DO, 4 action
level and 81 limit level exceedances on turbidity, 2 action level and 49 limit
level exceedances on SS were recorded in the reporting month.
vii.
Out of 66 action level exceedances on DO, 61 of these exceedances were
due to background contribution as recorded at the control stations on 14, 16,
18, 20, 22 and 29 April 2022 whereas action level exceedance on DO recorded at
SR9 and SR10 on 27 April 2022 were reviewed with no exceedance recorded at
nearby upstream stations SR5 and SR6 from the location of marine-based
construction works and concluded as non-project related.
viii.
Out of the 4 action level and 81 limit level exceedances on turbidity, 2
action level and 49 limit level exceedances on SS were recorded in the
reporting month, 4 action level exceedances on SS were concluded after removing
those false alarm exceedance using the “and“ approach proposed in the baseline
report. Action level exceedance on SS
recorded on 27 April 2022 was reviewed with no exceedance recorded at nearby
upstream stations SR5 and SR6 from the location of marine-based construction
works and concluded as non-project related.
Ecological Impact Monitoring
ix.
Transplanting of the trees of Aquilaris sinensis was completed on 26 April 2022. Maintenance works for trees in holding
nursery have commenced.
x.
Preservation of retain tree of Aquilaris sinensis on Project Site.
Complaint log
xi.
No environmental complaint regarding the construction works
was recorded in the reporting period.
Notifications
of Any Summons and Successful Prosecutions
xii.
No environmental notification of any summons and
successful prosecution regarding the construction works was recorded in the
reporting period.
Reporting
Changes
xiii.
Commencement date of marine works was 19 May 2022 and silt curtain installation
works was commenced on the same day.
Future
Key Issues
xiv.
In
coming reporting 3 months, the scheduled construction activities and the
recommended mitigation measures are listed as follows:
|
Recommended Mitigation Measures |
|
|
·
Maintenance and establishment works for transplanted trees in holding
nursery. ·
Preservation of existing trees on Project Site ·
Village sewers (excavation, sewer laying, construction of manhole) at
Pui O Lo Uk Tsuen and Chi Ma Wan Beach ·
Trunk Sewers and Rising Mains outside village and to POSPS ·
Construction of POSPS ·
Horizontal directional drilling (HDD) works for SSWSTW land side ·
Retaining wall construction and slope modification works at SSWSTW ·
HDD works at sea side |
·
Provide caring measures for the health,
form and structural conditions for
transplant trees including Aquilaris sinensis in holding nursery; ·
Fully implement tree preservation works on site and holding nursery to
ensure compliance of relevant legislation and guidelines stated in EM&A
Manual. ·
Implementation of noise pollution control in accordance with
Construction Noise Mitigation Plan; ·
Dust control during dust generating works; ·
Adopt surface
drainage and sediment control facilities for sewage installation in village
and public roads; ·
Adopt temporary
drainage and sediment control facilities on Site; ·
Vehicle wheel-washing and body washing facilities should be provided
at the site entrance; ·
Regular water spraying on exposed area; and ·
Proper waste handling, recycling and storage. ·
Silt curtains
should be installed to surround the marine dredging area in accordance with
Silt Curtain Deployment Plan. |
1.1.1.
Lam Environmental Services Limited (LES) has been appointed to work as
the Environmental Team (ET) under Environmental Permit (EP) no. EP-538/2017 to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Outlying Islands Sewerage Stage 2 - South Lantau
Sewerage Works (Register No.: AEIAR-210/2017).
1.1.2.
In accordance with Clause 3.4 stated in EP-538/2017, 4 hard copies and 1
electronic copy of Monthly EM&A Report shall be submitted to the Director
within 2 weeks after the end of each reporting month.
1.1.3.
According to Section 12.2 of the Project EM&A Manual, the Monthly
EM&A Report should be submitted within 10 working days of the end of each
reporting month, with the first report due in the month after construction commences.
Section 1 Introduction – details the scope and structure of the report.
Section 2 Environmental
Status – construction programme, works
undertaken during the month with illustrations, drawing showing the project
area, environmental sensitive receivers and monitoring locations.
Section 3 Implementation
Status – Advice on the implementation
status of environmental protection and pollution control/mitigation measures,
as recommended in the EIA Report and summarised in the updated implementation
schedule.
Section 4 Monitoring
Results – summarizes the monitoring
results obtained in the reporting period, including monitoring methodology,
name of laboratory and equipment used and calibration details, parameters
monitored, monitoring locations (and depth), monitoring date, frequency, and
duration.
Section 5 Report
on Complaints,
Notification of Summons and Successful Prosecutions
Record of all complaints
received (written or verbal) for each media, including locations and nature of
complaints investigation, liaison and consultation undertaken, actions and
follow-up procedures taken, results and summary;
Record of notifications
of summons and successful prosecutions for breaches of the current
environmental protection/pollution control legislations, including locations
and nature of the breaches, investigation, follow-up actions taken, results and
summary;
Review of the reasons for and
the implications of non-compliance, complaints, summons and prosecutions
including review of pollution sources and working procedures; and
Description of the actions
taken in the event of non-compliance and deficiency reporting and any follow-up
procedures related to non-compliance.
Section 6 Others – An account of the future key issues as reviewed from
the works programme and work method statements.
Section 7 Conclusion
2.1.1
The proposed sewerage works will collect the sewage generated from
the unsewered areas of Shui Hau, Tong Fuk,
Cheung Sha, San Shek Wan, Pui O and Ham Tin in South
Lantau (i.e. within the Project Catchment Area) and convey it to a proposed
sewage treatment works at San Shek Wan for treatment and disposal
into outer bay of Pui O/ Chi Ma Wan via a submarine outfall.
2.1.2
The entire Project are divided into three contracts. Contract No.
DC/2020/20 (the Contract) would have the following implementations as
demonstrated in Figure 2.1.
2.1.3
The major components of the Project under Environmental Permit (EP) (EP
No. EP-538/2017) comprises: (i) construction of sewage treatment works at San
Shek Wan (SSWSTW) and associated submarine outfall; (ii) construction of sewage
pumping station at Pui O (POSPS); (iii) village sewage works at Pui O; and (iv)
trunk sewers and rising mains on carriageways.
2.1.4
No construction programme with fine
tuning of construction activities showing the inter-relationship with
environmental protection/ mitigation measures for the month.
2.2.1
In the reporting month, the principal work activities conducted are as
follow:
·
Maintenance works for tree in holding nursery and Site
·
Excavation and site formation works at San Shek Wan Sewage Treatment
Works (SSWSTW) and Pui O Sewage Pumping Station (POSPS).
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen
·
Excavation of Trial Pit at Chi Ma Wan Road and South Lantau Road
·
Pre-drilling works at Pui O beach road
·
Preparation
of HDD works
·
Installation
of silt curtain and construction of temporary marine platform
The
locations of works are shown in Figure
2.2.
3.1.1 Mitigation measures according to
the environmental mitigation implementation schedule in Annex A of EM&A
Manual were generally implemented by the Contractor. Hence, the EM&A
programme was considered effective and shall be maintained.
3.1.2
Ecological mitigation measures – Preservation and protection of trees of
Aquilaris sinensis. Advices are the following:
a)
Protection and preservation of retain tree Aquilaris sinensis (tree no. T370) on Project
Site;
b)
Proper soiling and mulching practices for transplanted tree Aquilaris
sinensis (tree no. T392) in holding nursery.
c)
Timely conduct rectification works to enhance recovery of tree in
transit nursery.
3.1.3 Landscape & Visual mitigation
measures – Transplantation of 6 trees no. T113, T114, T742, T751, T758 and T392 have completed
on 1st March 2022. Advices are the following:
a)
Monitoring and maintaining transplanted trees in holding nursery should
follow General Specification of Civil Engineering Works – Section 3 and “Guidelines on Tree Transplanting”
specified in EM&A Manual.
b)
Timely conduct rectification works to enhance recovery of tree in
transit nursery.
3.1.4
Tree Protection and Preservation - Retain trees in the Project Site
should be protected and preserved in accordance with CEDD G.S. Section 3 and DEVB
TC(W) No. 7/2015. In particular, maintaining Tree Protection Zone with proper
tree label.
3.1.5
Water quality mitigation measures – Silt curtain should be installed
around the dredging area and pilot hole exit area vertically from sea surface
to seabed. The silt curtain extent, offset distance from the works area should
follow Silt Curtain Deployment Plan.
3.2.1
Environmental mitigation measures mentioned the EIA Report were weekly
reviewed and recorded in Weekly Environmental Site Audit Checklist. Also, a
summary of the current status on submissions and measures mentioned in
Environmental Permit (EP-538/2017) are shown in Table 3.1.
Table 3.1 Summary of
submission status under EP-538/2017
|
EP Condition |
Submission |
Date of Latest Submission to EPD^ / EPD Approval# |
|
Condition 2.10 |
Waste Management Plan (Rev. 5) (electronic copy) |
4 April 2022# |
|
Condition 2.11 |
Submission of Preservation and/or Transplantation Plan for Plant
Species of Conservation Importance (Rev. 4) |
25 June 2021^ |
|
Condition 2.12 |
Submission of Compensatory Woodland Planting Plan (Rev. 5) |
2 July 2021^ |
|
Condition 2.13 |
Silt Curtain Deployment Plan (Rev. 11) |
29 April 2022^ |
|
Condition 2.14 |
Landscape Mitigation Plan |
To be confirmed |
|
Condition 2.15 |
Construction Noise Mitigation Plan (Rev. 14) |
8 April 2022^ |
3.3.1
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.2.
Table 3.2 Summary of the
current status on licences and/or permits on environmental protection pertinent
to the Project
|
Permits and/or Licences |
Permit.
No. / Account No. |
Issued Date |
Valid Period & Expiry Date (dd-mm-yyyy to dd-mm-yyyy) |
Status |
|
Notification
of Works Under APCO |
466408 |
14 Apr
2021 |
N/A |
Valid |
|
Discharge
Licence |
POPS:
WT00039820-2021 SSWSTW:
WT00039636-2021 |
31 Dec
2021 30 Dec
2021 |
31-12-2021
to 31-12-2026 30-12-2021
to 31-12-2026 |
Valid |
|
Billing
account under Waste Disposal Ordinance |
Account
No.: 7040411 |
05 May
2021 |
N/A |
Valid |
|
Registration
as a Chemical Waste Producer |
0000-931-K3428-01 |
13 May
2021 |
N/A |
Valid |
|
Construction
Noise Permit |
GW-RS0921-21 |
26 Nov
2021 |
29-11-2021
to 28-05-2022 |
Valid |
Note: Only include
those valid or under application; fill in “N/A” for non-applicable item(s).
3.4.1
Within this reporting month, weekly environmental site inspections were
conducted on 06, 13, 19
and 26 April 2022.
IEC attended the SSEMC meeting held on 19 April 2022. Holding nursery visit for
transplanted trees on 26 April 2022.
3.4.2
No non-compliance was found during
the site inspection while reminders on environmental measures were recommended.
Results and findings of these inspections in this
reporting month are listed below in Table 3.3.
Table 3.3 Summary
of Environmental Inspections
|
Inspection Date |
Reminder and Recommendations |
Close-out Date / Status |
|
6 Apr 2022 |
Lo Uk Tsuen Village Sewer Works 1. Reminder
for using QPME for village sewer works San Shek Wan Sewage Treatment
Works 2. Fully
implement tree preservation and protection on site, including provision of
tree label and tree status, set up tree protection zone for retain trees Trial pit 3. Fully
implement tree preservation and protection on site, including provision of
tree label and tree status, set up tree protection zone for retain trees |
13 Apr
2022 |
|
13 Apr 2022 |
Lo Uk Tsuen Village Sewer Works Fully implement tree preservation
and protection on site, including provision of tree label and tree status,
set up tree protection zone for retain trees |
19 Apr
2022 |
|
19 Apr 2022 |
Lo Uk Tsuen Village Sewer Works Observation 1 - Fully implement
tree preservation and protection on site, construction waste should not be
placed within tree protection zone for retain trees. San Shek Wan Sewage Treatment
Works Observation 2 – Remove debris in
drainage facilities to ensure proper function Reminder 1 - Provide vehicle
wheel-washing facilities as soon as possible Pui O
Sewage Pumping Station Please be reminded wet
season has started. Temporary drainage has to be properly implemented and be
prepared for heavy rainstorm event to avoid effluent discharge accidentally
washed out with muddy water. |
21 Apr
2022 |
|
26 Apr 2022 |
Transplant trees in
holding nursery Observation
1:
Recommended
measures: rectify soil and required soil size
Recommended measures:
apply mulch in accordance with CEDD G.S. and GLTMS Guideline on Tree
Transplanting stated in Annex A of EM&A Manual |
Pending |
4.1.1
Monitoring Procedure
(a)
The impact noise monitoring should be
carried out at all the designated monitoring stations when there are
project-related construction activities undertaken within a radius of 300m from
the monitoring stations.
(b)
The monitoring station shall normally
be at a point 1m from the exterior of the sensitive receiver’s building façade
and be at a position 1.2m above the ground.
(c)
Façade measurements were made at the
monitoring locations. For free-field measurement, a correction factor of +3 dB (A)
would be applied.
(d)
The battery condition was checked to
ensure the correct functioning of the meter.
(e)
Parameters such as frequency weighting,
the time weighting and the measurement time were set as follows:
(f)
Frequency weighting: A, Time weighting:
Fast, Measurement time set: continuous 5 mins
(g)
Prior and after to the noise
measurement, the meter was checked using the acoustic calibrator for 94dB (A)
at 1000 Hz. If the difference in the calibration level before and after
measurement was more than ±1 dB (A), the measurement would be considered invalid
and repeat of noise measurement would be required after re-calibration or
repair of the equipment.
name of laboratory and
equipment used and calibration details
4.1.2
Noise monitoring was performed
using sound level meter at the
designated monitoring locations.
The sound level meters shall comply with the
International Electrotechnical Commission
Publications 651:1979
(Type
1) and
804:1985 (Type 1)
specifications.
Acoustic calibrator shall
be deployed to check the sound level meters at a known sound pressure level. Brand and model of the equipment is given in Table
4.1.
Table 4.1 Noise
Monitoring Equipment
|
0006346 |
||
|
Honglim HLES-02 |
2016611465 |
4.1.3 The calibration certificates of the noise monitoring
equipment are attached in Appendix
4.1.
4.1.4
Calibration Details
(a)
The microphone head of the sound level
meter was cleaned with soft cloth at regular intervals.
(b)
The sound level meter and calibrator
were calibrated at yearly intervals.
Parameters monitored
4.1.5
The construction noise level shall be measured in terms of the
A-weighted equivalent continuous sound pressure level (Leq). Leq
(30min) should be used as the monitoring parameter. Supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for reference.
4.1.6
For impact monitoring for construction of village sewers / rising main,
noise monitoring should be undertaken on weekly basis. One set of Leq (30min)
noise level as six consecutive Leq (5min) between 07:00-19:00 hours
on normal weekdays.
Monitoring Stations
4.1.7
The noise monitoring stations for the Project are listed and shown in Table
4.2, impact noise monitoring was
conducted at five (5) noise monitoring stations N12a, N12b, N13, N14 and N17
once per week in the reporting month.
Table 4.2 Noise
Monitoring Station
|
Monitoring
Station ID (1) |
Monitoring
Location |
Measurement
Type |
Level (in terms
of no.
of floor) |
|
N01a |
Shui Hau Village |
Free-Field |
G/F |
|
N01c |
Shui Hau Village |
Free-Field |
G/F |
|
N03a |
Tong Fuk Village |
Free-Field |
G/F |
|
N05a |
Residences at Cheung Fu Street |
Free-Field |
G/F |
|
N07 |
Government Holiday Bungalows |
Free-Field |
G/F |
|
N08 |
Cheung Sha Ha Tsuen |
Free-Field |
G/F |
|
N10 |
Cheung Sha Sheung Tsuen |
Façade |
G/F |
|
N11b |
San Shek Wan – Ming Garden |
Free-Field |
G/F |
|
N12a |
Lo Uk Tsuen |
Free-Field |
G/F |
|
N12b |
Lo Uk Tsuen |
Façade |
G/F |
|
N13 |
Pui O San Wai Tsuen |
Façade |
G/F |
|
N14 |
South Lantau Community Centre |
Free-Field |
G/F |
|
N15b |
Pui O Lo Wai Tsuen |
Façade |
G/F |
|
N16a |
Residences at Ham Tin |
Free-Field |
G/F |
|
N16b |
Residences at Ham Tin |
Free-Field |
G/F |
|
N17 |
Bui O Public School |
Façade |
R/F |
Remarks (1): Fine
adjustment of noise monitoring stations at all locations was proposed as per EP
Condition 3.1.
Monitoring date, time,
Frequency and Duration
4.1.8
For daytime construction work on normal weekdays, monitoring of Leq(30min)
should be carried out at each station at 0700-1900 hours on normal weekdays at
a frequency of once a week. Impact monitoring schedule can be referred to Appendix
4.2.
Noise Monitoring Results
4.1.9
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise monitoring results and graphical presentation
can be referred in Appendix 4.3.
4.1.10
No action or limit level exceedance was recorded in
construction noise level in this reporting period.
Monitoring Methodology
4.2.1
Monitoring Procedure
(a)
The condition near the monitoring
stations shall be observed and recorded on the data log sheet.
(b)
Check of sensors and electrodes with
certified standard solutions before each use.
(c)
Wet bulb calibration for a DO meter
should be carried out before measurement.
(d)
Water depth should be recorded by
detector before sampling.
(e)
Sample would be taken using bucket
sampler at surface level.
(f)
Transfer the sampled water carefully
into cleaned water bottles (2x 1000ml) provided by the laboratory at the spot
after the collection of the water sample for the subsequent laboratory
Suspended Solid testing.
(g)
Transfer the sampled water from the
bucket sampler to the rinsed water container for in-situ measurement (In case
of the in-situ measurement cannot be carried at spot due to safety and adverse
weather condition, sampled water from the bucket sampler will be transfer to
cleaned water bottles provided by laboratory. Then, In-situ measurement will be
conducted at a safe location which sampled water inside cleaned water bottle
will be transfer to the rinsed water container for in-situ measurement) In-situ
measurement shall be measured in duplicate.
(h)
Parameters including Water Temperature
(℃), pH (units), Salinity (ppt), DO (mg/L), DO saturation (%) will be measured
by the Multifunctional Meter and Turbidity (NTU) will be measured by turbid
meter. (Water Temperature and Salinity will be measured as reference
parameters)
(i)
Record the result on the data log sheet
and record any special finding during / after in-situ measurement.
(j)
The water sample bottles will be stored
in a cool box (at cooled to 4℃ without being frozen), which shall be delivered
to HOKLAS laboratory (ALS Technichem (HK) Pty Ltd) for further testing to
determine the level of SS.
Name of laboratory and
equipment used and calibration details
Laboratory Measurement /
Analysis
4.2.2
Analysis of suspended solids will be carried out in a HOKLAS accredited
laboratory, which is ALS Technichem (HK) Pty Ltd.
equipment used
Dissolved Oxygen, pH And Temperature Measuring
Equipment
4.2.3
Multifunctional Meter and Turbid Meter are used at each designated
monitoring station. They are capable of measuring:
(a)
a dissolved oxygen level in the range
of 0-20mg/L and 0-200% saturation (Detection Limit: 0.1mg/L)
(b)
a temperature of 0-45 degree Celsius (Detection Limit: 0.1 degree Celsius)
(c)
turbidity level between 0-1000NTU (Detection
Limit: 0.1NTU)
(d)
salinity in the range of 0-40ppt (Detection
Limit: 0.1ppt)
(e)
pH value in range of 0.0 – 14.0
(Detection Limit: 0.1units)
Other monitoring equipment namely water depth meter, water current
meter, dGPS positioning device, water sampler listed below were also deployed,
(a)
Water depth meter (Range: 0.6 -100m, Resolution: 0.1m)
(b)
Water current meter (Range: 0-360o, Detection
Limit: 1mm/s)
(c)
dGPS positioning device (Resolution: Horizontal: 0.25m; Vertical:
0.50 m )
(d)
Water sampler (Horizontal discrete type, Capacity: 2.2L)
Sampler Container and Storage
4.2.4
A water sampler, Water samples for suspended solids measurement
should be collected in high-density polythene bottles, packed in ice (cooled to
4°C without being frozen), and delivered to ALS Technichem (HK) Pty Ltd. as
soon as possible after collection for analysis.
Water Depth Detector
4.2.5
A portable, battery-operated echo sounder shall be used for the
determination of water depth at each designated monitoring station. This unit
can either be handheld or affixed to the bottom of the workboat, if the same
vessel is to be used throughout the monitoring programme.
calibration details
4.2.6
Maintenance and Calibration
(a)
The responses of sensors and electrodes
of the water quality monitoring equipment were cleaned and checked at regular
intervals.
(b)
DO meter (Multifunctional Meter) and
turbid meter was certified by a laboratory accredited under HOKLAS or any other
international accreditation scheme, and subsequently re-calibrated at three
monthly intervals.
4.2.7
Brand and model of the equipment are given in Table 4.3.
Table 4.3 Water Quality Monitoring Equipment
|
Equipment |
Brand and
model |
Series
Number |
|
Multifunctional Meter |
Sonde YSI Professional Plus |
17F100236 |
|
Turbid meter |
Xin Rui WGZ-3B |
2005060 |
The calibration certificates of the water
quality monitoring equipment are attached in Appendix
4.1.
4.2.8
Marine-based construction works commenced on 19 April 2022, water
quality monitoring commenced on 12 April 2022.
Parameters monitored
4.2.9
In construction phase, the levels of dissolved oxygen (DO), temperature,
turbidity and salinity should be measured in situ while suspended solids (SS)
is determined by laboratory analysis.
MONITORING STATIONS
4.2.10
Water quality monitoring involves 9 monitoring stations. The locations
of water quality monitoring station are shown in Table 4.4.
Table 4.4 Marine Water Quality Stations for Water
Quality Monitoring
|
Station |
Description |
Easting |
Northing |
|
CE |
Upstream
control station at ebb tide |
810838 |
807538 |
|
CF |
Upstream
control station at flood tide |
815886 |
808081 |
|
SR4 (1) |
Ecological
Sensitive Receiver (Coral Communities) at Pui O Wan |
814938 |
810975 |
|
SR5 |
Ecological
Sensitive Receiver (Coral Communities) at Pui O Wan |
814326 |
810540 |
|
SR6 |
Gazetted Bathing Beach at Lower Cheung Sha |
810553 |
810475 |
|
SR9 (1) |
Ecological Important Stream
at Tong Fuk |
811325 |
809787 |
|
SR10 |
Secondary Contact
Recreational Zones at South Lantau |
810561 |
809494 |
|
SR12 (1) |
Proposed Special Site of
Scientific Interest (SSSI) at Shui Hau Wan |
810359 |
808989 |
|
SR15 |
Gazetted Bathing Beach at Pui O and Ecologically Important Stream at Pui O |
816037 |
810722 |
Remarks (1): Fine adjustment of water
quality monitoring stations at SR4, SR9 and SR12 was proposed as per EP
Condition 3.1, and baseline monitoring was conducted at corresponding fine
adjusted locations.
Monitoring date, time,
Frequency and Duration
4.2.11
The levels of dissolved oxygen (DO), temperature, turbidity and salinity
were measured in situ while suspended solids (SS) is determined by laboratory
analysis at all the monitoring stations in Table 4.4 three times a week. Impact
monitoring schedule can be referred to Appendix
4.2.
4.2.12
In association with the water quality parameters, other relevant data
shall also be recorded, such as monitoring location / position, time, water
temperature, DO saturation, weather conditions, and any special phenomena
underway near the monitoring station.
4.2.13
Impact Monitoring shall be carried out three days per week, at mid-flood
and mid-ebb tides (within ± 1.75 hour of the predicted time). The interval
between two sets of monitoring shall not be less than 36 hours. The monitoring
period should avoid concurrent marine project in the vicinity.
4.2.14
The sampling frequency of at least three days per week should be
undertaken when the highest dust impact occurs. Upon completion of the
construction works, the monitoring exercise at the designated monitoring locations
should be continued for four weeks in the same manner as the impact monitoring.
In case exceedance of Action/Limit Level is recorded, the frequency shall be
increased as per the Event and Action Plan.
4.2.15
To ensure the robustness of in-situ measurement, parameters shall be
measured in duplicate. In case the difference between duplicates is larger than
25%, a third set of measurement shall be carried out.
Monitoring Results
4.2.16
Marine water quality monitoring results measured in this reporting
period are reviewed and summarized. Details of marine water quality monitoring
results and graphical presentation can be referred in Appendix 4.4
4.2.17
Water quality monitoring is evaluated against Action and Limit Levels.
Note that derived Action and Limit Level was proposed in Baseline Monitoring
Report for approval. Action and Limit Levels of marine water quality monitoring
have been set with reference to the EM&A Manual criteria and derived
criteria as shown in Table 4.5 below.
Table 4.5 Action
and Limit Levels of Water Quality
|
Parameters |
Action Level |
Limit Level |
|
Construction
Phase Marine Water Monitoring - EM&A Manual criteria |
||
|
DO in mg/L |
Surface and Middle: 5.8 mg/L Bottom: 5.9 mg/L |
Surface and Middle: 4 mg/L Bottom: 2 mg/L |
|
Turbidity
in NTU (Depth-averaged A) c |
14.4 NTU, or 20% exceedance of value at any impact station compared with
corresponding data from control station |
23.5 NTU, or 30% exceedance of value at any impact station compared with
corresponding data from control station |
|
SS in mg/L (Depth-averaged
A) c |
13.1 mg/L, or 20% exceedance of value at any impact station compared with
corresponding data from control station |
30.4 mg/L, or 30% exceedance of value at any impact station compared with
corresponding data from control station |
|
Construction
Phase Marine Water Monitoring - derived criteria |
||
|
DO in mg/L
B |
Surface and Middle: 5.8 mg/L Bottom: 5.9 mg/L |
Surface and Middle: 4 mg/L Bottom: 2 mg/L |
|
Turbidity
in NTU (Depth-averaged A) C |
14.4 NTU and 20% exceedance of value at any impact station compared with
corresponding data from control station D |
23.5 NTU and 30% exceedance of value at any impact station compared with
corresponding data from control station D |
|
SS in mg/L (Depth-averaged
A) C |
13.1 mg/L and 20% exceedance of value at any impact station compared with
corresponding data from control station D |
30.4 mg/L and 30% exceedance of value at any impact station compared with corresponding
data from control station D |
Notes (with proposed amendments in AL/LL in underlined
text):
A. “Depth-averaged” is calculated by taking
the arithmetic means of reading of all three depths.
B. For DO, non-compliance of the water
quality limits occurs when monitoring result is lower than the limits.
C. For SS and turbidity, non-compliance of
the water quality limits occurs when monitoring result is higher than the
limits.
D. Action Level and Limit Level with 95%-ile /
99%-ile derived from baseline data “and” 20% / 30% exceedance of control
station proposed in Baseline Monitoring Report.
4.2.18
Number of exceedances recorded during the reporting month are summarized
in Table
4.6.
Table 4.6 Summary
of Marine Water Quality Exceedances (EM&A manual)
|
|
Parameter |
DO (S&M) |
DO (Bottom) |
Turbidity |
SS |
Exceedance count |
|||||
|
Station |
Level exceeded |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
|
SR4 |
Action |
14/04/22 18/04/22 20/04/22 |
18/04/22 20/04/22 |
18/04/22 20/04/22 22/04/22 29/04/22 |
18/04/22 22/04/22 |
- |
- |
- |
- |
7 |
4 |
|
|
Limit |
- |
- |
- |
- |
12/04/22 14/04/22 18/04/22 20/04/22 22/04/22 25/04/22 27/04/22 29/04/22 |
12/04/22 18/04/22 20/04/22 22/04/22 25/04/22 27/04/22 29/04/22 |
16/04/22 20/04/22 25/04/22 27/04/22 29/04/22 |
18/04/22 20/04/22 22/04/22 25/04/22 27/04/22 |
13 |
12 |
|
SR5 |
Action |
14/04/22 18/04/22 20/04/22 |
18/04/22 20/04/22 22/04/22 |
14/04/22 16/04/22 20/04/22 22/04/22 29/04/22 |
20/04/22 22/04/22 29/04/22 |
18/04/22 22/04/22 |
- |
18/04/22 |
- |
11 |
6 |
|
|
Limit |
- |
- |
- |
- |
12/04/22 14/04/22 20/04/22 22/04/22 25/04/22 27/04/22 29/04/22 |
18/04/22 20/04/22 22/04/22 25/04/22 27/04/22 29/04/22 |
14/04/22 16/04/22 20/04/22 22/04/22 25/04/22 27/04/22 |
18/04/22 20/04/22 22/04/22 27/04/22 |
13 |
10 |
|
SR6 |
Action |
16/04/22 20/04/22 22/04/22 |
18/04/22 20/04/22 22/04/22 29/04/22 |
- |
- |
- |
- |
- |
- |
3 |
4 |
|
|
Limit |
- |
- |
- |
- |
12/04/22 14/04/22 18/04/22 20/04/22 22/04/22 25/04/22 29/04/22 |
12/04/22 18/04/22 20/04/22 22/04/22 25/04/22 29/04/22 |
14/04/22 16/04/22 25/04/22 27/04/22 |
18/04/22 20/04/22 22/04/22 |
11 |
9 |
|
SR9 |
Action |
12/04/22 14/04/22 18/04/22 27/04/22 29/04/22 |
29/04/22 |
12/04/22 16/04/22 18/04/22 20/04/22 22/04/22 27/04/22 |
18/04/22 20/04/22 22/04/22 27/04/22 29/04/22 |
- |
- |
- |
- |
11 |
6 |
|
|
Limit |
- |
- |
- |
- |
12/04/22 14/04/22 18/04/22 20/04/22 25/04/22 27/04/22 |
12/04/22 18/04/22 20/04/22 25/04/22 27/04/22 29/04/22 |
16/04/22 |
18/04/22 20/04/22 |
7 |
8 |
|
SR10 |
Action |
16/04/22 20/04/22 |
20/04/22 22/04/22 27/04/22 |
- |
- |
27/04/22 |
- |
20/04/22 |
- |
4 |
3 |
|
|
Limit |
|
|
- |
- |
12/04/22 16/04/22 18/04/22 25/04/22 29/04/22 |
18/04/22 20/04/22 27/04/22 29/04/22 |
16/04/22 27/04/22 |
18/04/22 20/04/22 25/04/22 27/04/22 |
7 |
8 |
|
SR12 |
Action |
16/04/22 20/04/22 22/04/22 |
20/04/22 |
- |
- |
- |
20/04/22 |
- |
- |
3 |
2 |
|
|
Limit |
- |
- |
- |
- |
12/04/22 16/04/22 18/04/22 25/04/22 27/04/22 |
12/04/22 18/04/22 25/04/22 27/04/22 |
16/04/22 27/04/22 |
12/04/22 18/04/22 20/04/22 25/04/22 27/04/22 |
7 |
9 |
|
SR15 |
Action |
12/04/22 16/04/22 18/04/22 20/04/22 22/04/22 |
12/04/22 14/04/22 20/04/22 |
- |
- |
- |
- |
- |
- |
5 |
3 |
|
|
Limit |
- |
- |
- |
- |
12/04/22 18/04/22 20/04/22 25/04/22 29/04/22 |
12/04/22 18/04/22 20/04/22 25/04/22 29/04/22 |
25/04/22 29/04/22 |
12/04/22 18/04/22 20/04/22 25/04/22 |
7 |
9 |
|
Total |
Action |
24 |
17 |
15 |
10 |
3 |
1 |
2 |
0 |
72 |
|
|
|
Limit |
0 |
0 |
0 |
0 |
43 |
38 |
22 |
27 |
130 |
|
4.2.19
In accordance with the EM&A Manual, 66 action level exceedances on
DO, 4 action level and 81 limit level exceedances on turbidity, 2 action level
and 49 limit level exceedances on SS were recorded in the reporting month.
4.2.20
With respect to marine-based construction works commenced on 19 April
2022, Event and Action Plan stated in EM&A Manual were implemented for exceedance
recorded starting from 20 April 2022 whereas those monitoring results before 19
April 2020 were taken as reference.
4.2.21
Action level exceedances on DO were also recorded at control station CE
on 14, 16, 18, 20, 22 and 29 April 2022 and control station CF on 14, 18, 20
and 22 April 2022 which such that these recorded exceedance could be the
background contribution to DO exceedances at the impact stations on 14, 16, 18,
20, 22 and 29 April 2022.
4.2.22
For action level exceedance on DO recorded at SR9 and SR10 on 27 April
2022, no exceedance on DO were recorded at the nearby upstream stations SR5 and
SR6 from the location of marine-based construction works, these exceedance was
non-project related.
4.2.23
For turbidity and SS exceedances, no muddy water plume observed
immediately outside the silt curtain on 19, 20, 21, 22, 25, 26, 28 and 29 April
2022 as per the site condition recorded by ET.
As such, majority of the exceedance were considered to be false alarm
with review of the “and“ approach
for counteracting the over-sensitivity of control station criteria as proposed in
the baseline report. Reviewing the “and“ approach, the number of
exceedances recorded without false alarm are summarized in Table 4.7.
Table 4.7 Review of
Exceedances in Turbidity and SS (proposed “and” approach)
|
|
Parameter |
Turbidity |
SS |
Exceedance count |
|||
|
Station |
Level exceeded |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
Mid Ebb |
Mid Flood |
|
SR4 |
Action |
- |
- |
27/04/22 |
22/04/22 |
1 |
1 |
|
|
Limit |
- |
- |
- |
- |
0 |
0 |
|
SR5 |
Action |
- |
- |
- |
22/04/22 |
0 |
1 |
|
|
Limit |
- |
- |
- |
- |
0 |
0 |
|
SR6 |
Action |
- |
- |
- |
- |
0 |
0 |
|
|
Limit |
- |
- |
- |
- |
0 |
0 |
|
SR9 |
Action |
- |
- |
- |
- |
0 |
0 |
|
|
Limit |
- |
- |
- |
- |
0 |
0 |
|
SR10 |
Action |
- |
- |
- |
- |
0 |
0 |
|
|
Limit |
- |
- |
- |
- |
0 |
0 |
|
SR12 |
Action |
- |
- |
- |
12/04/22 |
0 |
1 |
|
|
Limit |
- |
- |
- |
- |
0 |
0 |
|
SR15 |
Action |
- |
- |
- |
- |
0 |
0 |
|
|
Limit |
- |
- |
- |
- |
0 |
0 |
|
Total |
Action |
0 |
0 |
1 |
3 |
4 |
|
|
|
Limit |
0 |
0 |
0 |
0 |
0 |
|
4.2.24
Avoiding false alarm notification was considered in the Event and Action
Plan implementation. For the action
level exceedance on SS recorded on 27 Apr 2022, no exceedance on SS were
recorded at the nearby stations SR5 and SR6 from the marine-based construction
works, these exceedance was non-project related.
4.2.25
After considering the above-mentioned investigation results, it is
concluded that out of 66 action level exceedances on DO, 61 of these
exceedances were due to background contribution as recorded at the control
stations on 14, 16, 18, 20, 22 and 29 April 2022 whereas action level
exceedance on DO recorded at SR9 and SR10 on 27 April 2022 were reviewed with no
exceedance recorded at nearby upstream stations SR5 and SR6 from the location
of marine-based construction works and concluded as non-project related.
4.2.26
Out of the 4 action level and 81 limit level exceedances on turbidity, 2
action level and 49 limit level exceedances on SS were recorded in the
reporting month, 4 action level exceedances on SS were concluded after removing
those false alarm exceedance using the “and“
approach proposed in the baseline report.
Action level exceedance on SS recorded on 27 April 2022 was reviewed
with no exceedance recorded at nearby upstream stations SR5 and SR6 from the
location of marine-based construction works and concluded as non-project
related.
MONITORING METHODOLOGY
4.3.1
The weekly site audit to be carried out by the ET should include
checking whether good site practices are being properly implemented by the
Contractor.
4.3.2
Impact monitoring of the transplanted Aquilaris
sinensis at holding nursery and one retain tree of Aquilaris sinensis
in SSWSTW Project Site, establishment and after-establishment caring
measures of the compensatory mixed woodland to ensure the affected tree would
not be affected by any unacceptable construction works. The trees would be
treated with establishment works immediately after transplanting.
PARAMETERS
MONITORED
4.3.3
The extent of the work site boundaries should be checked by the ET
during the weekly site audit. Any
disturbance by the Contractor outside the works area especially any damage to
the vegetation and surrounding habitats outside the Project area shall be
reported to ER and IEC.
4.3.4
To identify any unacceptable construction works for the trees of Aquilaris
sinensis during transplanting, establishment and after-establishment caring
measures of the compensatory mixed woodland.
MONITORING
LOCATION
4.3.5
The original location of Aquilaris sinensis is at SSWSTW (Figure
2.5). The tree is transplanted to temporary holding nursery (Figure
2.6) for establishment.
4.3.6
Retain tree of Aquilaris sinensis at SSWSTW Project Site.
MONITORING
DATE, TIME, FREQUENCY AND DURATION
4.3.7
The recommended good site practices to be audited once every week as
part of the site audit programme. The weekly site audit to be carried out by
the ET includes checking whether good site practices are being properly
implemented by the Contractor. Results are recorded in Weekly Environmental
Site Audit Checklist.
4.3.8
Monitoring programme for post-transplantation will be conducted once per
month (26 April
2022).
MONITORING
RESULTS
4.3.9
Results and findings of site audit in this reporting month are listed in
Table 3.3.
4.4.1 The quantities of waste for disposal in the
Reporting Period are summarized in Table 4.6. The Monthly Summary Waste Flow
Table is shown in Appendix
4.5.
Table 4.8 Summary of
Quantities of Waste Material (as of April 2022)
|
Waste Type |
Quantity this month |
Quantity (the end of last month) |
Cumulative Quantity-to-Date |
|
Hard Rock and Large Broken Concrete (Inert) (in ‘000m3) |
0 |
0 |
0 |
|
Reused in this Contract (Inert) (in ‘000m3) |
0 |
0 |
0 |
|
Reused in other Projects (Inert) (in ‘000m3) |
0 |
0 |
0 |
|
Disposal as Public Fill (Inert) (in ‘000m3) |
0.62390 |
2.51320 |
6.37295 |
|
Metals (in ‘000kg) |
0.00450 |
1.55 |
1.56170 |
|
Paper / Cardboard Packing (in ‘000kg) |
0.04600 |
0 |
0.07048 |
|
Plastics (in ‘000kg) |
0.00350 |
0 |
0.01046 |
|
Chemical Wastes (in ‘000kg) |
0 |
0 |
0 |
|
General Refuses (in ‘000kg) |
9.74 |
34.82 |
276.11 |
*:
Further
breakdown into sub-group if considered applicable;
*: Please also
provide daily dumping report for our records.
*: Delete as
appropriate
5.1.1
No environmental
complaint, notification of summons and successful prosecution regarding
construction works was recorded in the reporting period.
5.1.2
Cumulative statistic on complaints and successful prosecutions are
summarized in Table 5.1 and Table 5.2 respectively.
Table 5.1 Cumulative
Statistics on Complaints
|
Reporting
Period |
No.
of Complaints |
|
April
2022 |
0 |
|
Project
commencement to the end of last reporting month |
- |
|
Total |
0 |
Table 5.2 Cumulative
Statistics on Successful Prosecutions
|
Environmental
Parameters |
Cumulative
No. Brought Forward |
No.
of Successful Prosecutions this month (Offence Date) |
Cumulative
No. Project-to-Date |
|
Air |
- |
0 |
0 |
|
Noise |
- |
0 |
0 |
|
Water |
- |
0 |
0 |
|
Waste |
- |
0 |
0 |
|
Other |
- |
0 |
0 |
|
Total |
- |
0 |
0 |
6.1.1
In coming reporting 3 months, the scheduled construction activities are
listed as follows:
·
Maintenance works for tree in holding nursery and Site
·
Excavation and site formation works at San Shek Wan Sewage Treatment
Works (SSWSTW) and Pui O Sewage Pumping Station (POSPS).
·
Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen
·
Excavation of Trial Pit at Chi Ma Wan Road and South Lantau Road
·
Pre-drilling works at Pui O beach road
·
Preparation
of HDD works
·
Installation
of silt curtain and construction of temporary marine platform
6.1.2
The scheduled construction activities and the recommended mitigation
measures for the coming 3 months are listed in Table 6.1. The
major construction activities for the next 3 months are summarized in Three
Months Rolling Programme - May 2021 to Jul 2022 in Appendix
6.1.
Table 6.1 Construction Activities and Recommended Mitigation Measures in Coming Reporting 3
Months
|
Key Construction Works |
Recommended Mitigation Measures |
|
·
Maintenance and establishment works for transplanted trees in holding
nursery. ·
Preservation of existing trees on Project Site ·
Village sewers (excavation, sewer laying, construction of manhole) at
Pui O Lo Uk Tsuen and Chi Ma Wan Beach ·
Trunk Sewers and Rising Mains outside village and to POSPS ·
Construction of POSPS ·
Horizontal directional drilling (HDD) works for SSWSTW land side ·
Retaining wall construction and slope modification works at SSWSTW ·
HDD works at sea side |
·
Provide caring measures for the health, form and structural conditions for
transplant trees including Aquilaris sinensis in holding nursery; ·
Fully implement tree preservation works on site and holding nursery to
ensure compliance of relevant legislation and guidelines stated in EM&A
Manual. ·
Implementation of noise pollution control in accordance with
Construction Noise Mitigation Plan; ·
Dust control during dust generating works; ·
Adopt surface
drainage and sediment control facilities for sewage installation in village
and public roads; ·
Adopt temporary
drainage and sediment control facilities on Site; ·
Vehicle wheel-washing and body washing facilities should be provided
at the site entrance; ·
Regular water spraying on exposed area; and ·
Proper waste handling, recycling and storage. ·
Silt curtains
should be installed to surround the marine dredging area in accordance with
Silt Curtain Deployment Plan. |
7.1.1
No action or limit level exceedance was recorded in construction noise
level in this reporting period.
7.2.1
Marine-based construction works commenced on 19 April 2022, water
quality monitoring was commenced on 12 April 2022. 66 action level exceedances on DO, 4 action
level and 81 limit level exceedances on turbidity, 2 action level and 49 limit
level exceedances on SS were recorded in the reporting month.
7.2.2
Out of 66 action level exceedances on DO, 61 of these exceedances were
due to background contribution as recorded at the control stations on 14, 16,
18, 20, 22 and 29 April 2022 whereas action level exceedance on DO recorded at
SR9 and SR10 on 27 April 2022 were reviewed with no exceedance recorded at
nearby upstream stations SR5 and SR6 from the location of marine-based
construction works and concluded as non-project related.
7.2.3
Out of the 4 action level and 81 limit level exceedances on turbidity, 2
action level and 49 limit level exceedances on SS were recorded in the reporting
month, 4 action level exceedances on SS were concluded after removing those
false alarm exceedance using the “and“ approach proposed in the baseline
report. Action level exceedance on SS
recorded on 27 April 2022 was reviewed with no exceedance recorded at nearby
upstream stations SR5 and SR6 from the location of marine-based construction
works and concluded as non-project related.
7.3.1
Maintenance works for transplanted Aquilaris sinensis have
commenced, preservation and protection of retain tree Aquilaris sinensis
at SSWSTW.
7.4.1
No environmental non-compliance was recorded in the reporting month.
7.5.1
There was no particular action taken since no non-compliance was
recorded in the reporting period.
Figure 2.1
Master Layout Plan
Figure 2.2
Contract Layout Plan
Figure 2.3
Locations of Noise Monitoring Station
Figure 2.4
Locations of Water Quality Monitoring Stations
Figure 2.5
Mark up Figure 5.4i extracted from approved EIA
Report (AEIAR-210/2017)
Figure 2.6
Location Plan for Temporary Holding Nursery
Appendix 4.1
Copies of Calibration Certificates
Appendix 4.2
Impact Monitoring Schedule
Appendix 4.3
Noise Monitoring Results and Graphical
Presentations
Appendix 4.4
Marine Water Quality Monitoring Results and
Graphical Presentations
Appendix 4.5
Monthly Summary Waste Flow Table
Appendix 6.1
Three Months Rolling Programme – May 2022 to July
2022